Resources / Construction pipeline

We read the permit record so a market conversation starts from evidence.

Most colocation capacity trades off market. There is no listings feed and no MLS. What there is, in every market that matters, is a public filing trail: a county building permit before a shell goes up, a state air permit before a generator runs. We collect it, count it, and link every line back to the office that issued it.

Our collection

What is in the record today

Every figure on this page is a count of records we pulled ourselves from a government portal. None of it is bought, and none of it is a vendor's marketing claim. Counts are deduplicated, because several counties issue a building record and a zoning record for the same work and counting both would inflate every market on this page by roughly half.

Our collection1000 filings trackedUpdated 4 August 2026

Every capacity figure in the record

9 filings out of 1,000 state a capacity. That ratio is the point: megawatts are the field public records almost never carry, so a permit that names one is worth reading closely. The basis matters as much as the number. A figure the applicant stated for the project is a claim about the build. A generator nameplate is backup plant, and treating it as sellable load is the most common way these records get misquoted.

What the filings are for

Type of workFilingsWhat it tells a buyer
Tenant fit-out527A customer is being installed in a specific hall. The clearest sign a building is filling up
Power and cooling217Generators, substations and switchgear. Power is being solved, which is where dates slip
Type not stated112The record proves the filing exists and names the site, and says nothing about the work
New building109Shell, foundation and site work. Capacity 12 to 24 months out, not capacity now
Expansion or phase35An existing campus is adding to itself, which is usually the fastest space to reach

Every facility we track, market by market

The permit record above says what is being built. It cannot say what is already standing, because a building that opened in 2019 stopped generating filings years ago. That question is answered by the facility database we hold as a Bridgepointe partner, which covers North America and is the second half of this page.

These rows carry no source link, and that difference is deliberate rather than an oversight. The permit counts are public record and you can open every one of them yourself. The facility counts are licensed partner data, which we can show you and cannot hand over, and street addresses are held back for the same reason.

Our collection1,774 facilities15 markets
MarketFacilitiesOperationalUnder constructionPlanned
Northern Virginia31716035122
Dallas-Fort Worth2889928161
Phoenix and Mesa171662183
Chicago169751381
Atlanta153511488
Silicon Valley144115821
Austin and San Antonio107301463
New York Tri-State978917
Richmond80101059
Los Angeles5745210
Hillsboro and Portland5324821
Columbus, Ohio47171317
Houston443329
Indiana and New Carlisle2412012
Des Moines and Council Bluffs231418
All markets we cover1,774840170762

From the Signal facility database, held as a Bridgepointe partner rather than as a public record, so these rows carry no filing link and street addresses are held back. A planned facility is an intention, not a delivery date, and an operational one may be entirely full.

What has been announced, and why it is the softest layer

The permit record says what a jurisdiction has issued. The facility database says what exists. Neither carries megawatts at any scale, because counties rarely publish capacity and Signal does not hold it. Announcements do, which is why they are here, and they are the weakest evidence on this page.

Nobody has to build what they announce. The figure is the one the developer chose to publish, the date moves, and the largest announced project in Northern Virginia is now a void rezoning with no buildings on it. Read this table as a map of intent and ambition, not of supply.

Announced, not filed28 projectsUpdated 4 August 2026
CapacityOperatorMarketProject
2 GWTractAustin and San AntonioCaldwell County park
1.8 GWPowerHouse Data Centers and ProvidentDallas-Fort WorthDFW campus
1.2 GWCloudBurstAustin and San AntonioSan Marcos campus
1 GWECLHoustonTerraSite-TX1
900 MWUndisclosed developerRichmondUpper Magnolia Green, Chesterfield County
600 MWSkybox Datacenters and PrologisAustin and San AntonioPowerCampus Austin, Hutto
550 MWYondrDallas-Fort WorthLancaster campus
360 MWPacific ProvingPhoenix and MesaPacific Proving Technology Park, Mesa
336 MWNTT Global Data CentersNorthern VirginiaGainesville campus
324 MWMicrosoftAtlantaUnion City campus
311 MWBig Digital EnergyDallas-Fort WorthCampus outside DFW
300 MWCorscale Data CentersNorthern VirginiaGainesville Crossing
300 MWRowan DigitalAustin and San AntonioCinco campus, Medina County
240 MWNTT Global Data CentersPhoenix and MesaMesa campus
220 MWSTACK InfrastructureDallas-Fort WorthDallas campus
200 MWIron MountainRichmondWhite Oak Technology Park, Henrico County
192 MWVantage Data CentersColumbus, OhioOH1, New Albany
108 MWGrindcapAtlantaBells Ferry Road, Marietta
108 MWAligned Data CentersHillsboro and PortlandPDX-01 and PDX-02, Hillsboro
100 MWAligned Data CentersChicagoORD1, Northlake
97 MWGoodmanSilicon ValleyWest Trimble Road, San Jose
48 MWStream Data CentersDallas-Fort WorthWilmer II
36 MWSTACK InfrastructureChicagoCHI02, Elk Grove Village
32 MWGoodman GroupLos AngelesLAX01, Vernon
32 MWDigital RealtyLos AngelesPacific Boulevard, Vernon
20 MW5C Data CentersPhoenix and MesaPhoenix facility
17 MWViVaVerse SolutionsHoustonViVa Center microgrid
10 MWElement CriticalHoustonHouston One expansion

No capacity figure has been announced in New York Tri-State, Des Moines and Council Bluffs, Indiana and New Carlisle. That is not a gap in our collection. Hyperscale self-builds publish dollars and square feet, and New York has paused permitting above 50 MW outright. Each market page says which applies.

How to read a permit like a buyer

The value is not in the total. It is in which kind of filing is moving, because the four types answer completely different questions.

Tenant fit-out

Someone is installing a customer in a named hall of a building that already stands. This is the only filing type that says a specific building is filling up, and it is the one worth acting on this quarter.

Power and cooling

Generators, substations, switchgear. Power is the thing that slips dates, so a substation filed alongside a campus means the hard problem was solved early. No filing means it was not.

New building

Shell, foundation, site work. Real capacity, 12 to 24 months out. Useful for planning a second site, useless for a requirement that lands this year.

Expansion or phase

A campus adding to itself. Usually the fastest space to reach, because the power, the fiber and the operating staff are already there.

What this record cannot tell you

It is worth being blunt about the limit, because a number quoted out of context is a liability in a sales conversation.

  • A permit is not availability. No public document anywhere discloses what is contractible at a named building. That number comes from an operator call, and it changes weekly.
  • A permit is not megawatts. Most jurisdictions publish square footage and valuation. Very few publish IT load, and the ones that publish generator ratings are describing backup, not capacity.
  • The applicant is usually not the operator. Filings name engineers, general contractors and single-purpose holding companies. Only the ones on the record by a recognizable name are published as operators here, and the rest are counted as unnamed.
  • Coverage is uneven by design. Some counties publish a live permit feed, some publish nothing machine readable at all. We collect where a source exists and say so where one does not, rather than filling gaps with estimates.
What this is actually for

It is proof of ground truth, not a product. If we can show you what was filed in your market last month and who filed it, the question of whether we know the market answers itself. The space itself still comes from picking up the phone, because that is the only place it exists.

Markets we do not collect filings in yet

Chicago, Silicon Valley, Hillsboro and Portland, and the New York Tri-State area carry the facility layer but no permit collection. Their construction record comes from published research instead, which is stated on each page. A market gets a permit collector when a probe shows the portal is machine readable, publishes a usable work description, and yields real filings from the last 24 months. Sources that fail that test are written down as dead ends rather than quietly retried.

The nearest thing to a listings answer is still a call. If your requirement is in a market below, we will tell you what the record shows and what it does not, and then go ask the operators the part that is not written down anywhere.

Market intelligence

Ask what we are seeing in your market this month.

The filing record tells you where construction is happening. A scout tells you which of it is reachable at your size, on your date, at a price worth signing.