Market guide / Salt Lake City

Utah's data centers are building their own power plants, because the utility could not serve them.

Rocky Mountain Power could not supply the full amount Novva needed until 2031, and even then it was not guaranteed. So Novva ran generators under air permits that capped its diesel units at 42 hours a year, and then applied to build 200 megawatts of its own gas generation. Senate Bill 132 turned that improvisation into state policy: a load of 100 megawatts or more negotiates its own large load contract, the utility has 90 days to say whether it can serve it, and if it cannot, the customer may go and find its own supply.

Market profile

Why Salt Lake City is a market at all

Salt Lake City sits in a genuinely useful place on the map. It is the natural western interior position: far enough from the coast to be a real disaster recovery pair for Silicon Valley or Los Angeles, close enough on fibre to serve both, and outside the seismic and wildfire exposure profile that makes California underwriters nervous. Power has historically been cheap, the climate allows a lot of free cooling, and land along the Wasatch Front is available in a way that coastal land is not.

What makes it unusual is how flat the interconnection map is. Most markets have one dominant carrier hotel that everything else orbits. This one does not: no single building holds even a quarter of the metro's network presences, and the top half dozen facilities are within striking distance of each other. That is a mixed blessing. It means real competition between operators, and it means no single building where everyone you need to reach already is.

The constraint here is not land, zoning or fibre. It is electricity, and it has been for several years.

How to read the numbers below

Every megawatt figure on this page is one of two things: capacity a builder says it delivered, or generation a builder has been permitted to build. Those are different, and neither one is space you can lease. Nothing published anywhere discloses contractible capacity in this metro. A number on a brochure is a marketing position, not an inventory.

Who is actually plugged in across Salt Lake City and the Wasatch Front

A building existing and a building being connected are different facts, and only one of them decides whether your traffic can get where it needs to go cheaply. These figures come from PeeringDB, which the network operators themselves maintain, so every row below links to the building's own public entry.

Public record23 buildings listed193 network presences
MeasureFigureWhat it means
Buildings listed23Registered in PeeringDB across Salt Lake City and the Wasatch Front, by 12 operators
Buildings with a network present203 carry no network presence, which usually means single tenant or simply unregistered
Network presences193Counted per building, so a carrier in three buildings counts three times
Internet exchange presences22Where you can reach many networks through one port instead of many cross-connects
Carrier presences12The physical transport choice you can buy without leaving the building
In the densest building20%DataBank Salt Lake City (SLC1) holds 38 of the market's network presences

The most connected buildings here

NetworksBuildingOperatorExchangesCarriers
38DataBank Salt Lake City (SLC1)DataBank, Ltd.33
25DataBank Salt Lake City (SLC2)DataBank, Ltd.22
25Flexential - Salt Lake City/Downtown (SLC04)Flexential Corp.31
24FIBERSTATE Salt Lake City (SLC1)FIBERSTATE10
18EdgeConneX Salt Lake City (EDCSLC01)EdgeConneX Inc.31
15DataBank Salt Lake City (SLC3)DataBank, Ltd.21
10Level(3) Salt Lake CityLumen Technologies Inc21
6Aligned Salt Lake (SLC-01)Aligned Data Centers00

From PeeringDB, which is maintained by the network operators present in these buildings rather than by the landlords, which is what makes it worth more than a directory. Two limits. Entries are voluntary, so a building showing no networks may be single tenant or may simply never have registered. And a network being present says nothing about whether the building has space, power or a price for you: that is still a call.

What has been announced in Salt Lake City and the Wasatch Front

Announcements are not filings. Nobody has to build what they announce, the figure is the one the developer chose to publish, and the date moves. They are here because megawatts are what a requirement is measured in, and because the size of what is coming changes who will take your call. Every figure below was read on the page it links to.

Announced, not filed2 projectsLargest: 200 MW
CapacityOperatorProjectWhat was announced
200 MWNovva Data CentersWest Jordan flagship campusA 100 acre campus with over 1.5 million square feet, served by an on-site 200 MW substation, which Novva calls the largest data center in Utah. Operator published capacity
200 MWQTS Data CentersEagle Mountain gas plantA 20 acre, 200 megawatt gas plant approved by the Eagle Mountain City Council to power the campus rather than capacity anyone can lease. On-site generation approved, not data center capacity
Read this before quoting any of it

Read the second row carefully, because it is the whole market in one line. It is a power station, not a data hall. Utah developers are building their own generation because the utility cannot serve them: Rocky Mountain Power could not supply the full amount Novva needed until 2031, and even then it was not guaranteed, so Novva ran diesel and gas generators under Utah air permits that capped the diesel units at 42 hours a year. Senate Bill 132 then made that the official route, letting a customer with 100 megawatts or more of load negotiate a separate large load contract, giving the utility 90 days to say whether it can serve the request, and allowing the customer to go find its own supply if the answer is no. Read the reporting.

Announced capacity is collected by hand from trade reporting and company statements, and each figure links to the report it came from. It is kept apart from the permit record above and never added to it: one is a document a jurisdiction issued, the other is a plan a company published. Neither is availability.

Announced capacity is collected by hand from trade reporting and company statements, and every figure links to the report it came from and was read in that report before it was written down. It is never added to the interconnection count above: one is a plan a company published, the other is a building a network registered itself into. Neither is availability.

Power is the whole story, and the answer was to stop asking the utility

Rocky Mountain Power serves most of the Wasatch Front and has not been able to keep up with data center demand. Novva, which operates the largest campus in the state, was told the utility could not provide the full amount of energy it needed until 2031, and that even that was not guaranteed. Novva's response was to build its own generation: a natural gas plant intended to supply 200 megawatts, which would itself take until 2027, backed in the meantime by a fleet of diesel and gas fired generators.

Those generators run on a permit, not on demand. The Utah Division of Air Quality capped the emissions volume of the gas fired units and limited the diesel units to 42 hours a year. If you are evaluating a Utah building whose power story includes on-site generation, that permit condition is a hard operational ceiling and it belongs in your due diligence, not in a footnote.

Senate Bill 132 then rewrote the rules around all of this. It modifies Rocky Mountain Power's duty to serve, defines a large load as 100 megawatts or more within five years, and lets such customers negotiate separate large load contracts. The utility gets 90 days to evaluate a large load request and determine whether it can meet the demand without significant investment. If it cannot, the law allows the customer to go and source its own energy, either connected to the grid or entirely separate from it behind the meter. Utah's argument for this is that it protects existing ratepayers, and the state points to a projection that for every new gigawatt of data center load, rates could fall as much as 2 percent.

In February 2026 Governor Cox, legislative leadership and Rocky Mountain Power announced the first major agreement under that law, part of the state's Operation Gigawatt programme. The utility said it moved from introductory conversations to delivering a firm large load request in under a year, with the data center customer fully covering the costs of service. That is a fast timeline by national standards. It is also a bespoke, negotiated arrangement rather than a published queue you can join.

What this means if you are buying colocation rather than building

Almost none of the above applies to you directly, and all of it applies to your operator. A colocation tenant taking a cage or a few hundred kilowatts is nowhere near the 100 megawatt threshold and will never negotiate a large load contract. But the building you are moving into is downstream of one, and its power supply may be partly or wholly self-generated. That changes the questions worth asking: not just how much power is available, but where it comes from, what permit governs it, and what happens in the hours when the permitted generation is unavailable.

Where the market actually is, submarket by submarket

Downtown Salt Lake City

The interconnection core, such as it is, with DataBank, Flexential, EdgeConneX and Lumen all holding downtown positions. This is where the carriers and the exchanges are, and it is the right answer for network-led requirements and for smaller enterprise footprints.

Bluffdale and the Point of the Mountain

The corridor between Salt Lake and Utah counties, where several of the newer purpose-built facilities sit on cheaper land with better power access than downtown. It is a twenty-five minute drive from the city and a different set of municipal politics.

West Jordan

Novva's flagship campus, a hundred acres with an on-site 200 MW substation, is the largest single concentration of capacity in the state. It is a wholesale and large-enterprise environment rather than a retail colocation one, and it is where the state's self-generation story is being written.

Utah County and Eagle Mountain

Forty miles south, and where the very large announcements land. QTS has approval from the Eagle Mountain City Council for a twenty acre, 200 megawatt gas plant to power its campus. Latency to Salt Lake City is immaterial; jurisdiction, incentives and community politics are not.

When this market is right, and when it is the wrong choice

Salt Lake City is the right answer for a western disaster recovery position, for enterprises headquartered along the Wasatch Front, and for workloads that want the interior west without Phoenix's heat or Denver's altitude. The flat interconnection map means you can negotiate: several operators can plausibly serve the same requirement, which is not true in most markets this size.

It is the wrong choice if you need a deep peering fabric. The whole metro carries fewer network presences than a single building in Seattle or Silicon Valley, and if your requirement is network-led rather than compute-led, this market will not satisfy it.

It is also the wrong choice if your power requirement is large and your date is fixed. The state's own legislation exists because the utility could not serve large loads on demand, and a bespoke negotiated contract is not a schedule you can hold anyone to. Two physical factors belong in the same conversation: the Wasatch Fault runs along the eastern edge of this valley, and the valley's winter inversions have periodically put it among the worst air quality in the country, which is precisely the context in which generator permits get tightened. Ask for the seismic design basis of the specific building and the current air permit conditions on any on-site generation, rather than the operator's regional narrative about either.

How to actually negotiate on the Wasatch Front

The first question is where the electricity in this building comes from. Ask whether the load you are being sold is served by Rocky Mountain Power under an existing energised service, by on-site generation, or by a combination, and get the answer in writing. If any of it is on-site, ask for the current Utah Division of Air Quality permit conditions, including the annual runtime cap on diesel units, and ask what happens to your load when that cap is reached. Ask whether the operator has a large load contract under Senate Bill 132 and, if the building is still being built out, what the utility said inside its 90 day evaluation window. Ask for the building's own network and carrier list rather than a metro figure, because this market is flat and the difference between two buildings a mile apart is real. Confirm which county and city you are actually in, because Eagle Mountain, Bluffdale and Salt Lake City are three different regulatory environments and all three get marketed as Salt Lake. And ask for the seismic design basis of the structure, in writing, from the operator rather than from a brochure.

Salt Lake City search

Find out what is actually deliverable in Salt Lake City.

A scout can test this market against your power, density and date, tell you which buildings carry the networks you need, and price it beside the alternatives so the comparison is honest.