Market guide / Ashburn, Virginia

Ashburn data center space: what capacity, cost, and availability really mean.

Ashburn offers unmatched network density and operator choice, but available power is scarce. Start with the requirement, not a list of buildings.

Ashburn and Northern Virginia colocation market
Updated July 2026

Why Ashburn is still the first market many teams check

Ashburn sits inside Northern Virginia's unusually dense data center and fiber ecosystem. For a buyer, that can mean broad carrier choice, established cloud connectivity, deep operator experience, and multiple ways to design for redundancy. It is especially useful when latency, interconnection, and access to East Coast users matter.

That depth does not make capacity easy to secure. CBRE reported that Northern Virginia reached 4,182 MW of inventory in Q1 2026, yet only 10.8 MW was available. The market vacancy rate was 0.3%. Those figures cover the wider Northern Virginia market, but they capture the practical Ashburn problem: new supply is being absorbed almost as quickly as it arrives.

The buying implication

A requirement with a hard date should be tested against live power, density, and network fit early. A building can have empty floor area and still lack the right deliverable power block.

Market figures: CBRE Global Data Center Trends 2026. Loudoun County also describes Data Center Alley as the world's largest concentration of data centers on its official data center page.

kW and MW, in plain English

Colocation capacity is usually discussed in committed electrical power, not square feet. One megawatt equals 1,000 kilowatts. The amount you need depends on the equipment load, redundancy design, rack density, cooling approach, and expected growth.

50 to 250 kW

A smaller enterprise footprint, disaster recovery environment, edge deployment, or a few cabinets through a private cage. Facility and contract minimums matter.

250 to 500 kW

A material enterprise deployment. This is also the requirement band used in CBRE's published Northern Virginia asking-rate benchmark.

500 kW to 2 MW

A larger private suite or phased deployment. Ramp schedules, adjacent expansion, and power-delivery dates become central commercial terms.

2 MW and above

Wholesale-scale capacity. Fewer facilities can deliver the block, and longer planning horizons or alternative Northern Virginia locations may be necessary.

What drives price in Ashburn

A monthly price per kW is useful for planning, but it is not the whole deal. Two quotes can use the same headline rate and still produce very different total costs.

  • Size and commitment: larger power blocks can receive better unit economics, but they carry a larger minimum commitment.
  • Term and ramp: longer terms can improve pricing. A staged power ramp can reduce early spend if the operator accepts it.
  • Density and cooling: high-density racks, liquid cooling, or containment can narrow the facility set and add engineering costs.
  • Redundancy: distribution design, backup architecture, and maintenance expectations influence both fit and cost.
  • Network: cross-connects, carrier ports, cloud on-ramps, and diverse entrances are often quoted separately.
  • One-time charges: installation, cages, cabinets, cabling, migration support, and custom security can materially change year-one spend.
  • Escalators and renewals: annual increases and renewal language can outweigh a small difference in the opening rate.

What "available" should mean in your shortlist

A useful availability answer includes the quantity, delivery date, density, redundancy, physical layout, expansion path, and any work required before service starts. A broad statement such as "we have capacity in Ashburn" is not enough to build a project plan.

  1. Confirm the initial committed kW and expected ramp by date.
  2. Document the power density required per cabinet or row.
  3. Define network carriers, cloud connections, route diversity, and cross-connect count.
  4. Set compliance, physical security, access, and support requirements.
  5. Identify future expansion and whether adjacent capacity is contractual or only aspirational.
  6. Normalize recurring and one-time charges across every option.

When Ashburn may not be the right answer

Ashburn can be the strongest ecosystem and still be the wrong project fit. If the deployment needs a very large contiguous block, an aggressive delivery date, a different risk profile, or better unit economics than the current market supports, nearby or secondary markets deserve a parallel look. The comparison should include latency, network cost, staff access, workload dependencies, and migration risk, not power price alone.

Shortlist rule

Do not trade away a business-critical requirement just to keep an Ashburn address. Use Ashburn when the ecosystem creates real value for the workload.

Northern Virginia by the numbers

Ashburn sits inside the largest data center market on earth, and the scale is worth stating precisely because it explains both the depth of choice and the difficulty of securing capacity.

Sourced figuresLatest available: Q1 2026Source: CBRE
MeasureFigureContext
Total inventory4,182.0 MWLargest market in the world, up 1,135.9 MW year over year
Overall vacancy0.3%An all-time low for the market
2026 supply already committed96%Preleasing now extends into 2027 and beyond
Interconnect queue4 to 6 yearsDominion's batching process governs new large-load dates
Industrial power$0.095 to $0.13/kWhAmong the higher US bands, and usually passed through
Data center land$3.5M to $4.0M/acreBest powered sites have exceeded $8M per acre

Sources: CBRE on Northern Virginia extending its lead and CBRE Global Data Center Trends 2026. Land is anchored on two disclosed 2026 trades: Amazon at about $427.3M for roughly 122 acres, and Starwood Capital at $166.8M for 42 acres in Fairfax County. Power bands and queue lengths vary by substation and by how load is staged, so confirm both for a specific site.

The submarkets, and why they are not interchangeable

Treating Northern Virginia as one market is the most common planning error. Price, availability and delivery date differ enough between corridors that the choice of submarket is often a bigger decision than the choice of provider.

Ashburn and Data Center Alley

Loudoun County. The densest concentration of exchange points, carrier cross-connects and cloud on-ramps anywhere. Highest pricing and tightest availability, and CBRE notes zoning and entitlement limits now constrain expansion here.

Sterling and Dulles

Immediately adjacent, sharing much of the same fiber and cloud access. Usually the first alternative when an Ashburn postcode is preferred rather than required.

Manassas and Prince William

Campus-scale development and larger contiguous blocks. Entitlement friction is a genuine risk, so verify the delivery path rather than the announced pipeline.

Fauquier, Culpeper, Stafford, Spotsylvania

The emerging outer ring CBRE has identified as new areas of activity. Land and power on timelines the core cannot match, at the cost of drive time and carrier depth.

Emerging submarket activity and the zoning constraints in Loudoun and Prince William per CBRE on record-low vacancy and emerging Northern Virginia growth areas.

Why the power queue decides your project plan

In Northern Virginia the scarce resource is not land, buildings or capital. It is an energized connection, and the wait for one is long enough to govern the entire schedule.

Dominion Energy's transmission upgrades support record absorption, but its batching system continues to extend delivery timelines for new projects. A four to six year horizon for new large load means the practical question is not whether a provider has space, but whether they already hold energized capacity or a firm position in the queue. Those are very different products sold at similar-sounding rates.

What to ask before you shortlist

Is this capacity energized today? If not, what is the contractual power date, which substation serves it, and what are the remedies if the date slips? A lower rate with a 2030 date is not competitive with a higher rate available in 2027, and the difference will not appear in a rate comparison.

What Northern Virginia gives you that other markets do not

The premium here buys specific, measurable things. It is worth paying when the workload uses them, and worth avoiding when it does not.

  • Interconnection density: more exchange points, carrier cross-connects and cloud on-ramps than almost any location globally, which lowers the cost and latency of reaching networks and clouds.
  • Operator choice: enough competing facilities that a normalized bid process produces real price tension, even in a tight market.
  • Redundancy design options: multiple diverse buildings and entrances within a short distance, which makes active-active and campus-diverse architectures practical.
  • Deep operational labor pool: mature staffing for remote hands, smart hands and migration support.
  • Predictable engineering: operators here have delivered high-density and liquid-ready builds repeatedly, which reduces execution risk on unusual requirements.

If your workload is latency-sensitive, interconnection-heavy or needs East Coast user proximity, those advantages are real and the pricing follows from them. If it is a batch or archival workload that simply needs cheap, reliable megawatts, you are paying for capabilities you will not use. The pricing benchmarks page shows what the alternative markets cost on land, power and interconnect queue.

The local politics are now part of the risk

Data centers are a large enough share of the Northern Virginia tax base that public policy is a live variable in a long-term plan. In Loudoun County, data centers are expected to contribute nearly half of local property tax revenue in 2026. That fiscal dependence cuts both ways for a tenant.

On one hand, local governments have a strong incentive to keep the sector healthy. On the other, concentration has produced real zoning and entitlement resistance in Loudoun and Prince William, which CBRE cites as limiting the market's ability to capture demand. For a buyer, the practical effect is that pipeline announcements in these counties deserve more scepticism than elsewhere, and a firm delivery commitment matters more than a large announced pipeline.

What has been announced in Northern Virginia

Announcements are not filings. Nobody has to build what they announce, the figure is the one the developer chose to publish, and the date moves. They are here because megawatts are what a requirement is measured in, and because the size of what is coming changes who will take your call. Every figure below was read on the page it links to.

Announced, not filed2 projectsLargest: 144 MW
CapacityOperatorProjectWhat was announced
144 MWSTACK InfrastructureLoudoun County CampusTwo two-story buildings of 72 MW each on 122 acres in greater Ashburn, near Dulles, drawing on an on-site substation. The figure is the operator's own and appears identically in its press release, its campus brochure and the trade coverage that followed
114 MWEdgeCore Digital InfrastructureAshburn campus, on Maries Road and Moran Road in SterlingReports disagree and the row carries the smaller. The current plan is described as roughly 685,000 SF and 114 MW of critical IT load across two sites under two miles apart, with first delivery in 2026. EdgeCore's own earlier description of the campus was 720,000 SF supporting 144 MW. Both are in circulation, and the difference is a plan that changed rather than a number anyone misread. Critical IT load across two buildings, the lower of two published figures
Read this before quoting any of it

Prince William County has its own page, and the figures for Gainesville, Haymarket and Manassas moved there on 13 August 2026. Nothing was lost: NTT's Gainesville campus and Corscale's Gainesville Crossing are counted on that page rather than this one, so no building is counted twice. The county is still Northern Virginia in every buyer's usage, and the reason it sits apart is that the largest project ever announced in it is now dead, which needed the room to explain. See that page.

Announced capacity is collected by hand from trade reporting and company statements, and each figure links to the report it came from. It is kept apart from the permit record above and never added to it: one is a document a jurisdiction issued, the other is a plan a company published. Neither is availability.

Every Northern Virginia facility we track

317 data centers across Northern Virginia, from our verified inventory. It is the layer that says whether a building exists yet, which no permit record answers directly.

Our collection317 facilities55 operators
StatusFacilitiesWhat it means for a search
Operational160Standing and running. The only layer that can hold a requirement this year
Under construction35Steel is up. Reachable for a date 6 to 18 months out, and usually pre-leasing now
Planned122Announced or entitled, not yet built. Treat every date on these as a forecast
Building area on file87,332,902 SFAcross the 249 facilities where a size is recorded, of 317
Largest single building2,294,300 SFCorscale, Gainesville

Operators with the most facilities here: Digital Realty (53), STACK Infrastructure (27), Equinix (24), CloudHQ (22), QTS (16), CyrusOne (15), NTT Global Data Centers (13), Iron Mountain Data Centers (10), Rowan Digital Infrastructure (9), TA Digital Group (9).

Where they cluster: Ashburn (101), Sterling (68), Manassas (55), Culpeper (10), Gainesville (10), Chantilly (9).

The largest buildings coming to this market

157 facilities here are under construction or planned. These are the ten largest by floor area, and a size on file is not a promise of a delivery date.

OperatorStatusBuilding sizeWhere
NTT Global Data CentersUnder Construction2,000,000 SFGainesville, VA
PointOne Development Corp.Planned1,800,000 SFRemington, VA
TA RealtyPlanned1,500,000 SFLeesburg, VA
CloudHQUnder Construction1,435,000 SFAshburn, VA
Aligned Data CentersUnder Construction1,300,000 SFFrederick, MD
PowerHouse Data CentersPlanned1,131,350 SFDulles, VA
CloudHQUnder Construction800,000 SFManassas, VA
PowerHouse Data CentersPlanned796,844 SFSterling, VA
DataBankPlanned795,700 SFCulpeper, VA
Digital RealtyUnder Construction794,000 SFSterling, VA

From our verified inventory rather than from a public record, so these rows carry no filing link and street addresses are held back. These buildings are verified, which is not the same as their space being available: every facility above may be full, pre-leased, or closed to your size. Finding out is a call, not a lookup. See what a verified building does and does not mean.

Who is actually plugged in across Northern Virginia

A building existing and a building being connected are different facts, and only one of them decides whether your traffic can get where it needs to go cheaply. These figures come from PeeringDB, which the network operators themselves maintain, so every row below links to the building's own public entry.

Public record72 buildings listed944 network presences
MeasureFigureWhat it means
Buildings listed72Registered in PeeringDB across Northern Virginia, by 28 operators
Buildings with a network present5913 carry no network presence, which usually means single tenant or simply unregistered
Network presences944Counted per building, so a carrier in three buildings counts three times
Internet exchange presences74Where you can reach many networks through one port instead of many cross-connects
Carrier presences72The physical transport choice you can buy without leaving the building
In the densest building55%Equinix DC1-DC15,DC21-DC22 - Ashburn holds 517 of the market's network presences

The most connected buildings here

NetworksBuildingOperatorExchangesCarriers
517Equinix DC1-DC15,DC21-DC22 - AshburnEquinix, Inc.814
84CoreSite - Reston (VA1)CoreSite65
36DataBank Ashburn (IAD1)DataBank, Ltd.22
25RagingWire VA1 - NTTRagingWire Data Centers - NTT12
22CoreSite - Reston (VA2)CoreSite32
16CoreSite - Washington,DC (DC1)CoreSite33
16Digital Realty IAD 39 (44274 Round Table)Digital Realty33
15CoreSite - Reston (VA3)CoreSite33

From PeeringDB, which is maintained by the network operators present in these buildings rather than by the landlords, which is what makes it worth more than a directory. Two limits. Entries are voluntary, so a building showing no networks may be single tenant or may simply never have registered. And a network being present says nothing about whether the building has space, power or a price for you: that is still a call.

What the public construction record shows in Northern Virginia

Loudoun County building permits plus Virginia air permits in the Northern Virginia counties. Every figure below is a count of filings we collected ourselves, and every row links to the record it came from.

Our collectionLatest filing: 2 September 2026651 filings tracked
MeasureFigureWhat it means
Filings we track651Deduplicated. Across 2 sources, April 2001 to September 2026
Filed in the last 12 months293The live rate of construction activity, which is the number that moves
Tenant fit-out filings484A customer is landing in a named building. The strongest signal in the set
New building filings75Shell and site work, which is capacity two years out, not now
Distinct addresses139Separate sites in the record, not separate buildings
Largest capacity in the record96 MWStated on 6 of 651 filings. Capacity is rarely published, so this is a floor, not a market total
Largest floor area filed2,242,904 SFOne permit, not a campus total. Floor area is published far more often than capacity
Operators we can name1448 of 651 filings name a recognizable operator. The rest name an engineer, a builder or a holding company

Operators appearing by name: Amazon Web Services (19), QTS (6), Vantage Data Centers (5), Equinix (4), STACK Infrastructure (3), EdgeCore (2), Sabey (2), CyrusOne (1).

The filings that state a capacity

Most permits never mention megawatts. These do, and the basis matters: a figure the applicant stated for the project is a different claim from a generator nameplate, which is backup plant rather than sellable load.

The most recent filings on the record

FiledNamed on the filingWhat it saysType
2 September 2026Not an identifiable operatorData Center Tenant Fitout Construction Phase 12 - Data HallTenant fit-out
2 September 2026Not an identifiable operatorData Center Tenant Fitout Construction Phase 11 - Data HallTenant fit-out
2 September 2026Not an identifiable operatorData Center Tenant Fitout Construction Phase 10 - Data HallTenant fit-out
2 September 2026Not an identifiable operatorData Center Tenant Fitout Construction Phase 09Tenant fit-out
2 September 2026Not an identifiable operatorData Center Tenant Fitout Construction Phase 08Tenant fit-out
31 August 2026Not an identifiable operatorInterior fit-up for building owner Data Center Accessory Office Use, approximately 2,832 SFTenant fit-out
27 August 2026Not an identifiable operatorTenant office & storage fit out for data hall tenant.Tenant fit-out
24 August 2026Not an identifiable operatorExisting Data Center. Scope Of Work: Replacement Of All Rooftop Up-Blast Exhaust Fans Utilizing Existing Roof Curbs, Al...Tenant fit-out

Collected from Loudoun County LandMARC permit records and Virginia DEQ air permit records. A permit proves that construction is happening. It does not prove that space is available, and no public filing anywhere discloses what is contractible at a named building. That answer comes from an operator call, which is the part we do by hand. See how we verify capacity.

Next step

Turn the requirement into a realistic Ashburn budget.

Use the open calculator for a planning range, or bring a scout the actual timeline and power profile for a live market check.