Why Richmond exists as a data center market at all
Richmond is a hundred miles south of Ashburn, on the same Dominion Energy system, with land that costs a fraction of Loudoun County's and a power queue that was, for a while, considerably shorter. When Northern Virginia's constraint stopped being land and started being electricity, developers went looking for the nearest place with the same utility and fewer neighbours. That place is Richmond.
It is a genuine market rather than a spillover story, because the anchor was already here. White Oak Technology Park in eastern Henrico County has hosted large-scale computing since the semiconductor era, and the fiber that follows Interstate 95 gives Richmond a real path north to Ashburn and south to the Carolinas. What is new is the scale of what has been announced on top of it.
Fifty nine of the eighty facilities we track here are planned rather than built. In Silicon Valley that ratio is twenty one of a hundred and forty four. A market that is mostly planned is a market where your delivery date depends on somebody else's construction schedule, and where the operator quoting you may not yet own the power.
What has been announced in Richmond
Announcements are not filings. Nobody has to build what they announce, the figure is the one the developer chose to publish, and the date moves. They are here because megawatts are what a requirement is measured in, and because the size of what is coming changes who will take your call. Every figure below was read on the page it links to.
| Capacity | Operator | Project | What was announced |
|---|---|---|---|
| 900 MW | Undisclosed developer | Upper Magnolia Green, Chesterfield County | Phased to 2031 or 2033, with Dominion building new high voltage lines to serve it. Announced capacity at full build-out |
| 200 MW | Iron Mountain | White Oak Technology Park, Henrico County | 66 acres, four buildings, more than 1 million SF, over $1bn |
Richmond is the market where the rules changed under the developers. From 10 January 2025 Henrico County requires a provisional use permit for any new hyperscale data center, ending by-right development, and it applies retroactively to rezoned projects that have not yet reached final site plan approval. The conditions attached are specific: a 500 foot tree buffer from homes, limits on generator testing, enclosed noise equipment, closed-loop cooling. Read any Henrico delivery date as a date plus a public hearing. Read the reporting.
Announced capacity is collected by hand from trade reporting and company statements, and each figure links to the report it came from. It is kept apart from the permit record above and never added to it: one is a document a jurisdiction issued, the other is a plan a company published. Neither is availability.
The rules changed under the developers, and that is now the market
On 10 January 2025 Henrico County ended by-right data center development. Every new hyperscale project now needs a provisional use permit, which means a public hearing at the Planning Commission and again at the Board of Supervisors, and the requirement reaches back to rezoned projects that have not yet reached final site plan approval.
The conditions are specific rather than symbolic: a five hundred foot tree buffer between a data center and homes, limits on when generators can be tested, enclosed and screened noise equipment, closed-loop cooling. Every one of those is a cost, and several are a schedule.
For a buyer this matters in one practical way. A Richmond delivery date is a date plus a hearing calendar. Ask which approvals a phase already holds, not which ones the developer expects, and ask what happens to your commencement date if a hearing slips a cycle.
Every Richmond facility we track
80 data centers across Richmond, from the facility database we hold as a Bridgepointe partner. It is the layer that says whether a building exists yet, which no permit record answers directly.
| Status | Facilities | What it means for a search |
|---|---|---|
| Operational | 10 | Standing and running. The only layer that can hold a requirement this year |
| Under construction | 10 | Steel is up. Reachable for a date 6 to 18 months out, and usually pre-leasing now |
| Planned | 59 | Announced or entitled, not yet built. Treat every date on these as a forecast |
| Building area on file | 18,730,812 SF | Across the 40 facilities where a size is recorded, of 80 |
| Largest single building | 3,500,000 SF | PowerHouse Data Centers, Spotsylvania |
Operators with the most facilities here: QTS (31), STACK Infrastructure (9), AVAIO Digital (7), PointOne Development Corp. (6), Iron Mountain Data Centers (5), Chirisa Technology Parks (4), Menlo Digital (4), CleanArc Data Centers (3), PowerHouse Data Centers (2), Tract (2).
Where they cluster: Sandston (36), Ruther Glen (18), Charles City (6), Chester (5), Petersburg (4), Richmond (3).
The largest buildings coming to this market
69 facilities here are under construction or planned. These are the ten largest by floor area, and a size on file is not a promise of a delivery date.
| Operator | Status | Building size | Where |
|---|---|---|---|
| PowerHouse Data Centers | Planned | 3,500,000 SF | Spotsylvania, VA |
| QTS | Planned | 1,193,100 SF | Sandston, VA |
| QTS | Planned | 562,626 SF | Sandston, VA |
| PointOne Development Corp. | Planned | 503,328 SF | Charles City, VA |
| PointOne Development Corp. | Planned | 503,328 SF | Charles City, VA |
| QTS | Planned | 500,430 SF | Sandston, VA |
| CleanArc Data Centers | Planned | 490,400 SF | Ruther Glen, VA |
| CleanArc Data Centers | Planned | 490,400 SF | Ruther Glen, VA |
| CleanArc Data Centers | Planned | 490,400 SF | Ruther Glen, VA |
| Iron Mountain Data Centers | Planned | 478,846 SF | Sandston, VA |
From the Signal facility database, which we hold as a Bridgepointe partner rather than as a public record, so these rows carry no filing link and street addresses are held back. A building existing is not the same as space being available in it: every facility above may be full, pre-leased, or closed to your size. Finding out is a call, not a lookup. See how we verify capacity.
Who is actually plugged in across Richmond
A building existing and a building being connected are different facts, and only one of them decides whether your traffic can get where it needs to go cheaply. These figures come from PeeringDB, which the network operators themselves maintain, so every row below links to the building's own public entry.
| Measure | Figure | What it means |
|---|---|---|
| Buildings listed | 6 | Registered in PeeringDB across Richmond, by 5 operators |
| Buildings with a network present | 4 | 2 carry no network presence, which usually means single tenant or simply unregistered |
| Network presences | 37 | Counted per building, so a carrier in three buildings counts three times |
| Internet exchange presences | 5 | Where you can reach many networks through one port instead of many cross-connects |
| Carrier presences | 3 | The physical transport choice you can buy without leaving the building |
| In the densest building | 59% | QTS Richmond (RIC1) holds 22 of the market's network presences |
The most connected buildings here
| Networks | Building | Operator | Exchanges | Carriers |
|---|---|---|---|---|
| 22 | QTS Richmond (RIC1) | QTS Realty Trust, Inc. | 3 | 3 |
| 11 | Pixel Factory Data Center | Pixel Factory Data Center | 1 | 0 |
| 3 | EdgeConneX Richmond (EDCRIC01) | EdgeConneX Inc. | 1 | 0 |
| 1 | Flexential - Richmond (RIC01/02) | Flexential Corp. | 0 | 0 |
From PeeringDB, which is maintained by the network operators present in these buildings rather than by the landlords, which is what makes it worth more than a directory. Two limits. Entries are voluntary, so a building showing no networks may be single tenant or may simply never have registered. And a network being present says nothing about whether the building has space, power or a price for you: that is still a call.
What the public construction record shows in Richmond
Virginia air permits filed in the Richmond corridor, from Henrico out to Louisa and Caroline. Every figure below is a count of filings we collected ourselves, and every row links to the record it came from.
| Measure | Figure | What it means |
|---|---|---|
| Filings we track | 6 | Deduplicated. One source, August 2024 to June 2026 |
| Filed in the last 12 months | 5 | The live rate of construction activity, which is the number that moves |
| Distinct addresses | 4 | Separate sites in the record, not separate buildings |
| Operators we can name | 2 | 5 of 6 filings name a recognizable operator. The rest name an engineer, a builder or a holding company |
Operators appearing by name: Amazon Web Services (3), QTS (2).
The most recent filings on the record
| Filed | Named on the filing | What it says | Type |
|---|---|---|---|
| 26 June 2026 | Amazon Web Services | Amazon Data Services Inc IAD-450 | Power and cooling |
| 2 March 2026 | QTS | QTS Richmond Data Center | Power and cooling |
| 1 December 2025 | Amazon Web Services | Northeast Creek Technology Campus | Power and cooling |
| 24 November 2025 | Not an identifiable operator | Clean Arc Data Centers - VA-1 Campus | Power and cooling |
| 14 October 2025 | Amazon Web Services | Amazon Data Services Inc - IAD-457 | Power and cooling |
| 30 August 2024 | QTS | QTS Richmond Data Center | Power and cooling |
Collected from Virginia DEQ air permit records. A permit proves that construction is happening. It does not prove that space is available, and no public filing anywhere discloses what is contractible at a named building. That answer comes from an operator call, which is the part we do by hand. See how we verify capacity.
Where the market actually is, submarket by submarket
Eastern Henrico and Sandston
White Oak Technology Park and the ground around it. The oldest large-scale computing footprint in the region, the most operator names on the record, and now the strictest permit path in the market.
Chesterfield County
Where the largest announcements have gone, including a proposal phased toward 900 MW that Dominion is building new high voltage lines to serve. Almost entirely forward-looking.
Ruther Glen and Caroline County
The I-95 corridor between Richmond and Fredericksburg. Cheap land, hyperscale-led, and the part of the market most likely to be sold to you as "Richmond" when it is an hour from downtown.
Downtown and the city core
The interconnection layer, small and network-facing. This is where a modest enterprise requirement is realistically served today, not on the campuses in the headlines.
Power is the reason to be here, and the reason to check twice
Richmond runs on Dominion, the same utility as Northern Virginia, which is both the attraction and the catch. The attraction is a utility with deep data center experience and a genuine transmission plan. The catch is that Dominion's load growth is now a statewide political question, and the same regulatory pressure that reshaped Loudoun's economics reaches Chesterfield and Henrico too.
The questions worth asking are unglamorous and they decide your date.
- Is the power for this phase energized, contracted, or queued, and what is the queue position?
- Does the campus have a dedicated substation, or is it sharing distribution with everything else on the circuit?
- Which transmission work does the delivery date assume, and who is building it?
- What tariff class applies at my size, and does a large-load rider change the economics?
- If a provisional use permit hearing slips, what does my contract say about the commencement date?
When Richmond is the right answer
Richmond fits when you want Northern Virginia's network reach without Northern Virginia's pricing, when you are planning far enough ahead to buy into a phase rather than a standing hall, and when a hundred miles of separation from Ashburn is a resilience feature rather than a latency problem. For a second site to an existing Ashburn primary it is close to ideal: same utility region, same fiber routes, genuinely different local risk.
It is the wrong answer when you need space this quarter. The operational layer here is thin, and a market that is three quarters planned cannot absorb an urgent requirement. If your date is inside twelve months, run Northern Virginia first and treat Richmond as the expansion option you negotiate now and take later.
Price Richmond against Ashburn in the same conversation, and make the Richmond operator quote you a phase with its permit status attached. The discount is real. So is the chance that the building is a year later than the brochure, and only one of those two things gets volunteered.