Market guide / Hillsboro and Portland, Oregon

Hillsboro and Portland colocation: 475 megawatts of inventory and about one you can lease.

This is the tightest primary market in North America. It is also the landing point for the transpacific subsea cables and one of the few markets with no state sales tax on equipment, which is why it stays full.

Hillsboro and Portland data center market

How much does colocation cost in Hillsboro and Portland?

Recent quotes we received for Oregon & Washington ran $345 to $395 per kW per month for up to 500 kW, falling to $220 to $260 above 1 MW. CBRE's published asking band for Hillsboro, Oregon is $185 to $225 per kW per month for 250 to 500 kW.

Hillsboro and Portland colocation pricing, USD per kW per month. Our quotes are for Oregon & Washington, updated October 26, 2026.
DeploymentMonthly rateSource
Up to 500 kW$345 to $395/kW-moOur quotes
Over 500 kW to 1 MW$280 to $320/kW-moOur quotes
Over 1 MW$220 to $260/kW-moOur quotes
250 to 500 kW, asking rent$185 to $225/kW-moCBRE, North America Data Center Trends H1 2026, first half of 2026

Smaller deployments cost more per kW. These are recent quotes we received, not a statement that space is available. Cross-connects, remote hands and one-time setup are extra. Operators often give 2–3 free months on a new term. See every region's quote ranges.

Hillsboro and Portland cabinet and cage prices

Smaller deployments are priced per cabinet or per cage rather than per kW. Use these monthly ranges to set a first-pass budget. They are not provider offers, and a building on this page is not a claim that space is available in it.

RequirementMonthly rangePower and bandwidth assumed
1 to 2U$295 to $455/mo1 to 3 A at 120 V, 1 to 5 TB of transfer
Half cabinet, 24U$1,185 to $1,445/mo2 to 3 kW, 100 Mbps to 1 Gbps
Full cabinet, 48U$1,415 to $1,660/mo2 to 5 kW, 100 Mbps to 1 Gbps
High-density cabinet, 48U$2,375 to $4,655/mo10 to 17 kW, three-phase
Private cage, 4 racks$5,245 to $5,760/mo5 kW per rack, 1 Gbps
High-density private cage, 4 racks$14,635 to $20,400/mo20 kW per rack, 1 Gbps

Based on quotes we received in the 30 days before 21 October 2026. Taxes, cross-connects, remote hands and one-time costs are extra. Replace these ranges with a normalized written quote before approval. How power is billed is covered in how colocation power is billed.

Get Hillsboro and Portland colocation prices for your setup

Tell us the racks, power and timing you need. A scout comes back with matching Hillsboro and Portland options and quoted prices.

Sample comparison of six colocation options side by side: monthly cost, committed power, dollars per kW, setup, term and deployment timing.
What you get back: every quote on one sheet, priced per kW so the options compare. This is a sample.
Add your name, company or phone Optional

Free to you. Powered by Bridgepointe Technologies, trusted by NVIDIA, Microsoft, Charles Schwab and 75+ Fortune 500 companies. A scout replies within one business day.

What providers in Hillsboro and Portland post as a list price

Most colocation in Hillsboro and Portland is quoted, not posted. The provider below is the exception: it publishes a monthly price on its own website, and every row links to that page. It is a smaller regional operator. The large operators here do not publish prices at all, so read these as a floor and a sanity check, not as what an enterprise contract lands at.

Posted by the provider1 offerChecked 22 September 2026
MonthlyProviderOfferPower includedPer usable kWBandwidth
$791SterlingFull cabinet, 44U. Tigard, Portland metro. $299 setupOne 1,800 W supply on UPSPower not stated3,600 GB a month

Each price was read on the provider's own page on the date shown. Usable kW is 80% of the circuit rating, with a redundant A+B pair counted once, and is only worked out where the provider states both amps and volts. "From" is the provider's own word for a starting price. Providers whose networks carry spam or abuse flags are left out whatever their price. A posted price is not availability, and bundles differ in bandwidth and power, so compare the whole row rather than the first column. How power is billed is covered in how colocation power is billed.

Holding a quote for Hillsboro and Portland?

Send it over and a scout will tell you how it compares with these posted prices and with the published benchmarks for this market. There is no obligation.

Who is actually plugged in across Hillsboro and Portland

A building existing and a building being connected are different facts, and only one of them decides whether your traffic can get where it needs to go cheaply. These figures come from PeeringDB, which the network operators themselves maintain, so every row below links to the building's own public entry.

Public record24 buildings listed203 network presences
MeasureFigureWhat it means
Buildings listed24Registered in PeeringDB across Hillsboro and Portland, by 15 operators
Buildings with a network present231 carries no network presence, which usually means single tenant or simply unregistered
Network presences203Counted per building, so a carrier in three buildings counts three times
Internet exchange presences15Where you can reach many networks through one port instead of many cross-connects
Carrier presences19The physical transport choice you can buy without leaving the building
In the densest building34%PTOR1 holds 70 of the market's network presences

The most connected buildings here

NetworksBuildingOperatorExchangesCarriers
70PTOR11547 Critical Systems Realty23
25EdgeConneX Portland (EDCPOR01)EdgeConneX Inc.22
23Flexential - Portland/Hillsboro 2 (PDX02)Flexential Corp.13
11QTS Hillsboro (HIL1)QTS Realty Trust, Inc.12
10Flexential - Portland/Hillsboro (PDX01)Flexential Corp.12
9Stack Infrastructure Portland PORO2Stack Infrastructure20
8EdgeConneX Hillsboro (EDCPOR02)EdgeConneX Inc.00
6Digital Realty Portland - PDX10Digital Realty11

From PeeringDB, which is maintained by the network operators present in these buildings rather than by the landlords, which is what makes it worth more than a directory. Two limits. Entries are voluntary, so a building showing no networks may be single tenant or may simply never have registered. And a network being present says nothing about whether the building has space, power or a price for you: that is still a call.

Year-end 2025 market profile

Why Hillsboro punches above its size

Hillsboro is the western terminus for several transpacific subsea cable systems, which makes it structurally important to any architecture that moves traffic between North America and Asia. Add Oregon's lack of a sales tax on equipment, historically low industrial power rates, and a mild climate that supports economiser cooling, and the market attracts demand well beyond what its size suggests.

CBRE reported 475.4 MW of inventory at the end of 2025 with a vacancy rate of 0.2%, an all-time low, leaving roughly 1.0 MW available across the entire market.

475.4 MW

Total inventory at the end of 2025, the sixth-largest primary market.

0.2% vacancy

An all-time low, and the tightest of any primary market.

About 1.0 MW

Available capacity across the whole market.

No 5 MW block

CBRE reports no facility with 5 MW or more of contiguous space available.

Source: CBRE on Hillsboro and CBRE North America Data Center Trends H2 2025. Figures describe the metro market, not a specific facility.

Read this number carefully

One megawatt available in a 475 MW market is not a tight market. It is a closed one. Anything you are offered here is either a small block in an existing hall, space someone else has released, or a future phase. Establish which of the three before you spend time on it.

What is actually constraining supply

Three things, and none of them resolve quickly. Oregon's urban growth boundary limits where development can happen at all, which is unusual among US data center markets and puts a hard edge on land supply. Power transmission into Washington County is limited. And permitting and zoning timelines have lengthened.

Oregon's POWER Act adds a further consideration by establishing a separate data center customer class at a 20 MW threshold, which changes how large loads are treated by the utility. Any large requirement needs that modelled rather than assumed.

CBRE reported that capacity under construction in Hillsboro fell 15% in 2025 against 2024. Supply is not catching up in the near term.

What drives a Hillsboro quote

Most capacity here is committed on long terms to a few large tenants, so there is little spot pricing. The published band tells you less than usual about what a new requirement will pay.

  • Existing or future. Assume nothing is free until an operator names a hall and a date. A phase that depends on transmission work runs on the utility's timeline.
  • Utility class. Model the tariff separately, including Oregon's 20 MW data center customer class if you are near it.
  • Renewal. In a market this tight, the renewal clause is the whole negotiation.
  • Cooling. Check the economiser-led design against your rack density.
  • Growth. With no 5 MW block free, expansion almost certainly means a second building.

When Hillsboro is the right answer

When the workload touches transpacific routing, needs Pacific Northwest presence, benefits from the equipment tax position, or pairs with a Californian primary site for regional resilience at a genuine distance. It is also credible for sustainability-led requirements given the regional hydro-heavy fuel mix.

It is the wrong answer when you need capacity soon and cannot wait for a phase. Compare with Silicon Valley when interconnection matters more than routing, and with Phoenix or Reno when the driver is western coverage at a deliverable date.

Best buying posture

Treat Hillsboro as a market you queue for, not one you shop in. Get in front of operators before the requirement is urgent, and keep a second market live so a delivery date slipping does not become your problem.

What has been announced in Hillsboro and Portland

Announcements are not filings. Nobody has to build what they announce, the figure is the one the developer chose to publish, and the date moves. They are here because megawatts are what a requirement is measured in, and because the size of what is coming changes who will take your call. Every figure below links to a published report that states it, and was checked against at least one other independent report before it was written down.

Announced, not filed1 projectLargest: 108 MW
CapacityOperatorProjectWhat was announced
108 MWAligned Data CentersPDX-01 and PDX-02, Hillsboro27 acres, first building 72 MW with 12 halls of 6 MW, second planned at 36 MW

Announced capacity is collected by hand from trade reporting and company statements, and each figure links to the report it came from. It is never added to a permit count: a permit is a document a jurisdiction issued, an announcement is a plan a company published. Neither is availability.

Every Hillsboro and Portland facility we track

53 data centers across Hillsboro and Portland, from our verified inventory. It is the layer that says whether a building exists yet, which no permit record answers directly.

Our collection53 facilities16 operators
StatusFacilitiesWhat it means for a search
Operational24Standing and running. The only layer that can hold a requirement this year
Under construction8Steel is up. Reachable for a date 6 to 18 months out, and usually pre-leasing now
Planned21Announced or entitled, not yet built. Treat every date on these as a forecast
Building area on file7,482,914 SFAcross the 31 facilities where a size is recorded, of 53
Largest single building648,000 SFSTACK Infrastructure, Hillsboro

Operators with the most facilities here: STACK Infrastructure (11), QTS (7), Flexential (6), Digital Realty (5), EdgeConneX (4), NTT Global Data Centers (4), Digital Fortress (3), Aligned Data Centers (2), Crane Data Centers (2), Rowan Digital Infrastructure (2).

Where they cluster: Hillsboro (40), Portland (4), Forest Grove (3), Beaverton (2), Umatilla (2), Boardman (1).

The largest buildings coming to this market

29 facilities here are under construction or planned. These are the ten largest by floor area, and a size on file is not a promise of a delivery date.

OperatorStatusBuilding sizeWhere
Crane Data CentersPlanned363,000 SFForest Grove, OR
FlexentialUnder Construction358,000 SFHillsboro, OR
Sabey Data CentersPlanned306,440 SFUmatilla, OR
Crane Data CentersUnder Construction180,000 SFForest Grove, OR
STACK InfrastructureUnder Construction180,000 SFHillsboro, OR
STACK InfrastructureUnder Construction180,000 SFHillsboro, OR
EdgeConneXUnder Construction172,232 SFHillsboro, OR
STACK InfrastructurePlanned140,000 SFHillsboro, OR
Five 9s DigitalPlanned84,610 SFHillsboro, OR
Aligned Data CentersUnder ConstructionNot on fileHillsboro, OR

From our verified inventory rather than from a public record, so these rows carry no filing link and street addresses are held back. These buildings are verified, which is not the same as their space being available: every facility above may be full, pre-leased, or closed to your size. Finding out is a call, not a lookup. See what a verified building does and does not mean.

Nothing here is listed

Find out which Hillsboro capacity is open to you.

With about a megawatt free market-wide, the only way to know what you can get is to ask. We ask operators against your requirement and date every answer.

From the research desk

Latest market developments

All news & analysis
Development & Power

Portland General lists 473 MW of executed data center contracts under construction, plus a separate contract for up to 420 MW

Portland General Electric said in its third quarter 2026 earnings slides, filed October 29, 2026, that 473 MW of executed 2025 and 2026 contracts with five data center customers are under construction. A further 2026 executed contract of up to 420 MW is not under construction and is expected to energize in 2028, ramping to full capacity in 2033. PGE also lists a pipeline of 1.3 GW of incremental large load requests to be energized in 2028 and beyond. PGE says the values represent customer capacity as of October 29, 2026. [Source 1]

Portland General Electric service area, Oregon · Utility contracts. 473 MW of executed 2025 and 2026 contracts with five data center customers under construction (PGE's words). Up to 420 MW 2026 executed contract not under construction, expected energization 2028, full capacity 2033. 1.3 GW of incremental large load requests for 2028 and beyond. Customer capacity as of October 29, 2026.
Read the analysis