Market guide / Hillsboro and Portland, Oregon

Hillsboro has 475 megawatts of inventory and about one megawatt you can lease.

This is the tightest primary market in North America. It is also the landing point for the transpacific subsea cables and one of the few markets with no state sales tax on equipment, which is why it stays full.

Year-end 2025 market profile

Why Hillsboro punches above its size

Hillsboro is the western terminus for several transpacific subsea cable systems, which makes it structurally important to any architecture that moves traffic between North America and Asia. Add Oregon's lack of a sales tax on equipment, historically low industrial power rates, and a mild climate that supports economiser cooling, and the market attracts demand well beyond what its size suggests.

CBRE reported 475.4 MW of inventory at the end of 2025 with a vacancy rate of 0.2%, an all-time low, leaving roughly 1.0 MW available across the entire market.

475.4 MW

Total inventory at the end of 2025, the sixth-largest primary market.

0.2% vacancy

An all-time low, and the tightest of any primary market.

About 1.0 MW

Available capacity across the whole market.

No 5 MW block

CBRE reports no facility with 5 MW or more of contiguous space available.

Source: CBRE on Hillsboro and CBRE North America Data Center Trends H2 2025. Figures describe the metro market, not a specific facility.

Read this number carefully

One megawatt available in a 475 MW market is not a tight market. It is a closed one. Anything you are offered here is either a small block in an existing hall, space someone else has released, or a future phase. Establish which of the three before you spend time on it.

What is actually constraining supply

Three things, and none of them resolve quickly. Oregon's urban growth boundary limits where development can happen at all, which is unusual among US data center markets and puts a hard edge on land supply. Power transmission into Washington County is limited. And permitting and zoning timelines have lengthened.

Oregon's POWER Act adds a further consideration by establishing a separate data center customer class at a 20 MW threshold, which changes how large loads are treated by the utility. Any large requirement needs that modelled rather than assumed.

CBRE reported that capacity under construction in Hillsboro fell 15% in 2025 against 2024. Supply is not catching up in the near term.

Pricing

CBRE puts Hillsboro asking rates at $175 to $225 per kW per month, against a national average of $195.94 for a 250 to 500 kW requirement. That is below Silicon Valley and roughly in line with Chicago, which is notable for a market with effectively no vacancy.

The reason rates have not run further is that most capacity here is committed on long terms to a small number of large tenants, so there is little spot pricing to reset the market. That also means the published band tells you less than usual about what you would actually pay for a new requirement today.

  • Confirm whether an offer is existing capacity or a phase dependent on transmission work.
  • Model the utility separately, including the 20 MW customer class threshold if you are near it.
  • Ask what happens at renewal. In a market this tight, the renewal clause is the whole negotiation.
  • Check the cooling design against your density. Economiser-led designs behave differently under high-density load.

When Hillsboro is the right answer

When the workload touches transpacific routing, needs Pacific Northwest presence, benefits from the equipment tax position, or pairs with a Californian primary site for regional resilience at a genuine distance. It is also credible for sustainability-led requirements given the regional hydro-heavy fuel mix.

It is the wrong answer when you need capacity soon and cannot wait for a phase. Compare with Silicon Valley when interconnection matters more than routing, and with Phoenix or Reno when the driver is western coverage at a deliverable date.

Risks to resolve before shortlisting

  • Availability is the risk: assume nothing is free until an operator confirms a named hall and a date.
  • Transmission dependency: a phase contingent on utility work carries the utility's timeline, not the operator's.
  • Land supply: the urban growth boundary means new sites are not simply a matter of capital.
  • Concentration: a small number of operators hold most of the market, which limits competitive tension.
  • Expansion: with no 5 MW blocks free, growth almost certainly means a second building.

A facility-ready Hillsboro brief

  1. Committed power now, and the expansion step with a date.
  2. Whether the requirement can be split across buildings or campuses.
  3. Subsea or long-haul routing dependencies, named.
  4. Density and cooling method, tested against the hall's design.
  5. Utility class, tariff and pass-through mechanics above 20 MW.
  6. Renewal protection, because retention leverage sits with the operator here.
Best buying posture

Treat Hillsboro as a market you queue for, not one you shop in. Get in front of operators before the requirement is urgent, and keep a second market live so a delivery date slipping does not become your problem.

What has been announced in Hillsboro and Portland

Announcements are not filings. Nobody has to build what they announce, the figure is the one the developer chose to publish, and the date moves. They are here because megawatts are what a requirement is measured in, and because the size of what is coming changes who will take your call. Every figure below was read on the page it links to.

Announced, not filed1 projectsLargest: 108 MW
CapacityOperatorProjectWhat was announced
108 MWAligned Data CentersPDX-01 and PDX-02, Hillsboro27 acres, first building 72 MW with 12 halls of 6 MW, second planned at 36 MW

Announced capacity is collected by hand from trade reporting and company statements, and each figure links to the report it came from. It is kept apart from the permit record above and never added to it: one is a document a jurisdiction issued, the other is a plan a company published. Neither is availability.

Every Hillsboro and Portland facility we track

53 data centers across Hillsboro and Portland, from the facility database we hold as a Bridgepointe partner. It is the layer that says whether a building exists yet, which no permit record answers directly.

Our collection53 facilities16 operators
StatusFacilitiesWhat it means for a search
Operational24Standing and running. The only layer that can hold a requirement this year
Under construction8Steel is up. Reachable for a date 6 to 18 months out, and usually pre-leasing now
Planned21Announced or entitled, not yet built. Treat every date on these as a forecast
Building area on file7,482,914 SFAcross the 31 facilities where a size is recorded, of 53
Largest single building648,000 SFSTACK Infrastructure, Hillsboro

Operators with the most facilities here: STACK Infrastructure (11), QTS (7), Flexential (6), Digital Realty (5), EdgeConneX (4), NTT Global Data Centers (4), Digital Fortress (3), Aligned Data Centers (2), Crane Data Centers (2), Rowan Digital Infrastructure (2).

Where they cluster: Hillsboro (40), Portland (4), Forest Grove (3), Beaverton (2), Umatilla (2), Boardman (1).

The largest buildings coming to this market

29 facilities here are under construction or planned. These are the ten largest by floor area, and a size on file is not a promise of a delivery date.

OperatorStatusBuilding sizeWhere
Crane Data CentersPlanned363,000 SFForest Grove, OR
FlexentialUnder Construction358,000 SFHillsboro, OR
Sabey Data CentersPlanned306,440 SFUmatilla, OR
Crane Data CentersUnder Construction180,000 SFForest Grove, OR
STACK InfrastructureUnder Construction180,000 SFHillsboro, OR
STACK InfrastructureUnder Construction180,000 SFHillsboro, OR
EdgeConneXUnder Construction172,232 SFHillsboro, OR
STACK InfrastructurePlanned140,000 SFHillsboro, OR
Five 9s DigitalPlanned84,610 SFHillsboro, OR
Aligned Data CentersUnder ConstructionNot on fileHillsboro, OR

From the Signal facility database, which we hold as a Bridgepointe partner rather than as a public record, so these rows carry no filing link and street addresses are held back. A building existing is not the same as space being available in it: every facility above may be full, pre-leased, or closed to your size. Finding out is a call, not a lookup. See how we verify capacity.

Nothing here is listed

Find out which Hillsboro capacity is open to you.

With about a megawatt free market-wide, the only way to know what you can get is to ask. We do that without naming you, and we date every answer.