Colocation Scout / News & Analysis

144 MW proposed for Digital Realty’s Corny data center campus in Hillsboro

An October 6 state application outlines two two-story buildings for hyperscale and enterprise colocation, with generator yards, a road extension and 0.39 acre of proposed wetland impact. The 144 MW figure is applicant-proposed capacity.

144 MW proposed for Digital Realty’s Corny data center campus in Hillsboro
All news & analysisDevelopment & PowerHillsboro, Washington County, OregonProposed; city planning review and state removal-fill application

Disclosed terms

Proposed capacity
144 MW for hyperscale and enterprise colocation [1]
Buildings
Two buildings, each two stories [1]
Wetland impact
0.39 acre proposed; mitigation bank credits proposed [1]
Employment projection
186 full-time opportunities, projected by the applicant [1]
State filing
Received October 6, 2026; APP0066364 [2]

The disclosure and our analysis

What the filing reveals

Digital Beaver 4 LLC proposes 144 MW of data storage and processing capacity at the Corny Data Center campus in Hillsboro, Oregon. The 92-page joint permit application, received by the Oregon Department of State Lands on October 6, 2026, identifies hyperscale and enterprise colocation as the intended uses. The application narrative and a signed city support letter connect the proposal to Digital Realty. [Sources 1 and 2]

The campus would sit east of NE Cornelius Pass Road and north of NE Cornell Road. Washington County identifies the property as the 28.95-acre Wishing Well Lot 2, parcel 1N226D000200. Its sales record shows a March 10, 2026 transfer from Legacy Health Systems to Digital Beaver 4 LLC for $50 million. That is a recorded land acquisition price, not a construction budget. [Source 3]

Two buildings and a road extension

The packet describes two buildings, each two stories, with generator and electrical equipment yards, campus circulation and stormwater facilities. The site plan places a stormwater facility toward the southeast. The proposal would extend NE Ronler Drive along the northern boundary toward NE Aloclek Drive. Its narrative describes a three-lane collector, an 80-foot improved right-of-way and two campus access points. [Source 1, pages 2, 10, 27 and 31]

The applicant projects 186 full-time employment opportunities. AKS Engineering & Forestry prepared the application. A November 3, 2025 letter signed by Hillsboro Economic Development Manager Valerie Okada supports Digital Realty’s wetland application. The letter documents city economic-development support; it is separate from a land-use approval. [Source 1, pages 5 and 33]

Wetlands remain part of the approval process

The applicant proposes 17,075 square feet, or 0.39 acre, of permanent wetland impact. The packet specifies 315 cubic yards of excavation and 6,830 cubic yards of structural fill, with 0.39 mitigation credit proposed from Dairy Creek Mitigation Bank. These are requested impacts and mitigation measures. The state application record displays Application awaiting fees and does not establish an issued removal-fill permit. [Sources 1 and 2]

How it connects to Hillsboro’s Q3 filings

Corny’s city Development Review II application, DR26-0031, was filed July 21, 2026. The state packet’s signed planning affidavit explicitly identifies that city case. Corny and the separate Wagon proposal entered the city process six days before Hillsboro adopted its 120-day application moratorium on July 27. The city said previously submitted applications could continue through review. [Sources 1, 4 and 5]

The October 6 state application supplies additional detail about the July proposal. Its filing date falls after the September 30 end of Q3. The proposed 144 MW is a post-quarter project disclosure, with the city application date kept separate.

What 144 MW means for the market

Our analysis: the disclosure gives buyers a clearer measure of Corny’s proposed scale. It does not establish when that capacity could be delivered. The next useful evidence would be an approved land-use decision, utility-service documentation and a construction schedule tied to those approvals.

What remains unknown

The reviewed records do not establish contracted utility capacity, an energization date, a tenant, construction cost, available inventory, cooling-water demand or generator count and ratings. The narrative references approximately 371,000 square feet of building space, but does not clearly reconcile that figure with the two-story layout; verified gross floor area remains unresolved. The state packet is not a complete substitute for the city’s architectural, traffic and noise submissions.

Sources

  1. Oregon DSL: Corny joint permit application, 92 pages · Published 2026-10-06
  2. Oregon DSL: APP0066364 application record · Published 2026-10-06
  3. Washington County: Corny parcel and March 10 sale · Published 2026-03-10
  4. Hillsboro: Corny DR26-0031 planning record · Published 2026-07-21
  5. City of Hillsboro: application moratorium · Published 2026-07-27

Explore the market

Related reporting

Development & Power

CleanSpark's 585 MW Sealy and Brazoria, Texas sites: tenant exclusivity expired, conditional ERCOT Batch Zero status

CleanSpark said on November 24, 2026 that the exclusivity period covering its Sealy and Brazoria, Texas campuses has expired, and that commercialization is proceeding with its existing Sandersville tenant and others. In the same fiscal fourth quarter release, the company reported a Conditional Batch Zero Baseload designation on 585 MW: 285 MW at Sealy and 300 MW at Brazoria Phase 1. It disclosed no Texas lease. [Source 1]

Sealy and Brazoria campuses, Texas · Announced sites with conditional grid designations (CleanSpark reports Conditional Batch Zero Baseload designation on 585 MW and Conditional Batch Zero Studied Load for Brazoria Phase 2, up to 300 MW, as of November 24, 2026). Tenant exclusivity expired. No lease disclosed. Not available capacity.
Read the analysis
Development & Power

Denton, Texas data center permit S26-0006 seeks a Specific Use Permit for 23.8 acres off E. University Dr.

A Specific Use Permit application for a data center on 23.8 acres in Denton, Texas, south of E. University Dr. and west of Geesling Rd., was submitted to the City of Denton on November 9, 2026. The city's planning record lists it as case S26-0006, project name Birddog, on land zoned Light Industrial and not platted. Its status was Under Review as of November 13, 2026. The record lists no megawatts, end user or hearing date. [Source 1]

South of E. University Dr. and west of Geesling Rd., Denton, Denton County, Texas · Proposed (Specific Use Permit application S26-0006 submitted November 9, 2026; city status Under Review as of November 13, 2026). No hearing date set in the record. No megawatt figure, tenant or end user disclosed.
Read the analysis
Development & Power

Entergy Arkansas plans a second phase of service for Google's West Memphis data center campus, with about $600 million of grid work and a 440 MW solar contract paid for by Google

Entergy Arkansas announced on October 19, 2026 a second phase of electric service for Google's data center campus in West Memphis, Arkansas. The utility says the phase needs about $600 million of planned investment plus a power purchase agreement, all covered by Google: two battery systems, a 440 MW (ac) solar contract, an expanded Galet substation and two new 230 kV lines to serve the expanded campus. The expansion still has to be submitted to the Arkansas Public Service Commission; Entergy targets service in 2028 if it is approved. Entergy listed the expanded Google agreement among its third quarter highlights on November 2. [Source 1] [Source 2]

West Memphis, Crittenden County, Arkansas · Announced October 19, 2026; to be submitted to the Arkansas Public Service Commission for approval. Pending approval, Entergy expects service in 2028. Not approved as of November 2, 2026.
Read the analysis