144 MW proposed for Digital Realty’s Corny data center campus in Hillsboro

An October 6 state application outlines two two-story buildings for hyperscale and enterprise colocation, with generator yards, a road extension and 0.39 acre of proposed wetland impact. The 144 MW figure is applicant-proposed capacity.

144 MW proposed for Digital Realty’s Corny data center campus in Hillsboro
All news & analysisDevelopment & PowerHillsboro, Washington County, OregonProposed; city planning review and state removal-fill application

Disclosed terms

Proposed capacity
144 MW for hyperscale and enterprise colocation [1]
Buildings
Two buildings, each two stories [1]
Wetland impact
0.39 acre proposed; mitigation bank credits proposed [1]
Employment projection
186 full-time opportunities, projected by the applicant [1]
State filing
Received October 6, 2026; APP0066364 [2]

The disclosure and our analysis

What the filing reveals

Digital Beaver 4 LLC proposes 144 MW of data storage and processing capacity at the Corny Data Center campus in Hillsboro, Oregon. The 92-page joint permit application, received by the Oregon Department of State Lands on October 6, 2026, identifies hyperscale and enterprise colocation as the intended uses. The application narrative and a signed city support letter connect the proposal to Digital Realty. [Sources 1 and 2]

The campus would sit east of NE Cornelius Pass Road and north of NE Cornell Road. Washington County identifies the property as the 28.95-acre Wishing Well Lot 2, parcel 1N226D000200. Its sales record shows a March 10, 2026 transfer from Legacy Health Systems to Digital Beaver 4 LLC for $50 million. That is a recorded land acquisition price, not a construction budget. [Source 3]

Two buildings and a road extension

The packet describes two buildings, each two stories, with generator and electrical equipment yards, campus circulation and stormwater facilities. The site plan places a stormwater facility toward the southeast. The proposal would extend NE Ronler Drive along the northern boundary toward NE Aloclek Drive. Its narrative describes a three-lane collector, an 80-foot improved right-of-way and two campus access points. [Source 1, pages 2, 10, 27 and 31]

The applicant projects 186 full-time employment opportunities. AKS Engineering & Forestry prepared the application. A November 3, 2025 letter signed by Hillsboro Economic Development Manager Valerie Okada supports Digital Realty’s wetland application. The letter documents city economic-development support; it is separate from a land-use approval. [Source 1, pages 5 and 33]

Wetlands remain part of the approval process

The applicant proposes 17,075 square feet, or 0.39 acre, of permanent wetland impact. The packet specifies 315 cubic yards of excavation and 6,830 cubic yards of structural fill, with 0.39 mitigation credit proposed from Dairy Creek Mitigation Bank. These are requested impacts and mitigation measures. The state application record displays Application awaiting fees and does not establish an issued removal-fill permit. [Sources 1 and 2]

How it connects to Hillsboro’s Q3 filings

Corny’s city Development Review II application, DR26-0031, was filed July 21, 2026. The state packet’s signed planning affidavit explicitly identifies that city case. Corny and the separate Wagon proposal entered the city process six days before Hillsboro adopted its 120-day application moratorium on July 27. The city said previously submitted applications could continue through review. [Sources 1, 4 and 5]

The October 6 state application supplies additional detail about the July proposal. Its filing date falls after the September 30 end of Q3. The proposed 144 MW is a post-quarter project disclosure, with the city application date kept separate.

What 144 MW means for the market

Our analysis: the disclosure gives buyers a clearer measure of Corny’s proposed scale. It does not establish when that capacity could be delivered. The next useful evidence would be an approved land-use decision, utility-service documentation and a construction schedule tied to those approvals.

What remains unknown

The reviewed records do not establish contracted utility capacity, an energization date, a tenant, construction cost, available inventory, cooling-water demand or generator count and ratings. The narrative references approximately 371,000 square feet of building space, but does not clearly reconcile that figure with the two-story layout; verified gross floor area remains unresolved. The state packet is not a complete substitute for the city’s architectural, traffic and noise submissions.

Sources

  1. Oregon DSL: Corny joint permit application, 92 pages · Published 2026-10-06
  2. Oregon DSL: APP0066364 application record · Published 2026-10-06
  3. Washington County: Corny parcel and March 10 sale · Published 2026-03-10
  4. Hillsboro: Corny DR26-0031 planning record · Published 2026-07-21
  5. City of Hillsboro: application moratorium · Published 2026-07-27

Explore the market

Related reporting

Development & Power

Serverfarm tops out ARK1 at its Clarksville, Arkansas campus, a building the company lists at 108 MW

Serverfarm has topped out ARK1, the first building at its Clarksville, Arkansas data center campus, DCD reported on October 12, 2026, citing a LinkedIn post by chief executive Avner Papouchado the previous week. [Source 1] Serverfarm's own campus page lists four buildings, ARK1 through ARK4, each with 108 MW of building capacity across 300,000 square feet on two floors, and says the first two buildings are expected to be complete by January 2028. The page does not say whether 108 MW is critical IT load or utility capacity. [Source 2]

Clarksville, Johnson County, Arkansas · Under construction. ARK1 topped out, per DCD on October 12, 2026 citing a CEO post the prior week. Serverfarm targets its first two buildings for January 2028. Not energized or available per the reviewed sources. As of October 12, 2026.
Read the analysis
Development & Power

Anne Arundel County passes a data center moratorium that stops new applications but lets filed plans and adjacent expansions proceed

The Anne Arundel County Council passed Bill 63-26 by a 7-0 vote on October 5, 2026, according to the county's legislation page. [Source 1] The amended bill text posted by the county bars the county from accepting new applications of any type for a proposed data storage center during an Effective Period that runs from the bill's effective date until the earlier of January 31, 2028 or the effective date of comprehensive rules based on a work group's recommendations. Plans filed before that period begins, and future phases of existing data centers on adjacent or adjoining properties, may proceed. [Source 2] The bill also repeals the county's personal property tax assessment reduction for qualified data storage centers. [Source 1]

Anne Arundel County, Maryland · Approved. Bill 63-26 passed by the Anne Arundel County Council, 7-0, on October 5, 2026; moratorium runs from the effective date to the earlier of January 31, 2028 or comprehensive rules. Effective date not stated on the county page. As of October 12, 2026.
Read the analysis
Development & Power

Virginia regulators cite Google's Project Peanut data center site in Chesterfield County for seven sediment incidents outside its water permit

The Virginia Department of Environmental Quality issued Notice of Violation No. 2026-08-PRO-203 on September 29, 2026 to Peanut LLC, the responsible party for Project Peanut in Chesterfield County, under Virginia Water Protection Permit No. 19-1094. The notice was emailed to a google.com address. It cites unauthorized filling of surface waters outside permitted impact areas reported on seven dates between December 30, 2025 and August 5, 2026, and estimates that about 7,735 linear feet of stream channel and about 1.4 acres of wetland were affected by sediment. [Source 1] Google told local media that heavy rainfall overwhelmed stormwater controls and that it temporarily paused general construction to focus on cleanup. [Source 2]

Chesterfield County, Virginia · Under construction (site work), per DEQ observations of project-related activities from December 2025 to August 2026. Notice of violation issued September 29, 2026; enforcement pending. Google told local media it temporarily paused general construction for cleanup. As of October 12, 2026.
Read the analysis