What Q3 2026 filings show
Headline lease announcements hide three things that decide what a tenant actually writes checks for: whether power is passed through, whether build-out charges sit in the revenue line, and whether the megawatts in the press release are critical IT load or gross facility power.
- Billed rent diverges from headline base rates by $18 to $56/kW a month. In Q3 2026, power pass-throughs, one-off fit-out billings, and GAAP straight-lining of annual escalators shifted realized per-kW revenue well above base license fees at Core Scientific and TeraWulf.
- Retail high-density deployments carry steeper friction than wholesale. A newly disclosed 250 kW Santa Clara agreement carries a 5% annual escalator, $274,113 in setup charges, a 3-month cash deposit, and no termination for convenience.
- Signed megawatt deals still fail before closing. Fermi and TensorWave terminated their 156 MW, $6.5 billion Texas lease before financing closed, showing why unfinanced build-to-suit capacity cannot replace a dated delivery path.
Billed Q3 2026 rent vs. headline AI leases
Four operators reported Q3 2026 colocation or HPC leasing revenue alongside delivered critical IT load. Dividing quarterly GAAP rent by delivered capacity shows what moved onto the income statement, and how far it differs from the headline contract number.
| Operator and site | Capacity billing in Q3 | Realized Q3 rate (our math) | Headline rate and basis |
|---|---|---|---|
| Core Scientific (mostly CoreWeave, six sites) | 440 MW avg billing (395 MW Jun 30 to 485 MW Sep 30) | ~$119/kW-mo license ($163 total) | $157.3M license fees ($108 at 485 MW to $133 at 395 MW) plus $57.6M ($44/kW-mo) power pass-through. Headline base fee is $100/kW-mo; GAAP straight-lines escalators. Cross-check: over $700M annualized at 485 MW = $120/kW-mo. |
| TeraWulf, Lake Mariner (Core42 and Fluidstack, NY) | 102 MW operational critical IT (first full quarter) | ~$150/kW-mo base ($206 gross) | $46.03M straight-line base rent matches the ~$152/kW-mo 10-year contracted average (438 MW, ~$8B). Gross total adds $5.38M ($18/kW-mo) power pass-through and $11.28M ($37/kW-mo) tenant fit-out. |
| Galaxy Digital, Helios I Phase I (CoreWeave, TX) | 133 MW critical IT (all delivered by Jun 30) | ~$198/kW-mo GAAP rent | $79.07M leasing revenue (~$2.38M/MW-yr), near triple net with CoreWeave paying power directly. Segment opex ran ~$25/kW-mo vs. $15/kW-mo steady-state footnote on Phase II. |
| Cipher Digital, Black Pearl (Amazon, Wink TX) | Phased delivery started Aug 2026; 18 MW delivered to Nov 2 | $145+/kW-mo lower bound | $5.23M fixed GAAP rent plus $0.62M variable over partial ramp, alongside $46.2M deferred rent billed ahead of GAAP. Compares to $141/kW-mo triple-net term average on critical load. |
Realized Q3 rates are our division of quarterly GAAP segment revenue by billing kW and three months. They are historical accounting measures, not asking quotes. Sources: Core Scientific Q3 2026 8-K Ex-99.1 and Ex-99.2; TeraWulf Q3 2026 Form 10-Q; Galaxy Digital Q3 2026 8-K; Cipher Digital Q3 2026 Form 10-Q.
First, gross HPC revenue per kW can be inflated by one-time fit-out reimbursements: TeraWulf's $206/kW gross revenue dropped to $150/kW base rent once the 10-Q split out $11.3M in tenant fit-out billings and $5.4M in power pass-through. Second, quoting gross facility MW instead of critical IT MW cuts apparent rent by roughly 30%. In its Q3 business update, Cipher quotes Black Pearl at $102/gross kW vs. $141/critical kW, and restates its 20-year Barber Lake commitment (300 MW gross / 207 MW critical) at $108 gross ($157 critical) for years 1 to 10 with Fluidstack and $144 gross ($209 critical) for years 11 to 20 with an unnamed AI lab.
A signed 250 kW retail GPU colocation contract (Santa Clara)
Most SEC-disclosed colocation deals are 40 to 400 MW hyperscale leases. On November 16, 2026, Exascale Labs Holdings disclosed the rare exception: a binding retail high-density agreement for 16 cabinets in Santa Clara, California, signed October 16, 2026 with Zillion Network Inc.
| Contract term | Disclosed figure | Notes |
|---|---|---|
| Market and scope | Santa Clara, CA; 16 cabinets, 250 kW allocated | ~15.6 kW per cabinet at SFO1 (building unnamed) |
| Initial term and start | 60 months; March 1, 2027 to February 28, 2032 | No termination for convenience |
| Year-one monthly recurring charge (MRC) | $91,755/mo ~$367/kW; ~$5,735/cab | Derived by dividing MRC by 250 kW and 16 cabinets |
| Annual escalator | 5% per year | Compounds to ~$6.08M total over 60 months |
| Non-recurring setup fee (NRC) | $274,113 | Roughly 3.0 months of year-one MRC |
| Security deposit | $275,265 | Exactly 3 months of year-one MRC |
Source: Exascale Labs Holdings Form 10-Q (filed November 16, 2026). Caveat: the filing does not state whether the $91,755 MRC includes metered electricity or only reserved capacity; treat ~$367/kW-mo as an upper bound on space-plus-power if power bills on top. Small high-density GPU retail deals sit well above wholesale Silicon Valley asking rents and are not directly comparable.
The term structure matters as much as the rate. Large wholesale leases on our colocation pricing guide carry 3% to 3.5% annual escalators. At 250 kW in Silicon Valley, Exascale accepted a 5% annual escalator plus nearly $550,000 combined in setup fees and cash security. If you are weighing whether to buy and colocate high-density GPU servers against renting capacity directly, compare our B300 cluster cost breakdown and our sister site's SEC-filed reserved GPU contract tracker.
What multi-tenant retail operators actually bill per built kW (KBRA bond filings)
Private multi-tenant operators rarely publish financial statements, except when they securitize facilities into asset-backed notes. Rating-agency press releases from KBRA state each issuer's portfolio annualized recurring revenue (AMRR or ARR) alongside total critical load MW across the pool.
| Operator pool (KBRA series) | Sites and critical load | Annualized recurring revenue | Derived per built kW-mo | Wtd avg remaining term |
|---|---|---|---|---|
| US Signal (2026-1/2, Oct 2026) | 10 sites, ~22.5 MW | ~$111.8M ARR (57% AANOI) | About $414/kW-mo | 2.1 yr (839 customers) |
| TierPoint (2026-1/2, Sep 2026) | 34 sites, 104.8 MW | ~$491.4M AMRR (49% AANOI) | About $391/kW-mo | 2.1 yr |
| Flexential (2026-1 to 4, Mar 2026) | 28 sites, 199 MW | ~$663.3M AMRR (53% AANOI) | About $278/kW-mo | 2.4 yr |
| Centersquare (2025-5/6/7, Nov 2025) | 40 sites, 296.6 MW | ~$755.4M AMRR (55% AANOI) | About $212/kW-mo | 2.7 yr |
| DataBank (2026-2/3/4, Oct 2026) | 38 sites, 287.2 MW | ~$555.2M AMRR (56% AANOI) | About $161/kW-mo | 2.6 yr (AI = 9.1% of AMRR) |
Math: portfolio AMRR or ARR divided by built critical load kW and 12 months. Three caveats apply: (1) KBRA's numerator is total recurring revenue across space, power recovery, interconnection, managed services and cloud, not base colocation rent; (2) the denominator is total critical load capacity rather than occupied kW (KBRA omits occupancy here, so billed revenue per leased kW is higher); (3) managed-services heavy portfolios (US Signal, TierPoint) bill more per built kW than wholesale-mixed pools (DataBank), and each pool is a securitized subset, not a live price list.
For contrast at the single-tenant hyperscale floor, KBRA's July 2026 rating of Lohrasp Enterprise II (LC3, Loudoun County VA) covers an ~80 MW building 100% leased triple-net to one investment-grade hyperscaler at ~$65.1M annualized base rent, or about $68/kW-mo with ~13.8 years remaining. Because the tenant pays power, taxes, insurance and operating expenses separately and the original lease date is not disclosed, it sits far below new-build turnkey rates.
Powered land, powered shell, and turnkey: why per-kW rates split 2.5x
Comparing a powered-shell rent against a turnkey rate without adjusting for build scope is the fastest way to misread an SEC filing. Fermi's Q3 2026 investor presentation published a 45-deal market benchmark splitting year-one triple-net fixed charges across all three delivery scopes on 15-to-20 year terms.
| Product (who builds what) | Capex per gross MW | Year-1 charge per gross kW-mo | Converted to IT kW-mo (x 1.37) |
|---|---|---|---|
| Powered Land+ (land, campus, power; tenant builds shell and fit-out) | $3.9M to $5.1M | $55 to $69 | About $75 to $95 |
| Powered Shell (landlord adds building shell) | $5.1M to $6.6M | $64 to $80 | About $88 to $110 |
| Turnkey (landlord delivers cooling, UPS and data halls) | $12.1M to $15.0M | $130 to $163 | About $178 to $223 |
Source: Fermi Inc. Q3 2026 Investor Presentation (8-K Ex-99.2, November 12, 2026, pp. 9 to 13; 45 market deals since July 2024; 1.37 gross-to-IT conversion stated by Fermi). Operator-compiled benchmark furnished under Item 7.01, not a signed contract or live quote.
Recent Q3 and Q4 2026 wholesale SEC filings line up inside that turnkey range:
- Duos Edge AI, 20 MW (10-year cloud deal): More than $400M initial term value (Q2 2027 target), implying a floor of at least ~$167/kW-mo (IT vs. gross unstated). Compares to Duos's 5-year, 10 MW Columbus, Georgia agreement stated at $185/kW-mo in its October 2026 investor deck.
- Riot Platforms, Rockdale TX (191 MW critical IT): 20-year lease with an unnamed frontier AI lab for ~$9.1B initial revenue, or ~$199/kW-mo term average (power treatment undisclosed).
- Host Digital, Northeast Oklahoma (43 MW critical IT): 15-year take-or-pay lease for ~$1.25B base revenue with a 3% annual escalator, or ~$161/kW-mo term average (~$130/kW-mo derived year one).
A signed AI lease only turns into capacity if project financing closes. In its November 12, 2026 earnings release, Fermi confirmed that it and TensorWave terminated their August 2026 Project Matador agreement (156 MW critical IT, ~$6.5B) along with its AMD credit support before closing.
Public REIT Q3 2026 scoreboard: Digital Realty, Equinix and Iron Mountain
The three largest public colocation filers reported Q3 2026 pricing and renewal metrics in late October and early November. These are portfolio-wide averages rather than local quotes; our 2026 pricing benchmarks page carries the full comparison.
| Operator (Q3 2026 filing) | Scale and size band | Q3 2026 reported figure | Renewal and trend context |
|---|---|---|---|
| Equinix (313,300 cabinets billing) | Global retail and interconnection (~78% utilized) | $2,574/cab-mo worldwide | $2,783 Americas, $2,452 EMEA, $2,389 APAC. Up 5.7% YoY from $2,436; includes interconnection revenue. |
| Digital Realty (0 to 1 MW, global at share) | 41.2 MW signed, 5.5-yr wtd avg term | $262/kW-mo GAAP ($248 cash) | YTD 2026 $263 GAAP. Cash renewals up 4.7% ($301 to $315/kW-mo). |
| Digital Realty (>1 MW, global at share) | 143.6 MW signed, 17.9-yr wtd avg term | $275/kW-mo GAAP ($217 cash) | YTD 2026 $216 GAAP ($213 LTM); Q3 reflects lumpy long-term deals. Cash renewals up 26.3% (+11.8% overall). |
| Iron Mountain (544.6 MW operating, 97.2% leased) | 102.5 MW signed; 29.2 MW commenced; 8.6 MW renewed | $127 signed $168 comm. / $302 ren. | YTD new signings $145/kW-mo (Q3 pulled down by large deals). Cash mark-to-market +10.0%; GAAP +14.9%. |
Benchmark your colocation quote against the filing record.
Send your target market, kW requirement, density and start date. We separate base rent, power, setup fees and escalators onto one comparable sheet and tell you where a proposal sits against current market quotes.
How we checked these numbers
Every figure on this page comes directly from SEC EDGAR filings (Forms 10-Q, 8-K, and Exhibits 99.1/99.2) or KBRA rating-agency press releases checked between October 27 and November 17, 2026. Derived monthly rates show their exact formula and keep realized GAAP billing, securitized all-service revenue per built kW, term-average contract values, and operator-compiled benchmarks strictly separate. None of these figures is a live offer or a statement of contractible availability.
Related pricing and pipeline guides: 2026 pricing benchmarks, colocation pricing by deployment size, government contract rates, B300 cluster rental vs. colocation, and the utility data center pipeline tracker.