Power / Utility earnings

Utility Data Center Pipelines, Quarter by Quarter

What each major U.S. utility has told investors about data center demand, every quarter since early 2025. Every figure links to the filing that printed it.

data center load pipelines reported by U.S. electric utilities, by quarter

27 investor-owned utilities, Q1 2025 through Q3 2026. 25 put a megawatt figure on data center demand at least once, and 17 report signed data center contracts. 19 have reported Q3 2026 so far. Filings read through November 4, 2026.

What the numbers show

Data center contracts rose at 12 of 14 utilities that report them over time. None fell.

  • FirstEnergy roughly doubled its signed contracts in a year, from 3.8+ GW to 7.88 GW. Xcel went from ~1 GW to ~2 GW, and Southern from 6 GW to 11+ GW.
  • Pipelines run 2 to 10 times larger than signed contracts. Xcel reports 20 GW in its pipeline against ~2 GW signed. Southern reports 75+ GW against 11+ GW.
  • Requests in Texas and Pennsylvania are still climbing every quarter. Oncor's data center queue grew from 156+ GW to ~282 GW in 18 months. PPL's advanced-stage requests rose from ~11 GW to 31.8 GW.
  • 10 of 27 utilities do not report signed data center contracts. They include the four with the largest pipelines: Oncor Electric Delivery, Exelon, NextEra Energy and PSEG.
  • At least eight utilities changed how they count during this period, among them PG&E, Duke, FirstEnergy, Evergy and Exelon. Compare each utility with itself, not with its neighbor.

Signed data center contracts by utility

Signed data center contracts: power demand that data center customers have committed to in a signed agreement with the utility, total to date. It is the closest figure the utilities have in common. Contract types and time horizons still differ a little: open a utility below for its exact wording. The pipeline column uses each utility's own definition and is not comparable between utilities. Select any figure to open the filing.
7-quarter trend
American Electric Power84 GWQ3 2026Agreements through 2031. Includes non-data-center load.First figure in this series190 GWQ3 2025load requests
Dominion Energy12.2 GWQ3 2026Service agreements+200 MW since Q2 2026~54.9 GWQ3 2026all contract stages
PPL Corp11+ GWQ2 2026Q3 2026 pendingService agreements, Pennsylvania+1 GW since Q1 202631.8 GWQ2 2026advanced-stage requests
Southern Company11+ GWQ1 2026Q3 2026 pendingContracted large load. Includes non-data-center load.+1 GW since Q4 202575+ GWQ2 2026prospective pipeline
FirstEnergy7.88 GWQ3 2026Contracts and service agreements+1.52 GW since Q2 202619.07 GWQ3 2026long-term pipeline
Duke Energy~7.8 GWQ2 2026Q3 2026 pendingService agreements+200 MW since Q1 2026~15.4 GWQ2 2026late-stage pipeline
Pinnacle West5.8 GWQ3 2026Committed load. Includes non-data-center load.+1.3 GW since Q2 2026~20 GWQ3 2026uncommitted opportunity
CenterPoint Energy~5 GWQ4 2025Firm commitments, HoustonFirst figure in this series~12 GWQ3 2026Batch Zero eligible
NiSource3.9 GWQ3 2026Signed customer capacity+800 MW since Q2 20269 GWQ3 2026pipeline by 2035
PG&E3.88 GWQ3 2026Signed, paid work agreementsNone since Q2 202612.87 GWQ3 2026applications
Alliant Energy3.4 GWQ3 2026Service agreementsNone since Q2 20262 to 4 GWQ3 2026advanced discussions
Ameren3.4 GWQ2 2026Q3 2026 pendingConstruction agreements, MissouriNone since Q1 20264 GWQ2 2026proposed projects
Evergy~2.6 GWQ2 2026Q3 2026 pendingService agreements+100 MW since Q1 202615+ GWQ4 2025total pipeline
DTE Energy2.4 GWQ2 2026Q3 2026 pendingExecuted agreementsFirst figure in this series5 to 6 GWQ2 2026additional pipeline
Xcel Energy~2 GWQ3 2026Contracted or under constructionNone since Q2 202620 GWQ3 2026additional pipeline
CMS Energy1+ GWQ2 2026One customerNone since Q1 2026~9 GWQ2 2026all sectors
Portland General Electric473 MWQ3 2026Executed, under construction+43 MW since Q4 20251.3 GWQ3 2026requests
Black Hills Corp.Not reportedQ3 2026 pending1 known project in its territory3+ GWQ2 2026pipeline
EntergyNot reported7 GWQ3 2025pipeline
ExelonNot reported3 known projects in its territory~23 GWQ3 2026future pipeline
NextEra EnergyNot reported2 known projects in its territory~21 GWQ2 2026FPL large-load interest
Oncor Electric DeliveryNot reportedQ3 2026 pending1 known project in its territory~282 GWQ2 2026interconnection queue
PSEGNot reported~11.8 GWQ4 2025inquiries
TXNM EnergyNot reportedNot reported
WEC Energy GroupNot reported2 known projects in its territory3.2+ GWQ3 2026forecast, named customers

Quarter by quarter, utility by utility

Open a utility to see every figure it reported each quarter, each linked to the filing that printed it. "Not stated" means it filed results that quarter without that figure.

Alliant EnergySigned: 3.4 GWPipeline: 2 to 4 GW

Iowa, Wisconsin

FigureQ1 2025Q2 2025Q3 2025Q4 2025Q1 2026Q2 2026Q3 2026
Contracted data center demand (executed electric service agreements, peak demand)~2.1 GW~2.1 GW3 GW~3 GW~3.4 GW~3.4 GW3.4 GW
Active negotiations for additional loadNot statedNot stated~2 to 4 GW~2 to 4 GWNot statedNot statedNot stated
Advanced discussions of large load prospectsNot statedNot statedNot statedNot statedNot statedNot stated2 to 4 GW

Signed contracts figure: Executed electric service agreements.

AmerenSigned: 3.4 GWPipeline: 4 GW

Missouri, Illinois

FigureQ1 2025Q2 2025Q3 2025Q4 2025Q1 2026Q2 2026Q3 2026
Ameren Missouri construction agreements signed (data center developers)2.3 GW~2.3 GW~3 GW3.4 GW3.4 GW3.4 GWNot yet reported
Ameren Missouri electric service agreements executed with large load customersNot statedNot statedNot stated2.2 GW2.8 GW2.8 GWNot yet reported
Ameren Illinois construction agreements with developersNot statedNot statedNot stated850 MW850 MWNot statedNot yet reported
Ameren Missouri proposed projects with completed interconnection studiesNot statedNot statedNot statedNot statedNot stated4 GWNot yet reported

Signed contracts figure: Ameren Missouri construction agreements with developers.

American Electric PowerSigned: 84 GWPipeline: 190 GW

Ohio, Texas, Indiana, Michigan, Kentucky, West Virginia, Virginia, Tennessee, Oklahoma, Louisiana, Arkansas

FigureQ1 2025Q2 2025Q3 2025Q4 2025Q1 2026Q2 2026Q3 2026
New power demand expected by the end of the decade20+ GWNot statedNot statedNot statedNot statedNot statedNot stated
Incremental load by 2030 backed by signed customer agreements (ESAs or letters of agreement)Not stated24 GW28 GW56 GW63 GW69 GWNot stated
Incremental contracted load by 2031 (fully executed ESAs or letters of agreement)Not statedNot statedNot statedNot statedNot statedNot stated84 GW
Load requests at various stages of developmentNot stated190+ GW190 GWNot statedNot statedNot statedNot stated
AEP Texas incremental load backed by signed letters of agreement, by 2030Not statedNot statedNot stated36 GW41 GW~45 GWNot stated
AEP Texas incremental load backed by executed letters of agreement, by 2031Not statedNot statedNot statedNot statedNot statedNot stated~49 GW

Signed contracts figure: Signed agreements for load through 2031. Includes load from customers other than data centers.

AEP moved its contracted figure from load through 2030 to load through 2031 in the third quarter of 2026, so the two horizons are shown as separate rows.

Black Hills Corp. (Black Hills Energy, Wyoming Electric)Signed: not reportedPipeline: 3+ GW1 known project

Cheyenne, Wyoming; also South Dakota, Colorado and other Black Hills service areas

FigureQ1 2025Q2 2025Q3 2025Q4 2025Q1 2026Q2 2026Q3 2026
Data center demand included in five-year plan (existing customers Microsoft and Meta)500 MW500+ MW500 MW600+ MW600+ MW600 MWNot yet reported
Data center pipeline (large-load requests, incl. under NDA)1+ GW1+ GW3+ GW3+ GW3+ GW3+ GWNot yet reported
Prospective data center project with generation reservation agreementNot statedNot statedNot statedNot stated1.8 GW1.8 GWNot yet reported

Known projects in its territory

Announced by developers, not reported by Black Hills Corp. An announcement is not a signed utility contract.

CenterPoint Energy (Houston Electric)Signed: ~5 GWPipeline: ~12 GW

Greater Houston, Texas (ERCOT); also Indiana Electric

FigureQ1 2025Q2 2025Q3 2025Q4 2025Q1 2026Q2 2026Q3 2026
Houston Electric interconnection requests (all load types)Not statedNot stated~60 GWNot statedNot statedNot statedNot stated
Data center load firmly committed (signed study commitments, site control, materials/labor), expected energized by YE 2028Not statedNot statedNot stated~5 GWNot statedNot statedNot stated
Data center load under constructionNot statedNot statedNot stated~2.5 GW3.5 GWNot statedNot stated
Data center load expected to be energized by year-end 2028Not statedNot statedNot stated~7.5 GWNot statedNot statedNot stated
Data center load expected to be energized by 2029Not statedNot statedNot statedNot stated8 GWNot statedNot stated
Firmly committed large industrial load at Houston Electric (all industries, includes data centers)Not statedNot statedNot statedNot stated12.2 GWNot statedNot stated
Large load projects submitted through ERCOT Batch ZeroNot statedNot statedNot statedNot statedNot stated17+ GWNot stated
Batch Zero large load expected to be eligible as base load or studied loadNot statedNot statedNot statedNot statedNot stated14+ GW~12 GW

Signed contracts figure: Firm commitments for its Houston system, Q4 2025. Later figures include all industry.

Most CenterPoint figures are for its Houston system. Its Batch Zero figures are large loads submitted to the Texas grid operator, not all of them data centers.

CMS Energy (Consumers Energy)Signed: 1+ GWPipeline: ~9 GW

Lower Peninsula of Michigan

FigureQ1 2025Q2 2025Q3 2025Q4 2025Q1 2026Q2 2026Q3 2026
Economic development load pipeline, all sectors (data centers, manufacturing, semiconductor)9 GW~9 GW9 GWNot stated~9 GW~9 GWNot stated
Large data center agreement (single new data center customer)Not stated1 GW1 GW1+ GW1+ GW1+ GWNot stated
Switch data center contracted load~230 MW~230 MWNot statedNot statedNot statedNot statedNot stated

Signed contracts figure: One signed data center customer.

The economic development pipeline covers manufacturing and other industry as well as data centers.

Dominion Energy (Dominion Energy Virginia)Signed: 12.2 GWPipeline: ~54.9 GW

Virginia and northeastern North Carolina (Dominion Energy Virginia); South Carolina

FigureQ1 2025Q2 2025Q3 2025Q4 2025Q1 2026Q2 2026Q3 2026
Dominion Energy Virginia data center contracted capacity (ESA + CLOA + engineering LOA)Not statedNot stated~47.1 GW~48.5 GW~51 GW~53.8 GW~54.9 GW
Data center contracted capacity under Electric Service Agreements (ESA)Not statedNot stated9.8 GW10.2 GW10.4 GW12 GW12.2 GW
Data center contracted capacity under Construction Letters of Authorization (CLOA)Not statedNot stated9 GW11 GW11.1 GW9.4 GW9.8 GW
Data center contracted capacity under Substation Engineering Letters of Authorization (SELOA; called ELOA in 2026Q3)Not statedNot stated28.2 GW27.4 GW29.5 GW32.4 GW32.8 GW

Signed contracts figure: Electric service agreements. Dominion also reports ~54.9 GW including construction and engineering letters.

The total is the sum of three contract stages Dominion charts each quarter: electric service agreements, construction letters and engineering letters.

DTE Energy (DTE Electric)Signed: 2.4 GWPipeline: 5 to 6 GW

Southeast Michigan

FigureQ1 2025Q2 2025Q3 2025Q4 2025Q1 2026Q2 2026Q3 2026
Non-binding agreements to serve data center load~2.1 GWNot statedNot statedNot statedNot statedNot statedNot yet reported
Executed data center agreement (Oracle, Saline Township)Not statedNot stated~1.4 GW~1.4 GW1.4 GW1.4 GWNot yet reported
Executed data center agreement (Google, Van Buren Township)Not statedNot statedNot statedNot stated1 GW1 GWNot yet reported
Executed data center agreements, totalNot statedNot statedNot statedNot statedNot stated2.4 GWNot yet reported
Hyperscaler load in advanced discussionsNot stated3+ GW~3 GW~3 GW~2 GW2 GWNot yet reported
Additional data center pipeline beyond executed agreementsNot statedNot stated6+ GW6 GW~5 GW5 to 6 GWNot yet reported

Signed contracts figure: Executed data center agreements.

Duke EnergySigned: ~7.8 GWPipeline: ~15.4 GW

North Carolina, South Carolina, Florida, Indiana, Ohio, Kentucky

FigureQ1 2025Q2 2025Q3 2025Q4 2025Q1 2026Q2 2026Q3 2026
New letter agreements signed for data centers~1 GWNot statedNot statedNot statedNot statedNot statedNot yet reported
Data center Electric Service Agreements signed (select announced large load project ESAs, 2025 signings)Not statedNot stated~3 GW~4.5 GWNot statedNot statedNot yet reported
Total data center capacity secured under Electric Service Agreements (includes 2024 signings)Not statedNot statedNot statedNot stated~7.6 GW~7.8 GWNot yet reported
High-confidence, late-stage large load pipelineNot statedNot statedNot statedNot stated~15.4 GW~15.4 GWNot yet reported
Data centers under constructionNot statedNot statedNot statedNot stated~5 GW~5.2 GWNot yet reported

Signed contracts figure: Electric service agreements, including 2024 contracts.

Duke restated its contract figure in 2026 to include 2024 contracts, so the 2025 and 2026 figures are separate rows.

EntergySigned: not reportedPipeline: 7 GW

Louisiana, Arkansas, Mississippi, Texas, New Orleans

FigureQ1 2025Q2 2025Q3 2025Q4 2025Q1 2026Q2 2026Q3 2026
Data center pipeline (potential data center customers)Not statedNot stated7 GWNot statedNot statedNot statedNot stated
EvergySigned: ~2.6 GWPipeline: 15+ GW

Kansas, Missouri

FigureQ1 2025Q2 2025Q3 2025Q4 2025Q1 2026Q2 2026Q3 2026
ESAs signed with large load customers to serve data centers (projected peak steady-state load)Not statedNot statedNot stated~1.9 GW~2.5 GW~2.6 GWNot yet reported
Large customer pipeline (total)~12.2 GW15+ GW~15 GW15+ GWNot statedNot statedNot yet reported
Tier 1 large load customer pipeline (Actively Building + Finalizing Agreements + Advanced Discussions)Not stated4 to 6 GW4 to 6 GWNot statedNot statedNot statedNot yet reported
Large customer pipeline: Actively Building1.1 GW~1.1 GW~1.2 GWNot statedNot statedNot statedNot yet reported
Large customer pipeline: Finalizing Agreements~1.3 GW~1 to 1.5 GW~1.5 to 2 GWNot statedNot statedNot statedNot yet reported
Tier 1 Active Operations and Signed ESAsNot statedNot statedNot stated~2.4 GW~3 GW~3 GWNot yet reported
Tier 1 Expansion Opportunities (existing customers with signed ESAs)Not statedNot statedNot statedNot stated~1 to 1.5 GW~2 to 2.5 GWNot yet reported
Large customer pipeline: Advanced Discussions~2.9 GW~2 to 3.5 GW~2 to 3 GW~2 to 3.5 GW~1.5 to 3 GW~1 to 2 GWNot yet reported
Balance of pipeline / incremental pipeline not yet in active queue~7 GWNot stated10+ GW10+ GW10+ GW10+ GWNot yet reported

Signed contracts figure: Electric service agreements.

Evergy reorganized its pipeline tiers twice in 2025. Each new tier is its own row.

Exelon (ComEd, PECO, BGE, Pepco, Delmarva, ACE)Signed: not reportedPipeline: ~23 GW3 known projects

Northern Illinois, Philadelphia region, Maryland, Washington DC, Delaware, southern New Jersey

FigureQ1 2025Q2 2025Q3 2025Q4 2025Q1 2026Q2 2026Q3 2026
Large load pipeline (data center and other large load projects in an official phase of engineering with deposits paid, not yet in service)17 GW17 GW19 GW~19 GWNot statedNot statedNot stated
Data center pipeline (committed data center projects, Phases 1-3, excluding other large load)Not statedNot stated18 GWNot stated~18 GWNot statedNot stated
High probability load (data center projects in advanced phases of design or backed by FERC-approved TSAs)Not statedNot statedNot statedNot statedNot stated~11 GW~11 GW
Future pipeline (data center load within current or future cluster studies)Not statedNot statedNot statedNot statedNot stated~25 GW~23 GW

Exelon replaced its single pipeline figure with high-probability and future pipeline figures in the second quarter of 2026.

Known projects in its territory

Announced by developers, not reported by Exelon. An announcement is not a signed utility contract.

FirstEnergySigned: 7.88 GWPipeline: 19.07 GW

Ohio, Pennsylvania, New Jersey, West Virginia, Maryland

FigureQ1 2025Q2 2025Q3 2025Q4 2025Q1 2026Q2 2026Q3 2026
Active or contracted data center demand included in the 2025-2029 plan2.6 GWNot statedNot statedNot statedNot statedNot statedNot stated
Cumulative large load studies received since January 2024 (GW studied, not committed)80+ GW95+ GWNot statedNot statedNot statedNot statedNot stated
Contracted data center demand, cumulative to 2029F (contract to construct facilities)Not stated~2.69 GWNot statedNot statedNot statedNot statedNot stated
Long-term data center pipeline demand (large load connections requested with reasonable assumption of construction), cumulative to end of forecast horizonNot stated11.13 GW~11.7 GW12.9 GW14.87 GW18.43 GW19.07 GW
Long-term contracted data center demand (contract to construct facilities and/or an electric service agreement), cumulative to end of forecast horizonNot statedNot stated3.8+ GW4.08 GW4.25 GW6.36 GW7.88 GW

Signed contracts figure: Contracts to build facilities or service agreements.

FirstEnergy widened its contracted figure in the third quarter of 2025 to include service agreements and a longer horizon, so the earlier figure is a separate row.

NextEra Energy (Florida Power & Light; NextEra Energy Resources)Signed: not reportedPipeline: ~21 GW2 known projects

Florida (FPL); NextEra Energy Resources nationwide

FigureQ1 2025Q2 2025Q3 2025Q4 2025Q1 2026Q2 2026Q3 2026
FPL large-load interest (GW of interest from hyperscalers and other large customers)Not statedNot statedNot stated~20 GW~21 GW~21 GWNot stated
FPL large-load interest in advanced discussionsNot statedNot statedNot stated~9 GW~12 GW12 GWNot stated
FPL large-load expectation by 2032 (planning assumption)Not statedNot statedNot statedNot statedNot stated8 GW8 GW
NextEra Energy Resources backlog projects intended to serve technology and data center customers (generation)Not stated~6 GWNot statedNot statedNot statedNot statedNot stated
NextEra Energy Resources capacity serving technology and data center customers, operating plus expected backlog buildout (generation)Not stated10.5+ GWNot statedNot statedNot statedNot statedNot stated
NextEra Energy Resources base-case goal of new generation for data center hubs / large load by 2035 ('15 by 35')Not statedNot statedNot stated15 GW15 GW15 GWNot stated
NextEra Energy Resources federal hub gas generation selected by U.S. Department of Commerce to serve large load (Texas and Pennsylvania)Not statedNot statedNot statedNot stated9.5 GWNot statedNot stated
NextEra Energy Resources federal hub projects with signed definitive agreements (Texas and Pennsylvania)Not statedNot statedNot statedNot statedNot statedNot stated~16.5 GW
NextEra Energy Resources data center hub origination channel, Federal Hubs plus Paducah HubNot statedNot statedNot statedNot statedNot statedNot stated20 GW

FPL figures are customer demand in Florida. The NextEra Energy Resources rows are generation it plans to build for data centers, not utility load.

Known projects in its territory

Announced by developers, not reported by NextEra Energy. An announcement is not a signed utility contract.

  • 16 MW Iron Mountain, MIA-1. In FPL's area on the federal utility territory map.
  • 9.2 MW RadiusDC, Miami I expansion. In FPL's area on the federal utility territory map.
NiSource (NIPSCO)Signed: 3.9 GWPipeline: 9 GW

Northern Indiana

FigureQ1 2025Q2 2025Q3 2025Q4 2025Q1 2026Q2 2026Q3 2026
Signed data center customer capacity requirementNot statedNot stated2.4 GW2.4 GW3.1 GW3.1 GW3.9 GW
GenCo strategic negotiations (additional data center load)Not statedNot stated1 to 3 GW1 to 3 GW3 GW3 GW2 GW
Additional developing data center opportunitiesNot statedNot stated3 GW3 GW2 GW2 GW2 GW
Data center pipeline by 2035, including signed customer capacityNot statedNot stated9 GW9 GW9 GW9 GW9 GW

Signed contracts figure: Signed data center customer capacity.

Oncor Electric DeliverySigned: not reportedPipeline: ~282 GW1 known project

North, Central and West Texas (ERCOT)

FigureQ1 2025Q2 2025Q3 2025Q4 2025Q1 2026Q2 2026Q3 2026
Data center load in Oncor's active large commercial and industrial (LC&I) transmission interconnection queue156+ GW~186 GW210+ GW~255 GW~271 GW~282 GWNot yet reported
Large-load requests expected to be eligible for ERCOT Batch Zero on Oncor's system (base or studied load)Not statedNot statedNot statedNot statedNot stated~44 GWNot yet reported

The queue counts requests for service, not signed contracts.

Known projects in its territory

Announced by developers, not reported by Oncor Electric Delivery. An announcement is not a signed utility contract.

  • 220 MW STACK Infrastructure, Dallas campus. The source names an on-site Oncor substation.
PG&ESigned: 3.88 GWPipeline: 12.87 GW

Northern and Central California

FigureQ1 2025Q2 2025Q3 2025Q4 2025Q1 2026Q2 2026Q3 2026
Data center pipeline, total MW (applications for new data center load of 20 MW or more), original methodology8.7 GW10 GW9.6 GW7.25 GW5.39 GWNot statedNot stated
Data center pipeline: MW in Final Engineering, original methodology1.4 GW1.5 GW1.6 GW3.55 GW3.55 GWNot statedNot stated
Data center pipeline, total MW (20 MW+ applications; Application & Preliminary Engineering stage requires the $500,000 Preliminary Engineering Study fee paid)Not statedNot statedNot statedNot statedNot stated12.71 GW12.87 GW
Data center pipeline: MW in Final Engineering (executed Work Performance Agreement with design and procurement payments begun)Not statedNot statedNot statedNot statedNot stated3.88 GW3.88 GW
New data center load energized since 2024 (MW)Not statedNot statedNot statedNot statedNot statedNot stated174 MW

Signed contracts figure: Projects in final engineering with a signed, paid work agreement.

PG&E changed how it counts its pipeline in the second quarter of 2026. Projects now need a paid study fee to count, so the new series starts there and is not comparable with earlier quarters.

Pinnacle West (APS)Signed: 5.8 GWPipeline: ~20 GW

Arizona

FigureQ1 2025Q2 2025Q3 2025Q4 2025Q1 2026Q2 2026Q3 2026
APS committed load (large customers incl. manufacturing and data centers, not data center only)Not statedNot stated~4.5 GW~4.5 GW~4.5 GW~4.5 GW5.8 GW
APS uncommitted load opportunityNot statedNot stated~20 GW~20 GW~20 GW~20 GW~20 GW

Signed contracts figure: Committed load from all large customers. Includes load from customers other than data centers.

Both APS figures cover all large customers, including manufacturing, not only data centers.

Portland General ElectricSigned: 473 MWPipeline: 1.3 GW

Portland and Hillsboro, Oregon

FigureQ1 2025Q2 2025Q3 2025Q4 2025Q1 2026Q2 2026Q3 2026
Executed contracts with data center customersNot statedNot statedNot stated430 MWNot statedNot stated473 MW
Additional 2026 executed data center contract, not yet under constructionNot statedNot statedNot statedNot statedNot statedNot stated420 MW
Additional incremental large load requestsNot statedNot statedNot stated1.7 GWNot statedNot stated1.3 GW

Signed contracts figure: Executed contracts under construction, plus 420 MW signed and not yet built.

PPL CorpSigned: 11+ GWPipeline: 31.8 GW

Eastern and central Pennsylvania (PPL Electric); Kentucky (LG&E and KU)

FigureQ1 2025Q2 2025Q3 2025Q4 2025Q1 2026Q2 2026Q3 2026
PPL Electric data center requests in advanced stages (signed agreements with developers), Pennsylvania~11 GW14.4 GW20.5 GW25.2 GW28.3 GW31.8 GWNot yet reported
PPL Electric data center load under signed Electric Service Agreements (ESAs), PennsylvaniaNot statedNot statedNot statedNot stated~10 GW11+ GWNot yet reported
PPL Electric data center load under construction, PennsylvaniaNot statedNot stated5 GW5 GW~5 GW6.5+ GWNot yet reported
Additional active data center requests, Pennsylvania (2026 to 2034)50+ GW50+ GWNot statedNot statedNot statedNot statedNot yet reported
Data center requests / data center-related load in the LG&E and KU economic development queue, Kentucky~6 GW~6 GW8.7 GW8 GW11.9 GW11.6 GWNot yet reported

Signed contracts figure: Electric service agreements, Pennsylvania.

PSEG (PSE&G)Signed: not reportedPipeline: ~11.8 GW

New Jersey

FigureQ1 2025Q2 2025Q3 2025Q4 2025Q1 2026Q2 2026Q3 2026
PSE&G large load inquiries for new service connections (MW of capacity requested)6.4+ GW9.4+ GW~11.5 GW~11.8 GWNot statedNot statedNot stated

PSEG reported large load inquiries through the end of 2025 and has not reported them since.

Southern Company (Georgia Power, Alabama Power, Mississippi Power)Signed: 11+ GWPipeline: 75+ GW

Georgia, Alabama, Mississippi

FigureQ1 2025Q2 2025Q3 2025Q4 2025Q1 2026Q2 2026Q3 2026
Contracted large load customers (system, per earnings deck)6 GW6 GW8 GW10 GW11+ GWNot statedNot yet reported
Contracted large load customers, including agreements fully agreed with the customer and subject to regulator review (per earnings deck)Not statedNot statedNot statedNot statedNot stated17 GWNot yet reported
Committed large load10 GW10 GWNot statedNot statedNot statedNot statedNot yet reported
System large load pipeline (through the mid-2030s)50+ GW50+ GW50+ GWNot statedNot statedNot statedNot yet reported
Prospective large load pipeline (early to mid-stage customers that have requested service)Not statedNot statedNot stated75+ GW75+ GW75+ GWNot yet reported
Contracts since 2023 with new data centers and other large load customers, each over 100 MW, signed and/or reviewed by state regulators (SEC filing)Not statedNot statedNot stated~9 GW~11 GWNot statedNot yet reported
Large Load Contracts since 2023 (each over 100 MW) reviewed by the applicable state PSC (SEC filing)Not statedNot statedNot statedNot statedNot stated~11 GWNot yet reported
Total Large Load Contracts since 2023, reviewed plus agreed and pending PSC review (SEC filing)Not statedNot statedNot statedNot statedNot stated~16 GWNot yet reported
Data center system load onlineNot statedNot statedNot statedNot statedNot stated1.2+ GWNot yet reported

Signed contracts figure: Contracted large load. Its Q2 2026 deck shows 17 GW including contracts awaiting regulator review. Includes load from customers other than data centers.

Southern tightened its definition of contracted in 2026, adding a row that includes agreements awaiting regulator review.

TXNM Energy (PNM and TNMP)Signed: not reported

New Mexico (PNM); Texas (TNMP)

FigureQ1 2025Q2 2025Q3 2025Q4 2025Q1 2026Q2 2026Q3 2026
TNMP data center load in service670 MWNot statedNot statedNot statedNot statedNot statedNot stated
WEC Energy GroupSigned: not reportedPipeline: 3.2+ GW2 known projects

Wisconsin, Michigan Upper Peninsula

FigureQ1 2025Q2 2025Q3 2025Q4 2025Q1 2026Q2 2026Q3 2026
Expected load growth in the Milwaukee-to-Chicago corridor (Microsoft data centers), up toNot statedNot statedNot stated2.6+ GW2.6+ GW2.6+ GW3.2+ GW
Vantage Data Centers Port Washington campus, forecast demandNot statedNot statedNot stated1.3 GW1.3 GW1.3 GW1.3 GW
Forecast electric demand added over the five-year planNot statedNot stated~3.4 GWNot statedNot statedNot stated~4.9 GW

The corridor and Port Washington figures are forecasts for named data center customers.

Known projects in its territory

Announced by developers, not reported by WEC Energy Group. An announcement is not a signed utility contract.

Xcel EnergySigned: ~2 GWPipeline: 20 GW

Minnesota, Colorado, Texas/New Mexico, Wisconsin

FigureQ1 2025Q2 2025Q3 2025Q4 2025Q1 2026Q2 2026Q3 2026
Data center load growth: total customer requests~8.9 GW~8.9 GWNot statedNot statedNot statedNot statedNot stated
Data center pipeline: contracted / under constructionNot statedNot stated~1 GW2 GW~2 GW~2 GW~2 GW
Data center pipeline: high-probability pipelineNot statedNot stated~2 GW~4 GWNot statedNot statedNot stated
Data center pipeline: contracted by year end 2027 (target)Not statedNot statedNot statedNot stated~4 GW~4 GW~4 GW
Data center pipeline: additional pipelineNot statedNot stated20 GW20 GW20 GW20 GW20 GW

Signed contracts figure: Contracted or under construction.

Xcel replaced its total customer requests figure with a three-tier data center pipeline in the third quarter of 2025.

IDACORP, OGE Energy filed results every quarter without putting a megawatt figure on data center demand.

How to read these numbers

A pipeline is not power anyone can buy. It counts customers asking a utility for service. Many of those requests are duplicates filed with several utilities at once, and many will never be built.

A contract is firmer. A signed electric service agreement usually commits the customer to pay for capacity, so a contracted figure moves slowly and rarely falls.

Each utility defines its own figure. One counts signed agreements, another counts every application above 20 MW, another counts load in the grid operator's queue. That is why this page never adds them up. Compare a utility with itself over time.

Where the numbers come from. Each quarter we read the earnings release, the investor presentation and the quarterly report each utility files with the SEC. Some utilities post their slides only on their own investor site, and in that case the link goes there. News coverage is never the source.

Pipeline figures describe demand for power, not data center space. A building can have power and still have no space to lease, and the reverse. Construction filings are tracked separately on the construction pipeline page.

Need space that already has power?

Utility queues are why new capacity takes years. Tell us your load and date, and a scout will come back with buildings that can energize it.

Add your name, company or phone Optional

Free to you. Powered by Bridgepointe Technologies, trusted by NVIDIA, Microsoft, Charles Schwab and 75+ Fortune 500 companies. A scout replies within one business day.