The disclosure and our analysis
Evidence dates
Evidence: City of Denton planning project record S26-0006 (Specific Use Permit layer), submitted November 9, 2026, status date November 13, 2026, added to the city's map November 17, 2026. City of Denton council agenda items dated January 13, 2026 and August 18, 2026. City of Denton pre-application records PAC24-0110 and PAC25-0030. All read November 23, 2026.
What the city record shows
1. **Case and type:** Project ID S26-0006, project name Birddog, project type Specific Use Permit. [Source 1]
2. **Site:** The description reads: Specific Use Permit for a data center situated on 23.8 ac., generally located South of E. University Dr. and West of Geesling Rd. Zoned: Light Industrial (LI). Not Platted. The address field lists E University Dr, and the record carries property ID 36752. [Source 1]
3. **Dates and status:** Submitted November 9, 2026. Status Under Review, with a status date of November 13, 2026. The city's simplified status reads Under Development Review. [Source 1]
4. **Applicant:** The applicant field reads McAdams, Candy Whitaker. The record does not name the developer, owner or end user behind the Birddog project name. [Source 1]
5. **Hearings:** The Planning and Zoning Commission and City Council date and decision fields are empty, so no hearing had been set in the record as of November 13, 2026. [Source 1]
How a Denton data center permit moves
A Specific Use Permit goes to a public hearing and a council ordinance. The closest precedent in the city's records is S25-0007a, a Specific Use Permit for a Modular Data Center use on approximately 4.064 acres in the Westpark Addition, south of Jim Christal Road. The Planning and Zoning Commission voted 6-0 to recommend approval, and the item went to a City Council public hearing on January 13, 2026. The agenda item we reviewed does not record the council's final vote. [Source 2]
At 23.8 acres, the S26-0006 site is a little under six times the land area of that 4.064 acre request. Land area alone does not establish building size or power. [Source 1] [Source 2]
The moratorium question
On August 18, 2026, the City Council agenda carried item ID 26-1287, a resolution regarding a moratorium on the acceptance, processing, and approval of applications for the development of data centers within the city limits, and a schedule for the required notices and public hearings. [Source 3]
The city records we reviewed do not show whether a moratorium has been adopted, when it would take effect, or how it would treat an application already filed, such as S26-0006 on November 9, 2026. Buyers and developers tracking this site should treat that as open until the city publishes an adopted ordinance.
Earlier interest in Denton data center sites
The city's pre-application records show two earlier data center inquiries, both now closed: PAC24-0110, a data center warehouse development on 157.2 acres south of Jim Christal Rd. and west of N. Masch Branch, and PAC25-0030, a data center development on 4.256 acres west of the I-35E and I-35W interchange. A closed pre-application conference is not a permit application. [Source 4]
Buyer analysis
This is our analysis, not a city finding. S26-0006 is an early zoning step for a site with no disclosed power, tenant or schedule. It is not capacity that a colocation buyer can contract for. Its value to buyers is as an early signal in the northern Dallas and Fort Worth area, where a new site would need a Specific Use Permit and, per the city record, starts on Light Industrial land that has not been platted.
Questions worth asking anyone marketing space here: who the developer and end user are, which utility will serve the site and at what confirmed load, the hearing schedule for S26-0006, and whether any city moratorium affects the application.