Colocation Scout / News & Analysis

CleanSpark's 585 MW Sealy and Brazoria, Texas sites: tenant exclusivity expired, conditional ERCOT Batch Zero status

CleanSpark said on November 24, 2026 that the exclusivity period covering its Sealy and Brazoria, Texas campuses has expired, and that commercialization is proceeding with its existing Sandersville tenant and others. In the same fiscal fourth quarter release, the company reported a Conditional Batch Zero Baseload designation on 585 MW: 285 MW at Sealy and 300 MW at Brazoria Phase 1. It disclosed no Texas lease. [Source 1]

CleanSpark's 585 MW Sealy and Brazoria, Texas sites: tenant exclusivity expired, conditional ERCOT Batch Zero status
All news & analysisDevelopment & PowerSealy and Brazoria campuses, TexasAnnounced sites with conditional grid designations (CleanSpark reports Conditional Batch Zero Baseload designation on 585 MW and Conditional Batch Zero Studied Load for Brazoria Phase 2, up to 300 MW, as of November 24, 2026). Tenant exclusivity expired. No lease disclosed. Not available capacity.

Disclosed terms

Exclusivity
Expired at Sealy and Brazoria; commercialization proceeding with the existing Sandersville tenant and others [1]
Grid designation
Conditional Batch Zero Baseload on 585 MW: 285 MW Sealy, 300 MW Brazoria Phase 1 [1]
Brazoria Phase 2
Conditional Batch Zero Studied Load, up to 300 MW [1]
Brazoria permits
TCEQ permits received, per CleanSpark; scope not stated [1]
July exclusivity
Sandersville tenant's letter of intent and exclusivity covered 718 acres with up to 885 MW of secured and planned power capacity [2]
Sandersville tenant
Anviran, LLC, described as a wholly owned subsidiary of Meta [3]
Washington, Georgia
86 MW energized, grid-connected; line study submitted to raise power to 500 MW; 500 adjacent acres acquired [1]

The disclosure and our analysis

Evidence dates

Evidence: CleanSpark fiscal fourth quarter and full year 2026 results, Exhibit 99.1 to a Form 8-K, dated November 24, 2026. CleanSpark Sandersville lease announcement, Exhibit 99.1 to a Form 8-K, dated July 14, 2026. CleanSpark investor presentation, Exhibit 99.1 to a Form 8-K, dated September 17, 2026. All read November 25, 2026.

What CleanSpark disclosed on November 24

Under a Texas Portfolio heading in its fiscal 2026 results, CleanSpark lists these items, all as company statements: [Source 1]

1. **Sites:** Strategic acquisitions of Sealy (285 MW) and Brazoria (up to 600 MW) assets.

2. **Grid status:** A Conditional Batch Zero Baseload designation on 585 MW, made up of 285 MW in Sealy and 300 MW in Brazoria Phase 1, and a Conditional Batch Zero Studied Load designation for Brazoria Phase 2, up to 300 MW. Batch Zero refers to ERCOT's batch process for large load interconnection requests, where CenterPoint has also reported base load and studied load classifications.The release describes both designations as conditional and does not list the conditions.

3. **Exclusivity:** In the company's words, the exclusivity period at Sealy and Brazoria expired during a period of temporary regulatory uncertainty, and commercialization efforts are proceeding with the existing Sandersville tenant and others.

4. **Permits:** CleanSpark says it received TCEQ permits for the Brazoria project. The release does not say which permits, or what they cover.

What the July exclusivity covered

On July 14, 2026, when CleanSpark announced its 20-year Sandersville, Georgia lease for 175 MW of critical IT load, it said the same tenant had executed a letter of intent and exclusivity arrangement covering its entire Texas portfolio. CleanSpark described that portfolio as 718 acres with up to 885 MW of secured and planned power capacity: 271 acres with nearly 300 MW at Sealy, and 447 acres at Brazoria, where it said transmission-level infrastructure supports an initial 300 MW demand load with the potential to expand to 600 MW. [Source 2]

CleanSpark's September 17, 2026 investor presentation names the Sandersville tenant as Anviran, LLC, which it describes as a wholly owned subsidiary of Meta. [Source 3]

What the megawatt figures mean

The 585 MW figure is a grid load designation reported by the company. It is not critical IT load and not leasable space. The July release described the same sites on a different basis, secured and planned power capacity and demand load. None of the reviewed sources converts these figures into critical IT capacity for Texas, so they should not be compared directly with the 175 MW of critical IT load contracted at Sandersville. [Source 1] [Source 2]

Other sites in the same release

Sandersville, Georgia: CleanSpark says it has obtained all material building and development permits and remains on track for a first planned data hall in November 2027. [Source 1]

Washington, Georgia: CleanSpark reports 86 MW of currently energized, grid-connected power, a submitted high-density line study to raise power to 500 MW, and the purchase of 500 acres of adjacent land for a future AI data center campus. It says preliminary study results indicate the ability to support up to 500 MW of transmission capacity over the next several years. That 500 MW is a study figure, not a committed service level. [Source 1]

Buyer analysis

This is our analysis, not a company statement. The July filing tied up roughly 885 MW of Texas power capacity with one tenant. The November filing says that exclusivity has ended and that the sites are being commercialized with that tenant and others. For a large AI or hyperscale buyer looking at the Houston area or the wider ERCOT grid, Sealy and Brazoria are now sites that a party other than the Sandersville tenant could, in principle, negotiate for.

That is not the same as available capacity. Under this site's status terms, the Texas campuses are announced sites with conditional grid designations. No lease, construction start, energization date or delivery window has been disclosed for either. CleanSpark's July release put estimated landlord project costs at Sandersville at $10 to $12 million per MW of critical IT load. That figure is for Sandersville and is not a Texas price. [Source 2]

Questions worth asking: what conditions attach to the Batch Zero designations and when they are expected to become final, the critical IT load each campus is designed to deliver, the delivery schedule for the first block, and what the Brazoria TCEQ permits cover.

What remains unknown

The reviewed filings do not disclose the conditions attached to the Batch Zero designations, critical IT load for either Texas campus, a construction or energization schedule, the date the exclusivity ended, which TCEQ permits Brazoria received, or any pricing. They do not say whether the Sandersville tenant remains in talks for a specific Texas site or capacity.

Sources

  1. CleanSpark, fiscal Q4 and full year 2026 results (Form 8-K Exhibit 99.1) · Published 2026-11-24
  2. CleanSpark, Sandersville lease announcement (Form 8-K Exhibit 99.1) · Published 2026-07-14
  3. CleanSpark, investor presentation (Form 8-K Exhibit 99.1) · Published 2026-09-17

Explore the market

Related reporting

Development & Power

Denton, Texas data center permit S26-0006 seeks a Specific Use Permit for 23.8 acres off E. University Dr.

A Specific Use Permit application for a data center on 23.8 acres in Denton, Texas, south of E. University Dr. and west of Geesling Rd., was submitted to the City of Denton on November 9, 2026. The city's planning record lists it as case S26-0006, project name Birddog, on land zoned Light Industrial and not platted. Its status was Under Review as of November 13, 2026. The record lists no megawatts, end user or hearing date. [Source 1]

South of E. University Dr. and west of Geesling Rd., Denton, Denton County, Texas · Proposed (Specific Use Permit application S26-0006 submitted November 9, 2026; city status Under Review as of November 13, 2026). No hearing date set in the record. No megawatt figure, tenant or end user disclosed.
Read the analysis
Development & Power

Entergy Arkansas plans a second phase of service for Google's West Memphis data center campus, with about $600 million of grid work and a 440 MW solar contract paid for by Google

Entergy Arkansas announced on October 19, 2026 a second phase of electric service for Google's data center campus in West Memphis, Arkansas. The utility says the phase needs about $600 million of planned investment plus a power purchase agreement, all covered by Google: two battery systems, a 440 MW (ac) solar contract, an expanded Galet substation and two new 230 kV lines to serve the expanded campus. The expansion still has to be submitted to the Arkansas Public Service Commission; Entergy targets service in 2028 if it is approved. Entergy listed the expanded Google agreement among its third quarter highlights on November 2. [Source 1] [Source 2]

West Memphis, Crittenden County, Arkansas · Announced October 19, 2026; to be submitted to the Arkansas Public Service Commission for approval. Pending approval, Entergy expects service in 2028. Not approved as of November 2, 2026.
Read the analysis
Development & Power

San Antonio now requires a City Council vote on every new data center after a 9-2 code change

San Antonio City Council voted 9-2 on October 29, 2026 to pass data center regulations proposed by District 6 Councilmember Ric Galvan. The approach requires a Specific Use Authorization, a zoning approval voted on by council, for each new data center, rather than allowing data centers by right where they meet set standards. The mayor said the change ensures council can review each data center application. The final signed ordinance was not posted in the sources we reviewed. [Source 1] [Source 2] [Source 4]

San Antonio, Bexar County, Texas (city limits) · Approved: City Council passed the data center code change 9-2 on October 29, 2026. Final signed ordinance not reviewed.
Read the analysis