The disclosure and our analysis
Evidence dates
Evidence: CleanSpark fiscal fourth quarter and full year 2026 results, Exhibit 99.1 to a Form 8-K, dated November 24, 2026. CleanSpark Sandersville lease announcement, Exhibit 99.1 to a Form 8-K, dated July 14, 2026. CleanSpark investor presentation, Exhibit 99.1 to a Form 8-K, dated September 17, 2026. All read November 25, 2026.
What CleanSpark disclosed on November 24
Under a Texas Portfolio heading in its fiscal 2026 results, CleanSpark lists these items, all as company statements: [Source 1]
1. **Sites:** Strategic acquisitions of Sealy (285 MW) and Brazoria (up to 600 MW) assets.
2. **Grid status:** A Conditional Batch Zero Baseload designation on 585 MW, made up of 285 MW in Sealy and 300 MW in Brazoria Phase 1, and a Conditional Batch Zero Studied Load designation for Brazoria Phase 2, up to 300 MW. Batch Zero refers to ERCOT's batch process for large load interconnection requests, where CenterPoint has also reported base load and studied load classifications.The release describes both designations as conditional and does not list the conditions.
3. **Exclusivity:** In the company's words, the exclusivity period at Sealy and Brazoria expired during a period of temporary regulatory uncertainty, and commercialization efforts are proceeding with the existing Sandersville tenant and others.
4. **Permits:** CleanSpark says it received TCEQ permits for the Brazoria project. The release does not say which permits, or what they cover.
What the July exclusivity covered
On July 14, 2026, when CleanSpark announced its 20-year Sandersville, Georgia lease for 175 MW of critical IT load, it said the same tenant had executed a letter of intent and exclusivity arrangement covering its entire Texas portfolio. CleanSpark described that portfolio as 718 acres with up to 885 MW of secured and planned power capacity: 271 acres with nearly 300 MW at Sealy, and 447 acres at Brazoria, where it said transmission-level infrastructure supports an initial 300 MW demand load with the potential to expand to 600 MW. [Source 2]
CleanSpark's September 17, 2026 investor presentation names the Sandersville tenant as Anviran, LLC, which it describes as a wholly owned subsidiary of Meta. [Source 3]
What the megawatt figures mean
The 585 MW figure is a grid load designation reported by the company. It is not critical IT load and not leasable space. The July release described the same sites on a different basis, secured and planned power capacity and demand load. None of the reviewed sources converts these figures into critical IT capacity for Texas, so they should not be compared directly with the 175 MW of critical IT load contracted at Sandersville. [Source 1] [Source 2]
Other sites in the same release
Sandersville, Georgia: CleanSpark says it has obtained all material building and development permits and remains on track for a first planned data hall in November 2027. [Source 1]
Washington, Georgia: CleanSpark reports 86 MW of currently energized, grid-connected power, a submitted high-density line study to raise power to 500 MW, and the purchase of 500 acres of adjacent land for a future AI data center campus. It says preliminary study results indicate the ability to support up to 500 MW of transmission capacity over the next several years. That 500 MW is a study figure, not a committed service level. [Source 1]
Buyer analysis
This is our analysis, not a company statement. The July filing tied up roughly 885 MW of Texas power capacity with one tenant. The November filing says that exclusivity has ended and that the sites are being commercialized with that tenant and others. For a large AI or hyperscale buyer looking at the Houston area or the wider ERCOT grid, Sealy and Brazoria are now sites that a party other than the Sandersville tenant could, in principle, negotiate for.
That is not the same as available capacity. Under this site's status terms, the Texas campuses are announced sites with conditional grid designations. No lease, construction start, energization date or delivery window has been disclosed for either. CleanSpark's July release put estimated landlord project costs at Sandersville at $10 to $12 million per MW of critical IT load. That figure is for Sandersville and is not a Texas price. [Source 2]
Questions worth asking: what conditions attach to the Batch Zero designations and when they are expected to become final, the critical IT load each campus is designed to deliver, the delivery schedule for the first block, and what the Brazoria TCEQ permits cover.