What the public filing record shows
Most construction cost articles repeat one global average per megawatt without showing how much belongs to the shell, how much belongs to electrical and cooling fit-out, or how many months are lost inside municipal plan review before construction starts.
- Three cost layers explain the wide spread per MW. Bare county shell permits declare $0.6M to $2.9M per MW, combined state construction registrations declare $3.8M to $7.6M per MW (higher on small 3 to 5 MW builds), and SEC-filed turnkey completions and acquisitions reach $7.7M to $14.4M+ per MW.
- Interior fit-out and liquid cooling drive most of the bill. Vantage's 96 MW San Antonio build split 38% shell ($2.88M/MW) and 62% tenant fit-up ($4.67M/MW), while an August 2026 Aurora, Colorado permit declared $27.2M ($9.07M/MW) just to convert 3 MW inside an existing hall to liquid cooling.
- Permit approval adds 3 to 6+ months before construction begins. Across 898 issued data center permits filed from 2022 through 2026, median review ran 168 days for ground-up builds in Loudoun County and Prince William County, 156 days for $10M+ permits in San Antonio, 140 days for $10M+ builds in Irving, and 97 days for new builds in Mesa.
Declared construction cost per megawatt in public permits
Where a municipal permit or Texas accessibility registration states both an estimated construction cost and critical IT megawatts, the gap across build scopes becomes clear. Treat every declared permit number as a construction floor, not a full project budget: filings typically omit land, design fees, utility upgrades, and owner-supplied generators, UPS, or switchgear.
| Filing and market | Scope | Declared cost per MW | Stated capacity and total |
|---|---|---|---|
| CloudHQ 2-story build, Ashburn VA | Bare county shell | $0.58M/MW $54/sq ft | 96 MW, $55.7M, 1,030,408 sq ft (BLDC-2025-029746, issued Oct 2025) |
| Vantage TX12 shell, San Antonio TX | Core and shell | $2.88M/MW 38% of total | 96 MW, $276.9M, 432,800 gross sq ft (TABS2026001234) |
| Vantage TX12 fit-up, San Antonio TX | Tenant fit-out | $4.67M/MW $7.55M combined | 96 MW, $448.0M fit-out; $724.9M with shell (62% fit-out) |
| Digital Realty Garland, DFW TX | New construction | $3.75M/MW $446/sq ft | 80 MW across ten 8 MW suites, $300.0M, 672,000 sq ft |
| Soluna Project Kati II, Willacy Co. TX | AI campus build | $4.21M/MW $1,000/sq ft | 112 MW critical IT load, $471.8M, 471,884 sq ft |
| Stream DFWC1, Wilmer TX | New build + sub. | $6.25M/MW $832/sq ft | 48 MW, $300.0M, 360,750 sq ft, includes substation |
| Oppidan El Paso & Temple, TX | Small ground-up | $5.43M to $6.20M per MW (5 MW each) | $27.2M in El Paso (61,554 sq ft); $31.0M in Temple |
| Prime DC 3 MW buildout, Dallas TX | Small buildout + gen. | $15.83M/MW $1,379/sq ft | 3 MW, $47.5M, 34,438 sq ft, includes 4 generators and switchgear |
| Data hall fit-out, Ashburn VA | Interior fit-out | $1.86M/MW $619/sq ft | 14 MW across 2 floors, $26.0M, 42,000 sq ft (BLDC-2026-038611) |
| QTS DEN1 DC2 fit-out, Aurora CO | Hot-aisle fit-out | $4.19M/MW 60 MW TI | 60 MW tenant improvement inside shell, $251.6M (26-2614863-000-00) |
| QTS SAT2 DC1 fit-out, San Antonio TX | Interior fit-out | $4.44M/MW $852/sq ft | 9 MW fit-out, $40.0M, 46,975 sq ft (issued Nov 2023) |
| QTS DEN1 DC1 6 MW TI, Aurora CO | Interior fit-out | $6.84M/MW 6 MW TI | 6 MW data hall interior remodel, $41.1M (issued Jul 2026) |
| DEN1 DC1 liquid cooling, Aurora CO | LC conversion TI | $9.07M/MW 3 MW retrofit | 3 MW liquid-cooling conversion inside existing hall, $27.2M ($15.8M materials) |
Sources: each row links directly to its municipal permit record or Texas Department of Licensing and Regulation (TDLR) registration, checked November 23, 2026. Per-MW figures are our division of declared valuation by stated megawatts. Small builds (3 to 5 MW) and liquid-cooling retrofits carry steep fixed-equipment overhead per MW compared with 48 to 112 MW hyperscale halls.
How permit floors compare with SEC turnkey build costs and overruns
Public SEC filings bridge the gap between municipal permit floors and full turnkey delivery cost. Recent Q3 and Q4 2026 disclosures show both what completed megawatts trade for and how fast real construction budgets can move mid-build.
| SEC filing (Q3/Q4 2026) | Basis | Disclosed cost or value | Per MW and context |
|---|---|---|---|
| Fermi 45-deal capex ladder (Nov 12, 2026 8-K) | Industry capex benchmark | $3.9M to $15.0M per gross MW | Powered Land+ $3.9M to $5.1M; Powered Shell $5.1M to $6.6M; Turnkey $12.1M to $15.0M per gross MW. |
| Blackstone Trust / Amazon (Nov 16, 2026 8-K) | 13 newly built sites (IN, MS) | $5.0B gross $7.7M/MW | 647 MW IT load valued at 7.0% initial cap rate across 9 Indiana and 4 Mississippi buildings. |
| Blue Owl Gainesville, VA (Nov 10, 2026 8-K) | Completed leased building | $779.5M $14.4M/MW | 54 MW hyperscaler building in Prince William County bought with a $512.6M loan. |
| Cipher Barber Lake, TX (Oct 13, 2026 8-K) | All-in estimate at completion | $2.94B to $2.97B +36% to +38% | Up from $2.157B original budget ($359M change orders + $375M to $400M extra completion cost); two halls slipped one quarter. |
Sources: SEC Form 8-K filings linked above. Industry averages from JLL's 2026 Global Data Center Market Outlook sit at $11.3M/MW for a standard build and $15M to $20M+/MW for AI liquid-cooled builds before land; see our colocation vs. private build model and Q3 2026 SEC lease rate study.
First, counties like Loudoun value the structural shell separately from electrical, mechanical, and tenant fit-up permits. Second, owner-furnished equipment (generators, chillers, medium-voltage switchgear, UPS modules) frequently sits outside the general contractor's building permit valuation. Third, land and utility substation deposits are never inside a building permit: Northern Virginia industrial parcels have traded at $3.5M to $4.0M per acre, and Cipher's Barber Lake filing shows real-world change orders can add more than a third after groundbreaking.
Declared cost per square foot: why Loudoun reads $176 while Texas reads $960
Filtering 2022 to 2026 filings to substantial projects (at least 20,000 square feet and $5 million declared) shows how dramatically valuation reporting differs across jurisdictions. Comparing raw county totals across markets without separating shell permits from combined registrations produces misleading rankings.
| Jurisdiction and permit scope | Sample (2022 to 2026) | Median per sq ft | Middle half (IQR) |
|---|---|---|---|
| Loudoun County, VA (New construction shell) | 40 commercial permits | $176/sq ft | $119 to $228/sq ft |
| Loudoun County, VA (Tenant fit-up) | 22 commercial permits | $414/sq ft | $121 to $495/sq ft |
| San Antonio / Bexar County, TX (Building permits) | 17 building permits | $405/sq ft | $95 to $852/sq ft |
| Irving, TX (DFW major data center builds) | 5 building permits | $721/sq ft | $492 to $1,048/sq ft |
| Fort Worth / Tarrant County, TX (Building permits) | 13 building permits | $956/sq ft | $597 to $1,252/sq ft |
| Texas TDLR statewide (New construction, 2025) | 24 state registrations | $764/sq ft | $602 to $1,529/sq ft |
| Texas TDLR statewide (New construction, 2026) | 34 state registrations | $1,015/sq ft | $644 to $2,976/sq ft |
Source: Colocation Scout public permit records (checked November 23, 2026), deduplicated by permit or TABS ID and filtered to filings at least 20,000 sq ft and $5M. Fort Worth excludes two 2026 ACS permits whose database square-footage field logged 29,427 sq ft against a 283,274 GSF narrative. Across all 61 Texas TDLR new-construction filings with both area and cost (2024 to 2026), the median is $960/sq ft (IQR $615 to $2,377/sq ft). San Jose permits (6 filings, median $790/sq ft) are omitted from the main table because the city allocates full project valuation onto 20% foundation permits.
How long data center permits actually take (applied to issued)
Time-to-power is the main reason enterprise buyers choose colocation over building. Before construction even starts, municipal building departments review structural, electrical, fire, and mechanical plans. We audited 898 issued data center permits filed from 2022 through November 2026 across jurisdictions that publish both a verified application date and a distinct permit issuance date.
| Jurisdiction and permit tier (2022 to 2026) | Verified permits | Median review | Middle half (IQR) and notes |
|---|---|---|---|
| Loudoun County, VA (New construction) | 51 issued | 168 days ~5.5 months | 115 to 230 days ($10M+ subset: 166 days, n=40). Excludes parallel zoning permits. |
| Prince William County, VA (Building permits) | 11 issued | 168 days ~5.5 months | 149 to 211 days across EnerGov permits (AWS, Digital Realty, CloudHQ, Corscale). |
| San Antonio / Bexar County, TX ($10M+ permits) | 21 issued | 156 days ~5.1 months | 125 to 339 days (all 36 new-build permits: 132 days; all 76 issued: 93 days). |
| Irving, TX ($10M+ data center builds) | 3 issued | 140 days ~4.6 months | Range 135 to 165 days ($350M EdgeCore took 165d; $152M QTS took 135d). |
| Mesa, AZ (New data center builds) | 11 issued | 97 days ~3.2 months | 89 to 155 days (all 61 issued Mesa data center permits: 109 days, IQR 81 to 160d). |
| Loudoun County, VA (Tenant fit-up) | 205 issued | 92 days ~3.0 months | 50 to 185 days ($10M+ fit-ups jump to 149 days, n=16; $10M+ alterations: 303d). |
| Aurora, CO ($10M+ data center permits) | 9 issued | 78 days ~2.6 months | 39 to 198 days (core-and-shell and major fit-outs ran 158 to 476d; all 39 permits: 29d). |
| Chicago, IL ($10M+ data center permits) | 10 issued | 78 days ~2.6 months | 54 to 126 days ($151.1M office-to-DC conversion took 91d; all 54 permits: 45d). |
| Douglas County, CO (All issued permits) | 19 issued | 69 days ~2.3 months | 10 to 106 days ($10M+ commercial finish-outs: 97 days median, n=3). |
| New York City DOB (Carrier hotel interiors) | 262 issued | 26 days interior work | 8 to 138 days for cage/MEP alterations in existing carrier hotels (26 standalone DC permits: 90d). |
Source: verified application-to-issuance date pairs in Colocation Scout's permit database (2022 to November 2026). Portals that publish only one date, or overwrite issuance dates with later status/finaled dates (such as Fort Worth and Denver's legacy feed), are deliberately excluded from this table so durations are never inflated.
Before a developer can even file for a building permit, land without by-right zoning has to clear rezoning and site-plan review. In Fairfax County, Virginia (2022 to 2026), approved data center rezonings took 467 to 528 days (15 to 17 months), and site plans took 244+ days. On October 29, 2026, San Antonio's City Council voted 9-2 to require a council-approved Specific Use Authorization for every new data center. After permit issuance, physical construction adds another 18 to 21 months: two finaled Irving, Texas builds ($180M data center and $152M QTS building) ran 22.2 months and 25.1 months from permit application to finaled occupancy, not counting land acquisition or multi-year utility interconnects.
Texas statewide declared construction pipeline (through Nov 17, 2026)
Texas is the only major state where virtually every commercial data center project registers an estimated construction cost before starting work. Tracking TDLR new-construction filings quarter by quarter shows the surge in declared capital since mid-2025, driven heavily by rural West Texas AI campuses.
| Quarter registered | New-construction filings | Declared construction cost | Largest filings in quarter |
|---|---|---|---|
| Q3 2025 | 8 | $3.0B | GN DC1 LLC ($500M x 2) |
| Q4 2025 | 18 | $16.6B | Abilene DC9 & DC10 ($6.3B each) |
| Q1 2026 | 15 | $6.4B | Galaxy Helios II ($1.3B x 2) |
| Q2 2026 | 32 | $20.2B | Capital Land ($2.8B); Vantage ($1.3B) |
| Q3 2026 | 37 | $20.8B | Childress DC1 & DC2 ($2.4B each) |
| Q4 2026 (to Nov 17) | 11 | $14.5B | Clocktower Quanah ($8.0B); Spur Hyper ($2.4B x 2) |
Source: Texas Department of Licensing and Regulation (TDLR) TABS new-construction registrations deduplicated by TABS ID, checked November 23, 2026. A registration is filed before construction begins; it is not an approved building permit, a construction start, or space available to lease. Through November 17, Q4 2026 includes November filings from Amazon in Pecos County and Nexus Data Centers in Hubbard ($400M x 2). See our construction pipeline hub for metro-level context.
Need capacity faster than a 24-month build cycle?
Tell us your target market, kW load, rack density and go-live date. We compare verified colocation space ready today against what a private build or delayed pipeline project actually costs and delivers.
Methodology and data boundaries
All permit counts, declared valuations, square-footage ratios, and approval durations on this page come from Colocation Scout's public-records permit database (checked November 23, 2026). Every municipal collector was audited at the source-field level before inclusion:
- Only true application-to-issuance pairs enter the timeline table. Loudoun County figures include only commercial building permits (excluding parallel zoning permits so projects are not double-counted). San Antonio excludes unissued application-submitted rows. Portals whose public feeds overwrite issuance dates with later status or completion dates (including Fort Worth and Denver's legacy feed) or publish only one date (air permits) are excluded from approval medians.
- Deduplication and outlier hygiene. Records are deduplicated by permit ID or TABS registration number. Two Fort Worth permits with a clear square-footage typo (29,427 sq ft logged against a 283,274 GSF narrative) are excluded from the per-square-foot median.
- Permits are not availability. A permit, state registration, or SEC construction disclosure proves capital and regulatory activity, never open capacity you can lease. For current verified colocation space, see available data center capacity.