Resources / Permit & SEC Cost Study

Data center construction cost and permit timelines: what public filings show.

Industry guides quote $11M to $20M+ per megawatt to build a data center. County building permits often declare $1M to $6M. Using 898 issued building permits from 2022 to 2026, Texas state project registrations, and Q3/Q4 2026 SEC filings, this study shows what each stage actually declares and how long municipal permit approval takes before a shovel hits dirt. Every figure links to its primary public record and is not available capacity.

Public building permits, Texas TDLR, and SEC filings checked November 23, 2026

What the public filing record shows

Most construction cost articles repeat one global average per megawatt without showing how much belongs to the shell, how much belongs to electrical and cooling fit-out, or how many months are lost inside municipal plan review before construction starts.

  • Three cost layers explain the wide spread per MW. Bare county shell permits declare $0.6M to $2.9M per MW, combined state construction registrations declare $3.8M to $7.6M per MW (higher on small 3 to 5 MW builds), and SEC-filed turnkey completions and acquisitions reach $7.7M to $14.4M+ per MW.
  • Interior fit-out and liquid cooling drive most of the bill. Vantage's 96 MW San Antonio build split 38% shell ($2.88M/MW) and 62% tenant fit-up ($4.67M/MW), while an August 2026 Aurora, Colorado permit declared $27.2M ($9.07M/MW) just to convert 3 MW inside an existing hall to liquid cooling.
  • Permit approval adds 3 to 6+ months before construction begins. Across 898 issued data center permits filed from 2022 through 2026, median review ran 168 days for ground-up builds in Loudoun County and Prince William County, 156 days for $10M+ permits in San Antonio, 140 days for $10M+ builds in Irving, and 97 days for new builds in Mesa.

Declared construction cost per megawatt in public permits

Where a municipal permit or Texas accessibility registration states both an estimated construction cost and critical IT megawatts, the gap across build scopes becomes clear. Treat every declared permit number as a construction floor, not a full project budget: filings typically omit land, design fees, utility upgrades, and owner-supplied generators, UPS, or switchgear.

Filing and marketScopeDeclared cost per MWStated capacity and total
CloudHQ 2-story build, Ashburn VABare county shell$0.58M/MW
$54/sq ft
96 MW, $55.7M, 1,030,408 sq ft (BLDC-2025-029746, issued Oct 2025)
Vantage TX12 shell, San Antonio TXCore and shell$2.88M/MW
38% of total
96 MW, $276.9M, 432,800 gross sq ft (TABS2026001234)
Vantage TX12 fit-up, San Antonio TXTenant fit-out$4.67M/MW
$7.55M combined
96 MW, $448.0M fit-out; $724.9M with shell (62% fit-out)
Digital Realty Garland, DFW TXNew construction$3.75M/MW
$446/sq ft
80 MW across ten 8 MW suites, $300.0M, 672,000 sq ft
Soluna Project Kati II, Willacy Co. TXAI campus build$4.21M/MW
$1,000/sq ft
112 MW critical IT load, $471.8M, 471,884 sq ft
Stream DFWC1, Wilmer TXNew build + sub.$6.25M/MW
$832/sq ft
48 MW, $300.0M, 360,750 sq ft, includes substation
Oppidan El Paso & Temple, TXSmall ground-up$5.43M to $6.20M
per MW (5 MW each)
$27.2M in El Paso (61,554 sq ft); $31.0M in Temple
Prime DC 3 MW buildout, Dallas TXSmall buildout + gen.$15.83M/MW
$1,379/sq ft
3 MW, $47.5M, 34,438 sq ft, includes 4 generators and switchgear
Data hall fit-out, Ashburn VAInterior fit-out$1.86M/MW
$619/sq ft
14 MW across 2 floors, $26.0M, 42,000 sq ft (BLDC-2026-038611)
QTS DEN1 DC2 fit-out, Aurora COHot-aisle fit-out$4.19M/MW
60 MW TI
60 MW tenant improvement inside shell, $251.6M (26-2614863-000-00)
QTS SAT2 DC1 fit-out, San Antonio TXInterior fit-out$4.44M/MW
$852/sq ft
9 MW fit-out, $40.0M, 46,975 sq ft (issued Nov 2023)
QTS DEN1 DC1 6 MW TI, Aurora COInterior fit-out$6.84M/MW
6 MW TI
6 MW data hall interior remodel, $41.1M (issued Jul 2026)
DEN1 DC1 liquid cooling, Aurora COLC conversion TI$9.07M/MW
3 MW retrofit
3 MW liquid-cooling conversion inside existing hall, $27.2M ($15.8M materials)

Sources: each row links directly to its municipal permit record or Texas Department of Licensing and Regulation (TDLR) registration, checked November 23, 2026. Per-MW figures are our division of declared valuation by stated megawatts. Small builds (3 to 5 MW) and liquid-cooling retrofits carry steep fixed-equipment overhead per MW compared with 48 to 112 MW hyperscale halls.

How permit floors compare with SEC turnkey build costs and overruns

Public SEC filings bridge the gap between municipal permit floors and full turnkey delivery cost. Recent Q3 and Q4 2026 disclosures show both what completed megawatts trade for and how fast real construction budgets can move mid-build.

SEC filing (Q3/Q4 2026)BasisDisclosed cost or valuePer MW and context
Fermi 45-deal capex ladder (Nov 12, 2026 8-K)Industry capex benchmark$3.9M to $15.0M
per gross MW
Powered Land+ $3.9M to $5.1M; Powered Shell $5.1M to $6.6M; Turnkey $12.1M to $15.0M per gross MW.
Blackstone Trust / Amazon (Nov 16, 2026 8-K)13 newly built sites (IN, MS)$5.0B gross
$7.7M/MW
647 MW IT load valued at 7.0% initial cap rate across 9 Indiana and 4 Mississippi buildings.
Blue Owl Gainesville, VA (Nov 10, 2026 8-K)Completed leased building$779.5M
$14.4M/MW
54 MW hyperscaler building in Prince William County bought with a $512.6M loan.
Cipher Barber Lake, TX (Oct 13, 2026 8-K)All-in estimate at completion$2.94B to $2.97B
+36% to +38%
Up from $2.157B original budget ($359M change orders + $375M to $400M extra completion cost); two halls slipped one quarter.

Sources: SEC Form 8-K filings linked above. Industry averages from JLL's 2026 Global Data Center Market Outlook sit at $11.3M/MW for a standard build and $15M to $20M+/MW for AI liquid-cooled builds before land; see our colocation vs. private build model and Q3 2026 SEC lease rate study.

Why permit values understate real budgets by 40% to 75%

First, counties like Loudoun value the structural shell separately from electrical, mechanical, and tenant fit-up permits. Second, owner-furnished equipment (generators, chillers, medium-voltage switchgear, UPS modules) frequently sits outside the general contractor's building permit valuation. Third, land and utility substation deposits are never inside a building permit: Northern Virginia industrial parcels have traded at $3.5M to $4.0M per acre, and Cipher's Barber Lake filing shows real-world change orders can add more than a third after groundbreaking.

Declared cost per square foot: why Loudoun reads $176 while Texas reads $960

Filtering 2022 to 2026 filings to substantial projects (at least 20,000 square feet and $5 million declared) shows how dramatically valuation reporting differs across jurisdictions. Comparing raw county totals across markets without separating shell permits from combined registrations produces misleading rankings.

Jurisdiction and permit scopeSample (2022 to 2026)Median per sq ftMiddle half (IQR)
Loudoun County, VA (New construction shell)40 commercial permits$176/sq ft$119 to $228/sq ft
Loudoun County, VA (Tenant fit-up)22 commercial permits$414/sq ft$121 to $495/sq ft
San Antonio / Bexar County, TX (Building permits)17 building permits$405/sq ft$95 to $852/sq ft
Irving, TX (DFW major data center builds)5 building permits$721/sq ft$492 to $1,048/sq ft
Fort Worth / Tarrant County, TX (Building permits)13 building permits$956/sq ft$597 to $1,252/sq ft
Texas TDLR statewide (New construction, 2025)24 state registrations$764/sq ft$602 to $1,529/sq ft
Texas TDLR statewide (New construction, 2026)34 state registrations$1,015/sq ft$644 to $2,976/sq ft

Source: Colocation Scout public permit records (checked November 23, 2026), deduplicated by permit or TABS ID and filtered to filings at least 20,000 sq ft and $5M. Fort Worth excludes two 2026 ACS permits whose database square-footage field logged 29,427 sq ft against a 283,274 GSF narrative. Across all 61 Texas TDLR new-construction filings with both area and cost (2024 to 2026), the median is $960/sq ft (IQR $615 to $2,377/sq ft). San Jose permits (6 filings, median $790/sq ft) are omitted from the main table because the city allocates full project valuation onto 20% foundation permits.

How long data center permits actually take (applied to issued)

Time-to-power is the main reason enterprise buyers choose colocation over building. Before construction even starts, municipal building departments review structural, electrical, fire, and mechanical plans. We audited 898 issued data center permits filed from 2022 through November 2026 across jurisdictions that publish both a verified application date and a distinct permit issuance date.

Jurisdiction and permit tier (2022 to 2026)Verified permitsMedian reviewMiddle half (IQR) and notes
Loudoun County, VA (New construction)51 issued168 days
~5.5 months
115 to 230 days ($10M+ subset: 166 days, n=40). Excludes parallel zoning permits.
Prince William County, VA (Building permits)11 issued168 days
~5.5 months
149 to 211 days across EnerGov permits (AWS, Digital Realty, CloudHQ, Corscale).
San Antonio / Bexar County, TX ($10M+ permits)21 issued156 days
~5.1 months
125 to 339 days (all 36 new-build permits: 132 days; all 76 issued: 93 days).
Irving, TX ($10M+ data center builds)3 issued140 days
~4.6 months
Range 135 to 165 days ($350M EdgeCore took 165d; $152M QTS took 135d).
Mesa, AZ (New data center builds)11 issued97 days
~3.2 months
89 to 155 days (all 61 issued Mesa data center permits: 109 days, IQR 81 to 160d).
Loudoun County, VA (Tenant fit-up)205 issued92 days
~3.0 months
50 to 185 days ($10M+ fit-ups jump to 149 days, n=16; $10M+ alterations: 303d).
Aurora, CO ($10M+ data center permits)9 issued78 days
~2.6 months
39 to 198 days (core-and-shell and major fit-outs ran 158 to 476d; all 39 permits: 29d).
Chicago, IL ($10M+ data center permits)10 issued78 days
~2.6 months
54 to 126 days ($151.1M office-to-DC conversion took 91d; all 54 permits: 45d).
Douglas County, CO (All issued permits)19 issued69 days
~2.3 months
10 to 106 days ($10M+ commercial finish-outs: 97 days median, n=3).
New York City DOB (Carrier hotel interiors)262 issued26 days
interior work
8 to 138 days for cage/MEP alterations in existing carrier hotels (26 standalone DC permits: 90d).

Source: verified application-to-issuance date pairs in Colocation Scout's permit database (2022 to November 2026). Portals that publish only one date, or overwrite issuance dates with later status/finaled dates (such as Fort Worth and Denver's legacy feed), are deliberately excluded from this table so durations are never inflated.

Building permits are only step two of the clock

Before a developer can even file for a building permit, land without by-right zoning has to clear rezoning and site-plan review. In Fairfax County, Virginia (2022 to 2026), approved data center rezonings took 467 to 528 days (15 to 17 months), and site plans took 244+ days. On October 29, 2026, San Antonio's City Council voted 9-2 to require a council-approved Specific Use Authorization for every new data center. After permit issuance, physical construction adds another 18 to 21 months: two finaled Irving, Texas builds ($180M data center and $152M QTS building) ran 22.2 months and 25.1 months from permit application to finaled occupancy, not counting land acquisition or multi-year utility interconnects.

Texas statewide declared construction pipeline (through Nov 17, 2026)

Texas is the only major state where virtually every commercial data center project registers an estimated construction cost before starting work. Tracking TDLR new-construction filings quarter by quarter shows the surge in declared capital since mid-2025, driven heavily by rural West Texas AI campuses.

Quarter registeredNew-construction filingsDeclared construction costLargest filings in quarter
Q3 20258$3.0BGN DC1 LLC ($500M x 2)
Q4 202518$16.6BAbilene DC9 & DC10 ($6.3B each)
Q1 202615$6.4BGalaxy Helios II ($1.3B x 2)
Q2 202632$20.2BCapital Land ($2.8B); Vantage ($1.3B)
Q3 202637$20.8BChildress DC1 & DC2 ($2.4B each)
Q4 2026 (to Nov 17)11$14.5BClocktower Quanah ($8.0B); Spur Hyper ($2.4B x 2)

Source: Texas Department of Licensing and Regulation (TDLR) TABS new-construction registrations deduplicated by TABS ID, checked November 23, 2026. A registration is filed before construction begins; it is not an approved building permit, a construction start, or space available to lease. Through November 17, Q4 2026 includes November filings from Amazon in Pecos County and Nexus Data Centers in Hubbard ($400M x 2). See our construction pipeline hub for metro-level context.

Need capacity faster than a 24-month build cycle?

Tell us your target market, kW load, rack density and go-live date. We compare verified colocation space ready today against what a private build or delayed pipeline project actually costs and delivers.

Add your name or company Optional

Free to you. Powered by Bridgepointe Technologies, trusted by NVIDIA, Microsoft, Charles Schwab and 75+ Fortune 500 companies. A scout replies within one business day.

Methodology and data boundaries

All permit counts, declared valuations, square-footage ratios, and approval durations on this page come from Colocation Scout's public-records permit database (checked November 23, 2026). Every municipal collector was audited at the source-field level before inclusion:

  • Only true application-to-issuance pairs enter the timeline table. Loudoun County figures include only commercial building permits (excluding parallel zoning permits so projects are not double-counted). San Antonio excludes unissued application-submitted rows. Portals whose public feeds overwrite issuance dates with later status or completion dates (including Fort Worth and Denver's legacy feed) or publish only one date (air permits) are excluded from approval medians.
  • Deduplication and outlier hygiene. Records are deduplicated by permit ID or TABS registration number. Two Fort Worth permits with a clear square-footage typo (29,427 sq ft logged against a 283,274 GSF narrative) are excluded from the per-square-foot median.
  • Permits are not availability. A permit, state registration, or SEC construction disclosure proves capital and regulatory activity, never open capacity you can lease. For current verified colocation space, see available data center capacity.

Related guides: colocation vs. building your own data center, 2026 colocation pricing benchmarks, Q3 2026 signed SEC lease rates, U.S. data center construction pipeline, data center shell LLCs and project codenames, and the utility power pipeline tracker.

Weighing a private build against colocation?

Share your power target, density and timeline. We verify live operator capacity and put lease options side by side against real build timelines.