Entergy Arkansas plans a second phase of service for Google's West Memphis data center campus, with about $600 million of grid work and a 440 MW solar contract paid for by Google

Entergy Arkansas announced on October 19, 2026 a second phase of electric service for Google's data center campus in West Memphis, Arkansas. The utility says the phase needs about $600 million of planned investment plus a power purchase agreement, all covered by Google: two battery systems, a 440 MW (ac) solar contract, an expanded Galet substation and two new 230 kV lines to serve the expanded campus. The expansion still has to be submitted to the Arkansas Public Service Commission; Entergy targets service in 2028 if it is approved. Entergy listed the expanded Google agreement among its third quarter highlights on November 2. [Source 1] [Source 2]

Entergy Arkansas plans a second phase of service for Google's West Memphis data center campus, with about $600 million of grid work and a 440 MW solar contract paid for by Google
All news & analysisDevelopment & PowerWest Memphis, Crittenden County, ArkansasAnnounced October 19, 2026; to be submitted to the Arkansas Public Service Commission for approval. Pending approval, Entergy expects service in 2028. Not approved as of November 2, 2026.

Disclosed terms

Planned investment
About $600 million plus a power purchase agreement, covered by Google [1]
Solar contract
440 MW (ac) power purchase agreement, Big Island solar facility [1]
Battery storage
1,000 MWh at Driver Solar near Osceola, online 2028 expected [1]
Campus delivery
Galet substation expansion and two new 230 kV lines [1]
Regulatory status
To be submitted to the Arkansas Public Service Commission [1]
Earnings mention
Listed as a Q3 2026 business highlight on November 2 [2]

The disclosure and our analysis

Evidence dates

Evidence: Entergy Arkansas news release, October 19, 2026; Entergy third quarter 2026 earnings release, Form 8-K Exhibit 99.1, November 2, 2026. Both read November 3, 2026. Status is as of November 2, 2026.

What Entergy disclosed

Entergy Arkansas describes the announcement as a second phase of its service to support Google's presence in West Memphis. It says the project will fulfill Google's plan for data center buildings on the site and accelerate the ramp-up of the original announced project. [Source 1]

Entergy lists these system resources, which it says require approximately $600 million in planned investment and a power purchase agreement, both covered by Google: [Source 1]

1. **Driver battery:** a 1,000 megawatt-hour battery energy storage system at Driver Solar near Osceola, expected online in 2028.

2. **Jones Mill battery:** a 400 megawatt-hour battery energy storage system near Hot Springs, expected online in 2028.

3. **Big Island solar contract:** a 440 megawatt (ac) solar power purchase agreement from the Big Island solar facility being built in Mississippi County. Entergy says this was added based on Arkansas Public Service Commission guidance from the initial filing of the resource.

4. **Delivery to the campus:** expansion of the Galet substation near West Memphis and two new 230 kV transmission lines to serve the expanded data center campus.

Entergy says Google is paying for the project under a new contract and that the new resources will not be charged through the Generating Arkansas Jobs Act Rider. [Source 1]

What the megawatt figures mean

The 440 MW is the AC rating of a solar supply contract. The 1,000 and 400 megawatt-hour figures are battery energy storage, not power. None of them is the data center's load, critical IT capacity or contracted demand. Entergy also says these resources, combined with the Arkansas Cypress Solar and Battery facility under construction in Jefferson County, will add over 1,000 megawatts of solar and 2,800 megawatt-hours of battery storage to its system. That combined figure is system supply, not campus capacity. [Source 1]

Economics, as Entergy describes them

Entergy says the second phase will bring at least $500 million in new customer savings starting in 2028 and extending over 20 years, on top of $1.6 billion identified for the first phase, and that the combined agreement is expected to return more than $2.1 billion to its 738,000 customers. These are the utility's projections. The reviewed sources do not show a Commission finding on them. [Source 1]

Status

On our status vocabulary, as of November 2, 2026: the second phase is Announced, and Proposed for regulatory review. Entergy says the expansion will be submitted to the Arkansas Public Service Commission for approval and that, pending approval, it expects service in 2028. The reviewed sources do not give a docket number or filing date. Nothing in them establishes construction, energization or capacity Available to other buyers on the campus. The campus is Google's own facility, not colocation inventory. [Source 1] [Source 2]

Buyer analysis

This is our analysis. The second phase signals that Google expects more load at West Memphis, sooner, than its original plan. Entergy does not give the new load in megawatts, so the size of the step up is not known from these sources.

For colocation buyers in the Memphis region, two points matter. First, new transmission and substation work for one large campus can take years and regulatory approval, and Entergy's own target here is 2028. Providers promising large new blocks nearby should be able to show where their power comes from and when. Second, the structure, where the hyperscaler funds the grid upgrades and supply under a separate contract, is becoming the norm for large loads. Smaller buyers should ask providers whether similar cost commitments sit behind their utility service, because those costs can show up in pricing and contract terms.

What remains unknown

The reviewed sources do not give the data center's load in MW for either phase, its critical IT capacity, the number of buildings, the term or price of the new contract, the regulatory docket or filing date, or the construction schedule for the substation and lines. They do not say how the 440 MW solar contract relates to Entergy's earlier filing for the same resource beyond Entergy's statement about Commission guidance. We did not review any Commission filing for this phase.

Sources

  1. Entergy Arkansas, news release · Published 2026-10-19
  2. Entergy Corporation, third quarter 2026 earnings release, Form 8-K Exhibit 99.1 · Published 2026-11-02

Explore the market

Related reporting

Development & Power

San Antonio now requires a City Council vote on every new data center after a 9-2 code change

San Antonio City Council voted 9-2 on October 29, 2026 to pass data center regulations proposed by District 6 Councilmember Ric Galvan. The approach requires a Specific Use Authorization, a zoning approval voted on by council, for each new data center, rather than allowing data centers by right where they meet set standards. The mayor said the change ensures council can review each data center application. The final signed ordinance was not posted in the sources we reviewed. [Source 1] [Source 2] [Source 4]

San Antonio, Bexar County, Texas (city limits) · Approved: City Council passed the data center code change 9-2 on October 29, 2026. Final signed ordinance not reviewed.
Read the analysis
Development & Power

California ISO's board approves a large load interconnection proposal with a flexible interim service, due at FERC by November 16

The California ISO Board of Governors approved a proposal on October 28, 2026 setting new procedures for connecting large loads such as data centers to its grid. A key element is a flexible interim load interconnection that would let large loads connect to the transmission system with enforceable flexibility until network upgrades are complete. The ISO says it will file the proposal with the Federal Energy Regulatory Commission by a November 16 deadline, in response to FERC's June 2026 show cause order on large loads. The rules are not in effect until FERC acts. [Source 1] [Source 2]

California ISO grid; no specific project site · Approved by the California ISO Board of Governors on October 28, 2026 for filing at FERC by November 16, 2026. Not yet accepted by FERC; no effective date in reviewed sources.
Read the analysis
Development & Power

Michigan's attorney general asks regulators to rehear their approval of DTE's 20-year contracts for Google's Van Buren Township data center

Michigan Attorney General Dana Nessel filed a petition for rehearing on October 30, 2026 in Michigan Public Service Commission case U-22058, where the Commission on October 1 conditionally approved DTE Electric's special contracts to serve a planned Google data center in Van Buren Township that the petition describes as a 1 gigawatt facility. She asks the Commission to require annual reconciliation of costs and benefits, drop a cap on the customer's collateral and order more cost modeling that includes transmission costs, or else reject the contracts. The Commission's approval stands while the petition is pending. [Source 1] [Source 2]

Van Buren Township, Wayne County, Michigan · Approved: MPSC conditionally approved the DTE and Google special contracts on October 1, 2026. Petition for rehearing filed by the Michigan Attorney General on October 30, 2026; pending as of that date. Service expected to begin December 2027, per DTE.
Read the analysis