Michigan's attorney general asks regulators to rehear their approval of DTE's 20-year contracts for Google's Van Buren Township data center

Michigan Attorney General Dana Nessel filed a petition for rehearing on October 30, 2026 in Michigan Public Service Commission case U-22058, where the Commission on October 1 conditionally approved DTE Electric's special contracts to serve a planned Google data center in Van Buren Township that the petition describes as a 1 gigawatt facility. She asks the Commission to require annual reconciliation of costs and benefits, drop a cap on the customer's collateral and order more cost modeling that includes transmission costs, or else reject the contracts. The Commission's approval stands while the petition is pending. [Source 1] [Source 2]

Michigan's attorney general asks regulators to rehear their approval of DTE's 20-year contracts for Google's Van Buren Township data center
All news & analysisDevelopment & PowerVan Buren Township, Wayne County, MichiganApproved: MPSC conditionally approved the DTE and Google special contracts on October 1, 2026. Petition for rehearing filed by the Michigan Attorney General on October 30, 2026; pending as of that date. Service expected to begin December 2027, per DTE.

Disclosed terms

Petition filed
October 30, 2026, MPSC case U-22058 [2]
Facility size in petition
1 GW data center facility (power basis not stated) [2]
Net cost years quoted from order
2035 through 2038 [2]
Collateral
Asks the Commission to reject a collateral cap [2]
Fallback request
Reject the contracts if her recommendations are not adopted [2]

The disclosure and our analysis

Evidence dates

Evidence: Attorney General petition for rehearing in MPSC case U-22058, dated October 30, 2026; Attorney General news release, October 30, 2026; MPSC news release on the approval, October 1, 2026. Read November 2, 2026. Status is as of October 30, 2026.

What the petition asks for

The petition challenges the Commission's October 1, 2026 order, which it says conditionally approved DTE's special contracts for electric service to a 1 gigawatt data center facility to be built in Van Buren Township and operated by Google. The petition does not say whether the 1 GW is peak demand, contract demand or IT load. [Source 2]

The Attorney General's requests on rehearing, as listed in the petition: [Source 2]

1. **More cost modeling:** order further record evaluation of cost and benefit questions, with DTE required to model the transmission cost categories she says were omitted, and hold the data center customer responsible through the contracts' affordability backstop for any added costs found.

2. **No contract-long aggregation:** reject DTE's standard of weighing costs and benefits over the full contract term, and reject the use of avoided costs realized in assessing the affordability backstop.

3. **Annual reconciliation:** adopt regulatory liability accounting with an annual reconciliation.

4. **Transmission cost tracking:** direct DTE, at a minimum, to work with ITC to capture and report project level transmission costs tied to the data center.

5. **DTE as backstop:** order that DTE's backstop cover all incremental costs of serving the Google data center.

6. **No collateral cap:** reject the cap on the customer's collateral requirement.

If the Commission does not adopt these recommendations, the petition says it should reject the special contracts outright. [Source 2]

The 2035 to 2038 point

The petition quotes the Commission's order as stating that there appears to be agreement that the four years of 2035 through 2038 will produce annual net costs to other customers, due to the need to build a proxy generation resource. The order, as quoted, found that the aggregate impact over the contract term is the key consideration rather than an annual net benefit test. The Attorney General argues that this standard accepts years in which other customers subsidize the data center. That is her characterization. DTE contends the contracts will produce a $1.7 billion benefit to other customers over the 20-year term, as described by the Commission in October. [Source 1] [Source 2] [Source 3]

What was approved on October 1

As described by the Commission, the approved supply agreement has a 20-year term, a minimum bill of 80% of contracted demand, an early termination payment of at least 15 years of minimum monthly charges, and credit and collateral requirements. A separate agreement has Google pay for up to 1,600 MW of renewable generation and 480 MW of battery storage that DTE will own. DTE expects service to begin in December 2027 and reach maximum load by December 2028. Our earlier article covers those terms. [Source 3] [Source 4]

Status

On our status vocabulary, as of October 30, 2026: the DTE and Google special contracts are Approved by the MPSC, with conditions, under its October 1 order. The rehearing petition is pending. The reviewed sources do not give a date for a Commission decision on it. Nothing in them establishes construction, energization or capacity Available to other buyers.

Buyer analysis

This is our analysis. The petition does not change the contract terms today, but it puts the shape of Michigan's large load deals back in front of the Commission. If annual reconciliation or uncapped collateral were adopted, the cost of a hyperscale contract in DTE territory would rise for the customer, and future large loads should expect the same asks.

For colocation buyers in the Detroit region, the practical effect is indirect. Providers that need new DTE service at scale may face longer terms, higher collateral and more cost tracking, and some of that can flow into wholesale and retail colocation pricing. Ask providers whether their own utility agreements carry minimum bills, collateral or reconciliation terms, and when their service dates fall relative to the 2027 to 2028 Google ramp.

What remains unknown

The reviewed sources do not give a deadline or expected date for the Commission's decision on rehearing, the contracted load in MW under the approved contracts, the dollar amount of the collateral or of the collateral cap, the size of the 2035 to 2038 net costs, or the amount of the transmission costs the Attorney General says were omitted. The petition's 1 GW figure has no stated power basis. We did not review the Commission's full October 1 order beyond the passages the petition quotes, or any response from DTE or Google.

Sources

  1. Michigan Department of Attorney General, news release · Published 2026-10-30
  2. Michigan Attorney General, petition for rehearing, MPSC case U-22058 · Published 2026-10-30
  3. Michigan Public Service Commission, news release (case U-22058) · Published 2026-10-01
  4. Colocation Scout, MPSC approval of DTE and Google contracts · Published 2026-10-03

Explore the market

Related reporting

Development & Power

California ISO's board approves a large load interconnection proposal with a flexible interim service, due at FERC by November 16

The California ISO Board of Governors approved a proposal on October 28, 2026 setting new procedures for connecting large loads such as data centers to its grid. A key element is a flexible interim load interconnection that would let large loads connect to the transmission system with enforceable flexibility until network upgrades are complete. The ISO says it will file the proposal with the Federal Energy Regulatory Commission by a November 16 deadline, in response to FERC's June 2026 show cause order on large loads. The rules are not in effect until FERC acts. [Source 1] [Source 2]

California ISO grid; no specific project site · Approved by the California ISO Board of Governors on October 28, 2026 for filing at FERC by November 16, 2026. Not yet accepted by FERC; no effective date in reviewed sources.
Read the analysis
Development & Power

Alliant Energy reports 3.4 GW of contracted data center demand in Iowa and Wisconsin and a proposed 15 year large load tariff

Alliant Energy said on October 29, 2026 that its Iowa and Wisconsin utilities, Interstate Power and Light (IPL) and Wisconsin Power and Light (WPL), have 3.4 gigawatts of contracted demand from data centers, and it raised its 2027 to 2030 capital expenditure forecast by 19% to $15.9 billion. Its quarterly report, filed October 30, 2026, adds that WPL has asked Wisconsin regulators to approve a large load tariff requiring a 15 year initial service term for customers of 100 MW or more, and that IPL filed in October 2026 for Iowa approval of an individual customer rate for another data center. The 3.4 GW is contracted demand, not critical IT load. [Source 1] [Source 2]

Interstate Power and Light (Iowa) and Wisconsin Power and Light (Wisconsin) service territories; specific sites not disclosed · Contracted demand of 3.4 GW (utility contracted demand, not IT load) as of October 29, 2026. WPL individual customer rate Approved by the PSCW in June 2026 with conditions; WPL large load tariff (15 year term, 100 MW threshold) Proposed September 2026, decision expected first half of 2027; IPL individual customer rate Proposed October 2026, decision expected first quarter of 2027.
Read the analysis
Development & Power

A data center building near Quanah, Texas is registered with state regulators at a listed $8 billion

A Texas Department of Licensing and Regulation (TDLR) filing created October 27, 2026 registers Clocktower NWB 05, a single story data center building with an office component of 288,355 square feet at 4628 Four Corners Road, Quanah, in Hardeman County. The owner is listed as 19000-200 Holdings, LLC of Dallas. The registration lists an estimated cost of $8,000,000,000 and construction from November 1, 2026 to December 31, 2028. No tenant is assigned. [Source 1]

4628 Four Corners Road, Quanah, Hardeman County, Texas · Proposed (TDLR accessibility registration created October 27, 2026; listed construction November 1, 2026 to December 31, 2028). Not a building permit. No tenant assigned. No megawatt figure disclosed.