California ISO's board approves a large load interconnection proposal with a flexible interim service, due at FERC by November 16

The California ISO Board of Governors approved a proposal on October 28, 2026 setting new procedures for connecting large loads such as data centers to its grid. A key element is a flexible interim load interconnection that would let large loads connect to the transmission system with enforceable flexibility until network upgrades are complete. The ISO says it will file the proposal with the Federal Energy Regulatory Commission by a November 16 deadline, in response to FERC's June 2026 show cause order on large loads. The rules are not in effect until FERC acts. [Source 1] [Source 2]

California ISO's board approves a large load interconnection proposal with a flexible interim service, due at FERC by November 16
All news & analysisDevelopment & PowerCalifornia ISO grid; no specific project siteApproved by the California ISO Board of Governors on October 28, 2026 for filing at FERC by November 16, 2026. Not yet accepted by FERC; no effective date in reviewed sources.

Disclosed terms

Board approval
October 28, 2026; FERC filing due November 16 [1]
Flexible interim service
Connect before network upgrades finish, with enforceable flexibility [1]
Study review
New monthly window for large load transmission upgrades [1]
Remote disconnect
Protocols to remotely disconnect large loads for reliability [1]
FERC order
Order instituting proceeding issued June 18, 2026 [2]

The disclosure and our analysis

Evidence dates

Evidence: California ISO news release, October 28, 2026; California ISO stakeholder presentation with the compliance schedule, October 19, 2026. Read November 2, 2026. Status is as of October 28, 2026.

What the board approved

According to the ISO, the board approved a proposal responding to FERC's June show cause order, which directed the California ISO and five other grid operators and their transmission owners to show they have rules for connecting large loads quickly without compromising reliability or shifting costs to other customers. The order instituting the proceeding was issued June 18, 2026. [Source 1] [Source 2]

The ISO describes these elements: [Source 1]

1. **Flexible interim load interconnection:** large loads could interconnect to the transmission system with enforceable flexibility, determined by grid conditions and constraints, until the associated network upgrades are complete.

2. **Faster study review:** a new monthly window for the ISO to review transmission additions or upgrades tied to large loads that fall outside the usual planning cycle, to fit FERC's 60 to 90 day requirement for transmission owners' load interconnection studies.

3. **Cost shifting:** a framework to prevent cost shifting to other customers. The release does not describe its terms.

4. **Co-located load and generation:** parallel information and application requirements for co-located arrangements, so the ISO has full visibility.

5. **Future policy work:** consideration of studying generation for loads located at separate but nearby sites.

The ISO also proposes technical requirements: hourly forecasts, telemetry and other operational data; communication protocols so the ISO and the transmission owner can remotely disconnect large loads when necessary to maintain reliability; and maintained communication channels with transmission customers serving large loads. The ISO says it will keep working with NERC on reliability standards for computational loads. [Source 1]

Timeline

The ISO's compliance schedule lists the October 28 board consideration and Section 205 tariff filings from the ISO and its participating transmission owners on November 16, 2026. FERC will then decide whether the proposal satisfies its show cause order. [Source 1] [Source 2]

Status

On our status vocabulary, as of October 28, 2026: the proposal is Approved by the California ISO Board of Governors for filing at FERC. It is not yet filed or accepted by FERC, and the reviewed sources give no effective date. The release does not give a megawatt threshold for what counts as a large load.

Buyer analysis

This is our analysis. The flexible interim service is the part that matters most for timing. If FERC accepts it, a California data center could take transmission service before its network upgrades are finished, but on terms that let the grid limit its load. Capacity delivered that way is not the same as firm power, and buyers should ask providers whether a site's early service is interim and flexible, and when firm service is expected.

The remote disconnect and hourly forecast requirements also flow down to tenants. Operators connecting under these rules will need curtailment plans and backup arrangements. Tenants in Silicon Valley, Los Angeles and other California markets should ask how a provider would handle a grid directed reduction, and whether their contract covers it.

What remains unknown

The reviewed sources do not give the megawatt threshold that defines a large load, the terms of the cost shifting framework, how much flexibility the interim service would require or for how long, or an effective date. They do not name any data center project that would use the interim service. We did not review the final tariff language the board approved, which the ISO plans to file at FERC.

Sources

  1. California ISO, news release · Published 2026-10-28
  2. California ISO, Large Loads draft tariff language stakeholder presentation · Published 2026-10-19
  3. California ISO, Large loads stakeholder initiative page · Published 2026-11-02

Related reporting

Development & Power

Michigan's attorney general asks regulators to rehear their approval of DTE's 20-year contracts for Google's Van Buren Township data center

Michigan Attorney General Dana Nessel filed a petition for rehearing on October 30, 2026 in Michigan Public Service Commission case U-22058, where the Commission on October 1 conditionally approved DTE Electric's special contracts to serve a planned Google data center in Van Buren Township that the petition describes as a 1 gigawatt facility. She asks the Commission to require annual reconciliation of costs and benefits, drop a cap on the customer's collateral and order more cost modeling that includes transmission costs, or else reject the contracts. The Commission's approval stands while the petition is pending. [Source 1] [Source 2]

Van Buren Township, Wayne County, Michigan · Approved: MPSC conditionally approved the DTE and Google special contracts on October 1, 2026. Petition for rehearing filed by the Michigan Attorney General on October 30, 2026; pending as of that date. Service expected to begin December 2027, per DTE.
Read the analysis
Development & Power

Alliant Energy reports 3.4 GW of contracted data center demand in Iowa and Wisconsin and a proposed 15 year large load tariff

Alliant Energy said on October 29, 2026 that its Iowa and Wisconsin utilities, Interstate Power and Light (IPL) and Wisconsin Power and Light (WPL), have 3.4 gigawatts of contracted demand from data centers, and it raised its 2027 to 2030 capital expenditure forecast by 19% to $15.9 billion. Its quarterly report, filed October 30, 2026, adds that WPL has asked Wisconsin regulators to approve a large load tariff requiring a 15 year initial service term for customers of 100 MW or more, and that IPL filed in October 2026 for Iowa approval of an individual customer rate for another data center. The 3.4 GW is contracted demand, not critical IT load. [Source 1] [Source 2]

Interstate Power and Light (Iowa) and Wisconsin Power and Light (Wisconsin) service territories; specific sites not disclosed · Contracted demand of 3.4 GW (utility contracted demand, not IT load) as of October 29, 2026. WPL individual customer rate Approved by the PSCW in June 2026 with conditions; WPL large load tariff (15 year term, 100 MW threshold) Proposed September 2026, decision expected first half of 2027; IPL individual customer rate Proposed October 2026, decision expected first quarter of 2027.
Read the analysis
Development & Power

A data center building near Quanah, Texas is registered with state regulators at a listed $8 billion

A Texas Department of Licensing and Regulation (TDLR) filing created October 27, 2026 registers Clocktower NWB 05, a single story data center building with an office component of 288,355 square feet at 4628 Four Corners Road, Quanah, in Hardeman County. The owner is listed as 19000-200 Holdings, LLC of Dallas. The registration lists an estimated cost of $8,000,000,000 and construction from November 1, 2026 to December 31, 2028. No tenant is assigned. [Source 1]

4628 Four Corners Road, Quanah, Hardeman County, Texas · Proposed (TDLR accessibility registration created October 27, 2026; listed construction November 1, 2026 to December 31, 2028). Not a building permit. No tenant assigned. No megawatt figure disclosed.
Read the analysis