Alliant Energy reports 3.4 GW of contracted data center demand in Iowa and Wisconsin and a proposed 15 year large load tariff

Alliant Energy said on October 29, 2026 that its Iowa and Wisconsin utilities, Interstate Power and Light (IPL) and Wisconsin Power and Light (WPL), have 3.4 gigawatts of contracted demand from data centers, and it raised its 2027 to 2030 capital expenditure forecast by 19% to $15.9 billion. Its quarterly report, filed October 30, 2026, adds that WPL has asked Wisconsin regulators to approve a large load tariff requiring a 15 year initial service term for customers of 100 MW or more, and that IPL filed in October 2026 for Iowa approval of an individual customer rate for another data center. The 3.4 GW is contracted demand, not critical IT load. [Source 1] [Source 2]

Alliant Energy reports 3.4 GW of contracted data center demand in Iowa and Wisconsin and a proposed 15 year large load tariff
All news & analysisDevelopment & PowerInterstate Power and Light (Iowa) and Wisconsin Power and Light (Wisconsin) service territories; specific sites not disclosedContracted demand of 3.4 GW (utility contracted demand, not IT load) as of October 29, 2026. WPL individual customer rate Approved by the PSCW in June 2026 with conditions; WPL large load tariff (15 year term, 100 MW threshold) Proposed September 2026, decision expected first half of 2027; IPL individual customer rate Proposed October 2026, decision expected first quarter of 2027.

Disclosed terms

Contracted data center demand
3.4 GW across IPL and WPL (contracted demand, not IT load) [1]
Capital plan
$15.9 billion for 2027 through 2030, up 19% [1]
Iowa agreement
About 370 MW of contracted peak demand, signed April 2026 [2]
Proposed Wisconsin tariff
15 year initial term for customers of 100 MW or more; filed September 2026 [2]
Transmission guarantees
About $199 million (IPL) and $125 million (WPL) as of September 30, 2026 [2]
Pending Iowa rate
IPL individual customer rate filed October 2026; decision expected Q1 2027 [2]

The disclosure and our analysis

Evidence dates

Evidence: Alliant Energy press release dated October 29, 2026, furnished with a Form 8-K; Alliant Energy Form 10-Q for the quarter ended September 30, 2026, filed October 30, 2026. Read November 1, 2026. Figures are as of the filing dates unless noted.

What Alliant disclosed

1. **Contracted demand:** IPL and WPL have 3.4 gigawatts of contracted demand from data centers, according to the release. Alliant expects peak demand to rise about 60% by 2031. [Source 1]

2. **Capital plan:** Alliant raised its four year capital expenditure forecast for 2027 through 2030 by 19% to $15.9 billion, which it ties to the energy resources needed to serve the expected load. [Source 1]

3. **A 370 MW agreement in Iowa:** In April 2026, IPL entered into an electric service agreement with a customer that expects to build a data center in IPL's territory, with contracted peak demand of about 370 MW. Alliant says the timing and amount of load increases depend on interconnections and actual customer demand, and that agreements are not expected to produce immediate load. [Source 2]

4. **Rate approvals:** In June 2026, the Public Service Commission of Wisconsin (PSCW) approved an individual customer rate for a customer constructing a data center in WPL's territory, subject to conditions. In October 2026, IPL asked the Iowa Utilities Commission to approve an individual customer rate for a data center expected to be built in its territory, with a decision expected in the first quarter of 2027. [Source 2]

5. **Proposed Wisconsin large load tariff:** As a condition of its June approval, the PSCW directed WPL to file a large load tariff for customers with demand of 100 MW or more. WPL filed it in September 2026. As proposed, it would require a 15 year initial service term, minimum demand commitments, termination charges, customer reimbursement obligations and credit support. A PSCW decision is expected in the first half of 2027. [Source 2]

6. **Transmission guarantees:** IPL and WPL have agreed to reimburse their transmission providers if data center related transmission projects are terminated before they are placed in service. As of September 30, 2026, those guarantees were about $199 million for IPL and $125 million for WPL. [Source 2]

How to read the gigawatts

The 3.4 GW is a utility's contracted demand figure. It is not critical IT load, and it is not capacity that is energized or available. The 370 MW Iowa agreement is contracted peak demand under one electric service agreement. The reviewed filings do not break the 3.4 GW down by customer, site or year, and do not say how much is already being served.

Status

On our status vocabulary, as of October 30, 2026: one WPL individual customer rate is Approved by the PSCW, with conditions, for a data center the filing says is under construction. The IPL individual customer rate and the WPL large load tariff are Proposed and pending. The reviewed filings do not name any customer, and nothing in them establishes capacity Available to new tenants.

Buyer analysis

This is our analysis, not Alliant's. For anyone siting large load in Wisconsin, the proposed tariff is the term sheet to plan around: a 15 year initial commitment, minimum demand, termination charges and credit support at 100 MW and above. Those terms would sit alongside the rent in any colocation or build to suit deal, and a tenant should expect a provider to pass them through.

The transmission guarantees show who carries the risk today. The utilities have guaranteed about $324 million combined (our arithmetic) to their transmission providers if data center projects stop before the lines are in service. That is the kind of exposure large load tariffs are designed to move onto customers.

For buyers, the practical questions are which of the contracted sites a provider is tied to, what service dates those agreements carry, and whether a new requirement would fall under the Wisconsin tariff or a negotiated Iowa individual customer rate.

What remains unknown

The reviewed filings do not name the data center customers or their sites, break the 3.4 GW down by customer, location or in-service year, or say how much of it is energized today. They do not disclose rates or other terms of the approved or pending individual customer rates, the service dates under the 370 MW agreement, or how much of the $15.9 billion capital plan is for generation, transmission or distribution serving data centers.

Sources

  1. Alliant Energy Corporation, third quarter 2026 earnings release (Form 8-K Exhibit 99.1) · Published 2026-10-29
  2. Alliant Energy Corporation, Form 10-Q for the quarter ended September 30, 2026 · Published 2026-10-30

Explore the market

Related reporting

Development & Power

A data center building near Quanah, Texas is registered with state regulators at a listed $8 billion

A Texas Department of Licensing and Regulation (TDLR) filing created October 27, 2026 registers Clocktower NWB 05, a single story data center building with an office component of 288,355 square feet at 4628 Four Corners Road, Quanah, in Hardeman County. The owner is listed as 19000-200 Holdings, LLC of Dallas. The registration lists an estimated cost of $8,000,000,000 and construction from November 1, 2026 to December 31, 2028. No tenant is assigned. [Source 1]

4628 Four Corners Road, Quanah, Hardeman County, Texas · Proposed (TDLR accessibility registration created October 27, 2026; listed construction November 1, 2026 to December 31, 2028). Not a building permit. No tenant assigned. No megawatt figure disclosed.
Read the analysis
Development & Power

TerraVolt takes options on 1,077 acres in Cassia County, Idaho for a planned behind the meter data center campus

TerraVolt Holdings said in a Form 8-K filed October 30, 2026 that on October 26, 2026 it entered two option agreements, dated October 23, 2026, to buy about 1,077 acres in Cassia County, Idaho, outside the town of Declo, at $30,000 per acre. TerraVolt says it intends to develop the site as a master-planned, behind the meter digital infrastructure campus designed to support an initial 240 MW of dedicated on-site power generation. That figure is generation capacity, not critical IT load. The options expire October 23, 2027, with a paid six month extension available. [Source 1] [Source 2]

Cassia County, Idaho, outside Declo, near State Highway 81 and Interstate 84 · Announced campus plan with land under option, as of October 30, 2026. Options on about 1,077 acres at $30,000 per acre expire October 23, 2027 (extendable six months). Initial 240 MW of planned on-site generation (generation capacity, not IT load). Permitting and design still to come.
Read the analysis
Development & Power

Oklahoma City rezones two Frisco Road parcels for a data center campus, with a potable water cap and power contract conditions

The Oklahoma City Council on October 27, 2026 adopted ordinances rezoning two parcels near I-40 and Frisco Road, about 110 acres at 3025 North Frisco Road (PUD-2105) and about 184 acres at 13921 NW 23rd Street (PUD-2124), to planned unit developments that permit data centers. Each ordinance passed 6 to 3 and was adopted without the emergency clause. The master design statements, prepared for developer BLE Landholdings, LLC, cap combined potable water use at 75,000 gallons per day for each site unless the Director of Utilities approves more, and require an Oklahoma Corporation Commission approved electric service instrument with at least a 10 year initial term before any certificate of occupancy. [Source 1] [Source 2] [Source 3]

I-40 and Frisco Road, west Oklahoma City (Canadian County), Oklahoma · Approved: rezoning of two parcels (about 110 and 184 acres) to data center PUDs by the Oklahoma City Council, October 27, 2026, subject to the technical evaluation as amended. Community benefits agreement required before building permits; Oklahoma Corporation Commission approved electric service of at least 10 years required before occupancy.
Read the analysis