Oklahoma City rezones two Frisco Road parcels for a data center campus, with a potable water cap and power contract conditions

The Oklahoma City Council on October 27, 2026 adopted ordinances rezoning two parcels near I-40 and Frisco Road, about 110 acres at 3025 North Frisco Road (PUD-2105) and about 184 acres at 13921 NW 23rd Street (PUD-2124), to planned unit developments that permit data centers. Each ordinance passed 6 to 3 and was adopted without the emergency clause. The master design statements, prepared for developer BLE Landholdings, LLC, cap combined potable water use at 75,000 gallons per day for each site unless the Director of Utilities approves more, and require an Oklahoma Corporation Commission approved electric service instrument with at least a 10 year initial term before any certificate of occupancy. [Source 1] [Source 2] [Source 3]

Oklahoma City rezones two Frisco Road parcels for a data center campus, with a potable water cap and power contract conditions
All news & analysisDevelopment & PowerI-40 and Frisco Road, west Oklahoma City (Canadian County), OklahomaApproved: rezoning of two parcels (about 110 and 184 acres) to data center PUDs by the Oklahoma City Council, October 27, 2026, subject to the technical evaluation as amended. Community benefits agreement required before building permits; Oklahoma Corporation Commission approved electric service of at least 10 years required before occupancy.

Disclosed terms

Council action
Ordinances 28,171 (PUD-2105) and 28,172 (PUD-2124) adopted without emergency, each 6 to 3, October 27, 2026 [1]
Sites
About 110 acres at 3025 North Frisco Road; about 184 acres at 13921 NW 23rd Street [2]
Potable water cap
75,000 gallons per day combined per site unless the Director of Utilities approves more [2]
Power contract
OCC approved electric service instrument with at least a 10 year initial term before occupancy [2]
Noise
55 dBA at the property perimeter [2]
Community benefits
Executed agreement with the end user or operator before a building permit [2]

The disclosure and our analysis

Evidence dates

Evidence: City of Oklahoma City Council Journal of Proceedings for October 27, 2026; amended master design statements for PUD-2105 and PUD-2124 dated August 25, 2026 and stamped for the October 27, 2026 meeting; Planning Commission minutes for January 15, 2026. Read October 31, 2026.

What the council did

1. **Votes:** The council approved amendments to each master design statement 8 to 1, then adopted the rezoning ordinances without emergency, Ordinance 28,171 (PUD-2105) and Ordinance 28,172 (PUD-2124), each 6 to 3. Both were approved subject to the Summary of Technical Evaluation as amended. The journal notes for each that an easement was requested but not received. [Source 1]

2. **History:** The Planning Commission recommended approval of PUD-2105 on January 15, 2026, and the journal records Planning Commission recommendations of approval for both items. The council had deferred the items repeatedly between March 10 and September 29, 2026. [Source 1] [Source 4]

3. **Use:** The PUDs change the base zoning from AA Agricultural and PUD-1637 to permit data center development, defined to include computer systems, cooling, power systems, electrical substations, battery energy storage and backup generation. [Source 2]

Conditions in the design statements

1. **Water:** No private groundwater wells. Combined potable water use for domestic, irrigation, fire protection and limited cooling may not exceed 75,000 gallons per day unless the Director of Utilities approves more in writing. Evaporative cooling is allowed only with treated wastewater from the city's water utility; closed-loop and liquid to chip cooling are allowed. [Source 2] [Source 3]

2. **Power and occupancy:** Before any certificate of occupancy for each building or phase, the applicant must show a final, executed electric service instrument approved by the Oklahoma Corporation Commission, with terms that do not shift incremental project costs to other Oklahoma City customers and an initial term of at least 10 years. On-site generation is limited to solar and what the design statement expressly permits. [Source 2]

3. **Noise:** Sound may not exceed 55 dBA at the property perimeter or 65 dBC from the development, with a separate rule where ambient sound is already at or above 65 dBC. Generator testing is limited to 10 a.m. to 4 p.m. on weekdays except in emergencies. [Source 2]

4. **Community benefits agreement:** Before a building permit, a legally binding community benefits agreement must be executed by the city, the applicant and the project's end user or operator, covering fiscal, infrastructure, natural resource, neighborhood and workforce topics. [Source 2]

5. **Other:** Maximum building height of 80 feet, 150 foot setbacks on the east, west and south boundaries of the Frisco Road parcel, a decommissioning plan before occupancy, and city sales tax and franchise fee obligations on energy purchases unless otherwise agreed. [Source 2]

Status

On our status vocabulary, as of October 27, 2026: Approved, for rezoning of both parcels to data center PUDs, subject to the technical evaluation as amended. Building permits still require an executed community benefits agreement, and occupancy requires an approved electric service contract. The reviewed documents do not establish construction, energization or capacity Available to tenants.

Buyer analysis

This is our analysis, not the city's. The design statements give no megawatt figure and no building count, so the approval says nothing yet about how much IT load could arrive or when. What it does show is the template Oklahoma City is using: a hard potable water cap, treated wastewater for evaporative cooling, a long term utility contract before occupancy, and an end user signature on a benefits agreement before permits.

That last condition matters for buyers. It means the operator or end user has to be identified, and has to sign, before a building permit is issued. Anyone evaluating capacity here should ask who that party is, what electric service terms are in negotiation with the utility, and which cooling design fits within the water rules.

What remains unknown

The reviewed documents do not give planned megawatts on any power basis, building count or square footage, an end user or tenant, an electric service agreement or its status at the Oklahoma Corporation Commission, a construction schedule, or the contents of the community benefits agreement. The council journal does not state the ordinances' effective date. The documents name the developer as BLE Landholdings, LLC; they do not describe its ownership.

Sources

  1. City of Oklahoma City, City Council Journal of Proceedings, October 27, 2026 · Published 2026-10-27
  2. City of Oklahoma City, PUD-2105 amended master design statement (I-40 and Frisco Rd.) · Published 2026-10-27
  3. City of Oklahoma City, PUD-2124 amended master design statement (NW 23rd St. and Frisco Rd.) · Published 2026-10-27
  4. City of Oklahoma City, Planning Commission minutes, PUD-2105 · Published 2026-01-15

Explore the market

Related reporting

Development & Power

TerraVolt takes options on 1,077 acres in Cassia County, Idaho for a planned behind the meter data center campus

TerraVolt Holdings said in a Form 8-K filed October 30, 2026 that on October 26, 2026 it entered two option agreements, dated October 23, 2026, to buy about 1,077 acres in Cassia County, Idaho, outside the town of Declo, at $30,000 per acre. TerraVolt says it intends to develop the site as a master-planned, behind the meter digital infrastructure campus designed to support an initial 240 MW of dedicated on-site power generation. That figure is generation capacity, not critical IT load. The options expire October 23, 2027, with a paid six month extension available. [Source 1] [Source 2]

Cassia County, Idaho, outside Declo, near State Highway 81 and Interstate 84 · Announced campus plan with land under option, as of October 30, 2026. Options on about 1,077 acres at $30,000 per acre expire October 23, 2027 (extendable six months). Initial 240 MW of planned on-site generation (generation capacity, not IT load). Permitting and design still to come.
Read the analysis
Development & Power

Exelon counts about 11 GW of high probability data center load, 9 GW of it at ComEd, with 23 GW more in cluster studies

Exelon said in its third quarter 2026 earnings slides, filed October 30, 2026, that it counts about 11 GW of high probability data center load: about 9 GW at ComEd and about 2 GW in its MidAtlantic utilities. It defines that tier as load in advanced phases of design or backed by FERC approved transmission security agreements, and says about 45% has those agreements, backed by about $1.2 billion in collateral. A further future pipeline of about 23 GW, 14 GW at ComEd and 9 GW MidAtlantic, sits within current or future cluster studies due to conclude in 2026 and 2027. [Source 1]

ComEd service area, northern Illinois; Exelon MidAtlantic utilities · Utility forecast. About 11 GW high probability data center load (ComEd about 9 GW, MidAtlantic about 2 GW), in advanced design or backed by FERC approved TSAs; about 45% with TSAs and about $1.2 billion collateral. Future pipeline about 23 GW in cluster studies concluding 2026 and 2027. As of October 30, 2026.
Read the analysis
Development & Power

Portland General lists 473 MW of executed data center contracts under construction, plus a separate contract for up to 420 MW

Portland General Electric said in its third quarter 2026 earnings slides, filed October 29, 2026, that 473 MW of executed 2025 and 2026 contracts with five data center customers are under construction. A further 2026 executed contract of up to 420 MW is not under construction and is expected to energize in 2028, ramping to full capacity in 2033. PGE also lists a pipeline of 1.3 GW of incremental large load requests to be energized in 2028 and beyond. PGE says the values represent customer capacity as of October 29, 2026. [Source 1]

Portland General Electric service area, Oregon · Utility contracts. 473 MW of executed 2025 and 2026 contracts with five data center customers under construction (PGE's words). Up to 420 MW 2026 executed contract not under construction, expected energization 2028, full capacity 2033. 1.3 GW of incremental large load requests for 2028 and beyond. Customer capacity as of October 29, 2026.