TerraVolt takes options on 1,077 acres in Cassia County, Idaho for a planned behind the meter data center campus

TerraVolt Holdings said in a Form 8-K filed October 30, 2026 that on October 26, 2026 it entered two option agreements, dated October 23, 2026, to buy about 1,077 acres in Cassia County, Idaho, outside the town of Declo, at $30,000 per acre. TerraVolt says it intends to develop the site as a master-planned, behind the meter digital infrastructure campus designed to support an initial 240 MW of dedicated on-site power generation. That figure is generation capacity, not critical IT load. The options expire October 23, 2027, with a paid six month extension available. [Source 1] [Source 2]

TerraVolt takes options on 1,077 acres in Cassia County, Idaho for a planned behind the meter data center campus
All news & analysisDevelopment & PowerCassia County, Idaho, outside Declo, near State Highway 81 and Interstate 84Announced campus plan with land under option, as of October 30, 2026. Options on about 1,077 acres at $30,000 per acre expire October 23, 2027 (extendable six months). Initial 240 MW of planned on-site generation (generation capacity, not IT load). Permitting and design still to come.

Disclosed terms

Land under option
About 1,077 acres in Cassia County, Idaho, outside Declo [1]
Price
$30,000 per acre; about 903.3 acres in cash, about 174.1 acres by convertible note [1]
Option fee
$150,000 in escrow, half nonrefundable [1]
Option term
Expires October 23, 2027; six month extension for $75,000 [1]
Planned generation
Initial 240 MW of dedicated on-site power generation (generation capacity, not IT load) [1]
Gas supply
Previously announced firm supply agreement of 55,000 MMBtu per day [1]

The disclosure and our analysis

Evidence dates

Evidence: TerraVolt Holdings, Inc. Form 8-K (Item 1.01) and its Exhibit 99.1 press release, both filed October 30, 2026. Read October 31, 2026. The option agreements are dated October 23, 2026 and were entered into on October 26, 2026.

What TerraVolt disclosed

1. **Site control by option:** Two option agreements with Wickel Land Company LLP cover about 1,077 acres in Cassia County, Idaho, outside Declo. Final acreage will be set by an ALTA/NSPS land title survey. [Source 1]

2. **Price:** About 903.3 acres at $30,000 per acre in cash, and about 174.1 acres at $30,000 per acre paid with a two year convertible secured promissory note. The note converts into TerraVolt common stock at $5.00 per share, automatically after 60 consecutive trading days at or above $5.00, or at the holder's election on the business day before maturity. If not converted it is repaid in cash, secured by a mortgage on those 174.1 acres. [Source 1]

3. **Option fee and term:** TerraVolt deposited $150,000 in option fees in escrow. Half is nonrefundable and released to the seller. The options expire October 23, 2027, and TerraVolt may extend them six months for a $75,000 payment. Both options must be exercised together. Half of the fees come back if TerraVolt terminates over a verified environmental, zoning, water rights, utility, access, title or permitting issue. [Source 1]

4. **Power plan:** TerraVolt says the campus is designed to support an initial 240 MW of dedicated on-site power generation, supported by its previously announced firm natural gas supply agreement of 55,000 MMBtu per day. The company describes the site as near State Highway 81, Interstate 84, long-haul fiber routes and the Williams Northwest Pipeline, and says it is zoned Multiple-Use. [Source 1] [Source 2]

5. **Business model:** After entitlements and civil development, TerraVolt says it plans to sell shovel-ready building sites to data center operators and provide power, fiber, water, wastewater treatment and other site services under a long-term infrastructure services agreement. It says it intends to require low water use cooling, such as closed-loop cooling, as a condition of each site sale. [Source 2]

How to read the megawatts

The 240 MW is TerraVolt's stated initial on-site generation capacity. It is not critical IT load, and the filing does not say how much IT load the generation would support after redundancy, cooling and other site loads. It is a design target for a planned campus, not capacity that exists or is offered today.

Status

On our status vocabulary, as of October 30, 2026: the campus is Announced. TerraVolt holds options on the land, not title. The press release says the options let it advance land use plans, environmental due diligence, power plant and distribution design, and county and state permitting, so those steps are still ahead. Nothing in the reviewed filings establishes approvals, construction, energization or capacity Available to tenants.

Buyer analysis

This is our analysis, not TerraVolt's. The disclosed land price, $30,000 per acre, is a useful benchmark for powered land plays outside established markets. The structure is low cost to hold for now: $150,000 in option fees against a purchase price of roughly $32 million at the stated acreage (our arithmetic), and the options run a year with an extension.

For buyers and operators, the pitch is time to power through islanded gas generation rather than a utility queue. The questions to ask are the ones the filing leaves open: what IT load the generation supports, what redundancy the plant design carries, what the energy services agreement would charge, and how equipment lead times for turbines, engines, switchgear and transformers would set the first delivery date. TerraVolt itself lists financing, permitting, definitive offtake and equipment lead times among its risks.

We have not assigned this story to a Colocation Scout market page. Cassia County is in south central Idaho, outside the markets we currently track.

What remains unknown

The reviewed filings do not give a delivery date for the first building or power block; the critical IT load the 240 MW of generation would support; the generation technology mix or redundancy design; any named tenant, buyer or offtaker; pricing for the planned infrastructure and energy services agreements; the gas supplier or term of the 55,000 MMBtu per day agreement (described as previously announced); or how TerraVolt will finance the land purchase and plant. They do not say which county or state permits will be sought or when.

Sources

  1. TerraVolt Holdings, Inc., Form 8-K (Item 1.01, option agreements) · Published 2026-10-30
  2. TerraVolt Holdings, Inc., press release (Form 8-K Exhibit 99.1) · Published 2026-10-30

Related reporting

Development & Power

Oklahoma City rezones two Frisco Road parcels for a data center campus, with a potable water cap and power contract conditions

The Oklahoma City Council on October 27, 2026 adopted ordinances rezoning two parcels near I-40 and Frisco Road, about 110 acres at 3025 North Frisco Road (PUD-2105) and about 184 acres at 13921 NW 23rd Street (PUD-2124), to planned unit developments that permit data centers. Each ordinance passed 6 to 3 and was adopted without the emergency clause. The master design statements, prepared for developer BLE Landholdings, LLC, cap combined potable water use at 75,000 gallons per day for each site unless the Director of Utilities approves more, and require an Oklahoma Corporation Commission approved electric service instrument with at least a 10 year initial term before any certificate of occupancy. [Source 1] [Source 2] [Source 3]

I-40 and Frisco Road, west Oklahoma City (Canadian County), Oklahoma · Approved: rezoning of two parcels (about 110 and 184 acres) to data center PUDs by the Oklahoma City Council, October 27, 2026, subject to the technical evaluation as amended. Community benefits agreement required before building permits; Oklahoma Corporation Commission approved electric service of at least 10 years required before occupancy.
Read the analysis
Development & Power

Exelon counts about 11 GW of high probability data center load, 9 GW of it at ComEd, with 23 GW more in cluster studies

Exelon said in its third quarter 2026 earnings slides, filed October 30, 2026, that it counts about 11 GW of high probability data center load: about 9 GW at ComEd and about 2 GW in its MidAtlantic utilities. It defines that tier as load in advanced phases of design or backed by FERC approved transmission security agreements, and says about 45% has those agreements, backed by about $1.2 billion in collateral. A further future pipeline of about 23 GW, 14 GW at ComEd and 9 GW MidAtlantic, sits within current or future cluster studies due to conclude in 2026 and 2027. [Source 1]

ComEd service area, northern Illinois; Exelon MidAtlantic utilities · Utility forecast. About 11 GW high probability data center load (ComEd about 9 GW, MidAtlantic about 2 GW), in advanced design or backed by FERC approved TSAs; about 45% with TSAs and about $1.2 billion collateral. Future pipeline about 23 GW in cluster studies concluding 2026 and 2027. As of October 30, 2026.
Read the analysis
Development & Power

Portland General lists 473 MW of executed data center contracts under construction, plus a separate contract for up to 420 MW

Portland General Electric said in its third quarter 2026 earnings slides, filed October 29, 2026, that 473 MW of executed 2025 and 2026 contracts with five data center customers are under construction. A further 2026 executed contract of up to 420 MW is not under construction and is expected to energize in 2028, ramping to full capacity in 2033. PGE also lists a pipeline of 1.3 GW of incremental large load requests to be energized in 2028 and beyond. PGE says the values represent customer capacity as of October 29, 2026. [Source 1]

Portland General Electric service area, Oregon · Utility contracts. 473 MW of executed 2025 and 2026 contracts with five data center customers under construction (PGE's words). Up to 420 MW 2026 executed contract not under construction, expected energization 2028, full capacity 2033. 1.3 GW of incremental large load requests for 2028 and beyond. Customer capacity as of October 29, 2026.