Exelon counts about 11 GW of high probability data center load, 9 GW of it at ComEd, with 23 GW more in cluster studies

Exelon said in its third quarter 2026 earnings slides, filed October 30, 2026, that it counts about 11 GW of high probability data center load: about 9 GW at ComEd and about 2 GW in its MidAtlantic utilities. It defines that tier as load in advanced phases of design or backed by FERC approved transmission security agreements, and says about 45% has those agreements, backed by about $1.2 billion in collateral. A further future pipeline of about 23 GW, 14 GW at ComEd and 9 GW MidAtlantic, sits within current or future cluster studies due to conclude in 2026 and 2027. [Source 1]

Exelon counts about 11 GW of high probability data center load, 9 GW of it at ComEd, with 23 GW more in cluster studies
All news & analysisDevelopment & PowerComEd service area, northern Illinois; Exelon MidAtlantic utilitiesUtility forecast. About 11 GW high probability data center load (ComEd about 9 GW, MidAtlantic about 2 GW), in advanced design or backed by FERC approved TSAs; about 45% with TSAs and about $1.2 billion collateral. Future pipeline about 23 GW in cluster studies concluding 2026 and 2027. As of October 30, 2026.

Disclosed terms

High probability load
About 11 GW: ComEd about 9 GW, MidAtlantic about 2 GW [1]
TSA share
About 45% of the high probability tier, backed by about $1.2 billion of collateral [1]
Future pipeline
About 23 GW: ComEd about 14 GW, MidAtlantic about 9 GW, in cluster studies (2026 and 2027 conclusion) [1]
PJM submission
2027 Large Load Adjustment aligns with about 11 GW of high probability load [1]
Northern Illinois growth
About 28% CAGR in actual data center load, 2022 to 2026 YTD September [1]

The disclosure and our analysis

Evidence dates

Evidence: Exelon Corporation third quarter 2026 earnings conference call presentation, filed as Exhibit 99.2 to a Form 8-K on October 30, 2026 (slide 15). Read October 30, 2026. Figures are Exelon projections as of that date.

What Exelon disclosed

1. **High probability load:** under the heading Exelon's Projected Data Center Growth, the slide shows about 11 GW of high probability load: ComEd about 9 GW and MidAtlantic about 2 GW. [Source 1]

2. **Definition:** Exelon describes that tier as load in advanced phases of design or backed by FERC approved transmission security agreements (TSAs). A note on the tier says about 45% is with TSAs, backed by about $1.2 billion in collateral. On the slide, that note applies to the 11 GW tier as a whole; it does not split the TSA share between ComEd and MidAtlantic. [Source 1]

3. **Future pipeline:** the slide shows a future pipeline of about 23 GW: ComEd about 14 GW and MidAtlantic about 9 GW, described as within current or future cluster studies with 2026 and 2027 conclusions. [Source 1]

4. **PJM forecast:** Exelon says its Large Load Adjustments submitted to PJM in 2025 and 2026 were fully approved, and that its 2027 submission reflects enhanced commitment criteria and aligns with about 11 GW of high probability load. [Source 1]

5. **History:** a chart of actual data center load in northern Illinois shows growth at about 28% CAGR from 2022 to 2026, measured year to date through September, against about 9% before that. The chart does not print the megawatt values. [Source 1]

6. **Framework:** Exelon says FERC has endorsed its TSA framework as a model for protecting customers, improving queue certainty and enabling large load growth. [Source 1]

How to read the megawatts

These are Exelon projections of data center load on its utility systems. They are not critical IT capacity, and the slide does not say what share of the load is under construction, when it would energize, or which sites it covers. The 11 GW tier and the 23 GW pipeline are separate categories and should not be added together as a single forecast. ComEd serves northern Illinois, including the Chicago area. The slide does not say which states the 2 GW and 9 GW MidAtlantic figures fall in.

Status

On our status vocabulary, as of October 30, 2026: these are forecasts. About 45% of the high probability tier is backed by TSAs, which are interconnection security agreements, not leases or energization. The future pipeline is still in cluster studies. Nothing here establishes construction, energization or capacity Available to new customers.

Buyer analysis

This is our analysis, not Exelon's. The split between the two tiers is the useful part. Load backed by a TSA has collateral behind it; load in a cluster study does not yet have a confirmed path. For buyers evaluating new capacity in the Chicago market, a provider that can show a signed ComEd TSA, its collateral position and its study results is in a different place from one that is still waiting for a 2026 or 2027 cluster study to conclude.

Scale also matters. Even the high probability ComEd figure of about 9 GW is many times the northern Illinois data center load shown on Exelon's own historical chart. That gap implies years of transmission and generation work, and it is a reason to press providers for energization dates in writing rather than relying on a utility headline.

We have assigned this story to our Chicago market because ComEd's service area covers it. The slide does not name individual projects.

What remains unknown

The reviewed slides do not name customers or projects; give site locations or states for the MidAtlantic figures; split the TSA backed share between ComEd and MidAtlantic; give energization dates for the high probability load; say how much of it is under construction; or print the megawatt values behind the northern Illinois load chart.

Sources

  1. Exelon Corporation, Q3 2026 earnings conference call presentation (Form 8-K Exhibit 99.2) · Published 2026-10-30

Explore the market

Related reporting

Development & Power

Portland General lists 473 MW of executed data center contracts under construction, plus a separate contract for up to 420 MW

Portland General Electric said in its third quarter 2026 earnings slides, filed October 29, 2026, that 473 MW of executed 2025 and 2026 contracts with five data center customers are under construction. A further 2026 executed contract of up to 420 MW is not under construction and is expected to energize in 2028, ramping to full capacity in 2033. PGE also lists a pipeline of 1.3 GW of incremental large load requests to be energized in 2028 and beyond. PGE says the values represent customer capacity as of October 29, 2026. [Source 1]

Portland General Electric service area, Oregon · Utility contracts. 473 MW of executed 2025 and 2026 contracts with five data center customers under construction (PGE's words). Up to 420 MW 2026 executed contract not under construction, expected energization 2028, full capacity 2033. 1.3 GW of incremental large load requests for 2028 and beyond. Customer capacity as of October 29, 2026.
Read the analysis
Development & Power

AEP details transmission terms for a proposed 10.4 GW Piketon, Ohio data center campus and raises its contracted load forecast to 84 GW

American Electric Power said in its third quarter 10-Q, filed October 28, 2026, that its Ohio transmission subsidiary, Ohio Power and an unnamed customer executed definitive agreements in August 2026 for three 765 kV transmission lines to support a proposed 10.4 GW data center campus in Piketon, Ohio. The agreements set a project budget of about $5 billion, the lines target in-service dates at the end of 2028, 2029 and 2030, and the first 800 MW of load is expected to use existing transmission. The project still needs PJM, PUCO and FERC approvals. Separately, AEP said it signed 15 GW of new load commitments in the quarter and expects incremental contracted load to reach 84 GW by 2031. [Source 1] [Source 2]

Piketon, Ohio (campus); AEP service territory for the load figures · Piketon campus Proposed (AEP's word). Transmission agreements executed August 2026; PJM, PUCO and FERC approvals still required. First 800 MW expected to use existing transmission; three 765 kV lines targeted for end of 2028, 2029 and 2030. AEP contracted load forecast 84 GW by 2031 (ESAs or letters of agreement), alongside about 49 GW of AEP Texas letters of agreement tied in part to a paused ERCOT Batch Zero process. As of October 28, 2026.
Read the analysis
Development & Power

CenterPoint expects about 12 GW of ERCOT Batch Zero large load on its Houston system, pending ERCOT allocation decisions

CenterPoint Energy said in an October 27, 2026 investor update that it expects about 12 GW of new large load from ERCOT's Batch Zero process to be energized on its Houston Electric system by 2030, rising from about 3 GW in 2027. It compares that with a current system peak of 21 GW. CenterPoint says ERCOT is expected to decide how much counts as base load in December 2026 and how much is allocated as studied load in April 2027, and that actual demand may be lower. AEP's 10-Q, filed a day later, says ERCOT has paused Batch Zero classification and study work pending a state directed verification. [Source 1] [Source 2]

CenterPoint Houston Electric service territory, Greater Houston, Texas · Utility forecast. CenterPoint expects about 12 GW of Batch Zero large load energized on Houston Electric by 2030 (3 GW in 2027), against a 21 GW current peak. ERCOT base load determination expected December 2026 and studied load allocation April 2027, per CenterPoint. AEP's 10-Q says ERCOT has paused Batch Zero classification and study. No project level status established. As of October 27 and 28, 2026.
Read the analysis