AEP details transmission terms for a proposed 10.4 GW Piketon, Ohio data center campus and raises its contracted load forecast to 84 GW

American Electric Power said in its third quarter 10-Q, filed October 28, 2026, that its Ohio transmission subsidiary, Ohio Power and an unnamed customer executed definitive agreements in August 2026 for three 765 kV transmission lines to support a proposed 10.4 GW data center campus in Piketon, Ohio. The agreements set a project budget of about $5 billion, the lines target in-service dates at the end of 2028, 2029 and 2030, and the first 800 MW of load is expected to use existing transmission. The project still needs PJM, PUCO and FERC approvals. Separately, AEP said it signed 15 GW of new load commitments in the quarter and expects incremental contracted load to reach 84 GW by 2031. [Source 1] [Source 2]

AEP details transmission terms for a proposed 10.4 GW Piketon, Ohio data center campus and raises its contracted load forecast to 84 GW
All news & analysisDevelopment & PowerPiketon, Ohio (campus); AEP service territory for the load figuresPiketon campus Proposed (AEP's word). Transmission agreements executed August 2026; PJM, PUCO and FERC approvals still required. First 800 MW expected to use existing transmission; three 765 kV lines targeted for end of 2028, 2029 and 2030. AEP contracted load forecast 84 GW by 2031 (ESAs or letters of agreement), alongside about 49 GW of AEP Texas letters of agreement tied in part to a paused ERCOT Batch Zero process. As of October 28, 2026.

Disclosed terms

Proposed campus
10.4 GW data center campus in Piketon, Ohio (basis not stated) [1]
Transmission lines
Three 765 kV lines, about 3.2 GW of incremental transmission capacity each [1]
Target in-service dates
December 31, 2028, 2029 and 2030 (goals) [1]
Initial load
First 800 MW expected on existing transmission, no added approvals needed [1]
Project budget
About $5 billion [1]
Approvals required
PJM, PUCO and FERC [1]
New load commitments
15 GW signed in Q3 2026; contracted load expected to reach 84 GW by 2031 [2]
Texas letters of agreement
About 49 GW of incremental load by 2031, including Batch Zero prospective load [1]

The disclosure and our analysis

Evidence dates

Evidence: American Electric Power Company, Inc. Form 10-Q for the quarter ended September 30, 2026, filed October 28, 2026, and AEP's third quarter 2026 earnings release, filed as Exhibit 99.1 to a Form 8-K on October 28, 2026. Read October 29, 2026. Figures are as of those filings unless noted.

What AEP disclosed about Piketon

1. **Agreements:** AEP says that in August 2026, AEP Ohio Transmission Company (OHTCo), Ohio Power Company (OPCo) and an unaffiliated customer executed definitive agreements related to OHTCo building three 765 kV transmission lines to support the development of a proposed 10.4 GW data center campus in Piketon, Ohio. The filing does not name the customer. [Source 1]

2. **Lines and timing:** each line is expected to provide about 3.2 GW of incremental transmission capacity, with targeted in-service date goals of December 31, 2028, 2029 and 2030. [Source 1]

3. **First 800 MW:** AEP says the initial 800 MW of load is expected to be served using existing transmission capacity and does not require any additional regulatory approvals. [Source 1]

4. **Who pays:** for the balance of the roughly 10.4 GW, and subject to regulatory approvals, AEP says OHTCo expects to recover approved transmission costs through arrangements with OPCo, which would recover them from the customer under a retail service agreement designed so that none of the project's costs are allocated to other OPCo customers. [Source 1]

5. **Economics:** the agreements provide for a base return on equity of 11.35%, which can rise to 11.99% or fall to 10.71% depending on actual costs against budget and actual in-service dates against targets, with payment terms extending 20 years after each line's in-service date. They establish a project budget of about $5 billion. The equipment purchase agreement requires the customer to fully collateralize OHTCo equipment purchases before the required approvals are received. [Source 1]

6. **Approvals still needed:** AEP says the Piketon Transmission Project requires approvals from PJM, the Public Utilities Commission of Ohio and FERC, and that its scope, timing, cost recovery and economics remain subject to regulatory review. [Source 1]

What AEP disclosed about contracted load

AEP says it signed 15 GW of new load commitments during the third quarter and that its incremental contracted load is expected to grow to 84 GW by 2031. It says projects count as incremental contracted load only if backed by fully executed electric service agreements or letters of agreement. AEP also announced a $100 billion capital plan for 2027 through 2031, including about $37 billion for transmission and $36 billion for generation. [Source 2]

The 10-Q adds a Texas figure. AEP Texas has executed letters of agreement for about 49 GW of incremental load by 2031, including prospective load seeking consideration in ERCOT's Batch Zero process. AEP says ERCOT has paused Batch Zero classification and study activity and will not authorize large loads to energize until a state directed verification is complete, so the amount, timing and cost responsibility of those prospective interconnections remain subject to ERCOT and PUCT action. [Source 1]

How to read the megawatts

The 10.4 GW is AEP's description of the proposed campus. The filing does not say whether that figure is utility service capacity, peak demand or critical IT load, and it should not be read as IT capacity. The 3.2 GW per line is incremental transmission capacity. The 84 GW and 49 GW figures are utility load forecasts backed by service agreements or letters of agreement, not data center capacity, and AEP does not say how much of either is data center load. A letter of agreement is not the same commitment as a fully executed service agreement.

Status

On our status vocabulary, as of October 28, 2026: the Piketon campus is Proposed, in AEP's own word. The transmission project has executed agreements but is not Approved; it still needs PJM, PUCO and FERC approval. The filing establishes no construction, energization or capacity Available to new customers at the campus.

Buyer analysis

This is our analysis, not AEP's. The Piketon terms show the shape utilities now want for very large loads: the customer funds the dedicated transmission, collateralizes equipment before approvals, and pays over 20 years, with the utility's return tied to cost and schedule. Buyers negotiating with providers that are building in AEP territory should expect similar cost responsibility to be passed through in some form.

The schedule is the other signal. Only 800 MW can be served on existing transmission. The rest depends on three new lines whose targets run to the end of 2030, and on approvals not yet granted. A 10.4 GW headline therefore says little about near term capacity at the site.

On the contracted load total, the 49 GW of Texas letters of agreement is equal to more than half of the 84 GW, and AEP counts letters of agreement as contracted load. The reviewed filings do not say outright how much of the 49 GW is inside the 84 GW. Either way, Texas load tied to a Batch Zero process that, by AEP's account, is paused should be treated as less firm than load backed by executed service agreements.

We have not assigned this story to a tracked market. Piketon is in southern Ohio, outside the Columbus market we cover.

What remains unknown

The reviewed filings do not name the Piketon customer; say whether 10.4 GW is critical IT, utility service capacity or another basis; give a construction or energization date for the first 800 MW; say when AEP expects PJM, PUCO or FERC decisions; split the 84 GW of contracted load between data centers and other customers or between service agreements and letters of agreement; say how much of the 49 GW in Texas is Batch Zero load; or state how much of the 49 GW is counted within the 84 GW.

Sources

  1. American Electric Power Company, Inc., Form 10-Q for the quarter ended September 30, 2026 · Published 2026-10-28
  2. American Electric Power, third quarter 2026 earnings release (Form 8-K Exhibit 99.1) · Published 2026-10-28

Related reporting

Development & Power

CenterPoint expects about 12 GW of ERCOT Batch Zero large load on its Houston system, pending ERCOT allocation decisions

CenterPoint Energy said in an October 27, 2026 investor update that it expects about 12 GW of new large load from ERCOT's Batch Zero process to be energized on its Houston Electric system by 2030, rising from about 3 GW in 2027. It compares that with a current system peak of 21 GW. CenterPoint says ERCOT is expected to decide how much counts as base load in December 2026 and how much is allocated as studied load in April 2027, and that actual demand may be lower. AEP's 10-Q, filed a day later, says ERCOT has paused Batch Zero classification and study work pending a state directed verification. [Source 1] [Source 2]

CenterPoint Houston Electric service territory, Greater Houston, Texas · Utility forecast. CenterPoint expects about 12 GW of Batch Zero large load energized on Houston Electric by 2030 (3 GW in 2027), against a 21 GW current peak. ERCOT base load determination expected December 2026 and studied load allocation April 2027, per CenterPoint. AEP's 10-Q says ERCOT has paused Batch Zero classification and study. No project level status established. As of October 27 and 28, 2026.
Read the analysis
Development & Power

FirstEnergy says contracted data center demand on its system has nearly doubled to about 7.9 GW in its long range forecast, with another 19 GW in its pipeline

FirstEnergy said in an October 27, 2026 investor presentation that contracted data center demand across its five state footprint has nearly doubled since year end 2025, to about 7.9 GW of cumulative demand forecast for 2036. It counts another 19 GW of pipeline demand, says it is in active contract negotiations with about 4 GW, and lists 117 GW of large load studies outside its pipeline. Contracted means a contract to construct facilities and/or an electric service agreement. In West Virginia, it says it is negotiating with a data center customer to take the long-term output of a planned gas plant. [Source 1]

FirstEnergy service territory in Ohio, Pennsylvania, Maryland, West Virginia and New Jersey · Utility demand forecast. FirstEnergy reports about 7.9 GW of contracted cumulative data center demand forecast for 2036 (construction contracts and/or electric service agreements), 19 GW of pipeline demand and 117 GW of load studies outside the pipeline. West Virginia gas plant off-take with a data center customer under negotiation. No project level status established. As of October 27, 2026.
Read the analysis
Development & Power

A planned 11-building data center campus in Putnam County, Georgia lists about 520 MW of estimated peak connected load in its state review filing

Putnam County, Georgia filed a Development of Regional Impact review with the state on October 26, 2026 for Eatonton 379, a proposed data center development on about 543 acres with about 11 buildings totaling about 3.5 million square feet. The filing lists an estimated peak connected electrical load of about 520 MW, names Tri-County EMC or Georgia Power as the energy supplier, and gives an estimated value at build-out of about $3.5 billion with completion in 2031. The developer is seeking a rezoning and a conditional use. Putnam County has a moratorium on data center land development permits that it extended on October 21, 2026 to November 17, 2026. [Source 1] [Source 2] [Source 4]

Unincorporated Putnam County, Georgia, off Glenwood Spring Road (33.304423, -83.406540) · Proposed. Developer seeking a rezoning and a conditional use from Putnam County; Georgia DRI #4861 filed October 26, 2026 with estimated completion in 2031. Putnam County data center moratorium extended October 21, 2026 to November 17, 2026. No zoning approval, utility agreement, construction, energization or availability established. As of October 27, 2026.