CenterPoint expects about 12 GW of ERCOT Batch Zero large load on its Houston system, pending ERCOT allocation decisions

CenterPoint Energy said in an October 27, 2026 investor update that it expects about 12 GW of new large load from ERCOT's Batch Zero process to be energized on its Houston Electric system by 2030, rising from about 3 GW in 2027. It compares that with a current system peak of 21 GW. CenterPoint says ERCOT is expected to decide how much counts as base load in December 2026 and how much is allocated as studied load in April 2027, and that actual demand may be lower. AEP's 10-Q, filed a day later, says ERCOT has paused Batch Zero classification and study work pending a state directed verification. [Source 1] [Source 2]

CenterPoint expects about 12 GW of ERCOT Batch Zero large load on its Houston system, pending ERCOT allocation decisions
All news & analysisDevelopment & PowerCenterPoint Houston Electric service territory, Greater Houston, TexasUtility forecast. CenterPoint expects about 12 GW of Batch Zero large load energized on Houston Electric by 2030 (3 GW in 2027), against a 21 GW current peak. ERCOT base load determination expected December 2026 and studied load allocation April 2027, per CenterPoint. AEP's 10-Q says ERCOT has paused Batch Zero classification and study. No project level status established. As of October 27 and 28, 2026.

Disclosed terms

Expected energization
About 3 / 8 / 11 / 12 GW cumulative in 2027 / 2028 / 2029 / 2030 [1]
Current peak
Houston Electric system peak demand of 21 GW [1]
Peak increase
More than 55% if expected Batch Zero demand arrives [1]
Base load eligible
About 10 GW (55% of submissions) [1]
ERCOT base load decision
Expected December 2026 (per CenterPoint) [1]
Capital plan
About $70.7 billion for 2026 to 2035 [1]
ERCOT pause
Batch Zero classification and study paused pending verification (AEP account) [2]

The disclosure and our analysis

Evidence dates

Evidence: CenterPoint Energy, Inc. Third Quarter 2026 Investor Update, filed as Exhibit 99.2 to a Form 8-K on October 27, 2026, and American Electric Power Company, Inc. Form 10-Q filed October 28, 2026. Read October 29, 2026. Figures are forecasts as of those filings.

What CenterPoint disclosed

1. **Expected energization:** the investor update gives estimated cumulative energization of expected Batch Zero large load demand of about 3 GW in 2027, 8 GW in 2028, 11 GW in 2029 and 12 GW in 2030. [Source 1]

2. **Against today's peak:** CenterPoint says the 12 GW represents new large load requests eligible for base load or studied load, compared with Houston Electric's current system peak demand of 21 GW, and that it would mean more than a 55% increase in peak load demand. It adds that actual customer demand may vary and be less than the potential load interconnected. [Source 1]

3. **Category mix:** of its Batch Zero submissions, CenterPoint lists about 10 GW eligible as base load (55% of submissions), about 2 GW expected to be eligible as studied load (15%), and about 5 GW of incremental demand (30%) not expected to qualify for either but that could be considered in future batches. Base load eligibility, in its definition, means two or more studies completed before July 10 and a security deposit equal to the cost of interconnection. [Source 1]

4. **Total 2030 growth:** CenterPoint says 2030 load growth remains at 14 GW: the 12 GW of Batch Zero demand plus 2 GW of distribution level and lower voltage transmission growth under 75 MW. [Source 1]

5. **ERCOT decisions:** CenterPoint says the amount of load included as base load is expected to be determined by ERCOT in December 2026, that base load projects reclassified as studied load may face delayed energization, and that studied load allocations are expected in April 2027 and may be less than the amounts eligible. [Source 1]

6. **Capital plan:** the update shows a 10 year capital plan of about $70.7 billion for 2026 through 2035, up from $66.7 billion, and about $38.7 billion for 2026 through 2030. [Source 1]

The ERCOT pause

CenterPoint's slides do not describe a pause. AEP's 10-Q, filed October 28, says the Governor of Texas in August 2026 directed the PUCT and ERCOT to verify all Batch Zero loads and audit data center projects of 25 MW and above, that ERCOT missed an August 2026 Batch Zero study deadline and received a good cause exception from the PUCT, and that ERCOT has paused Batch Zero classification and study activity and will not authorize large loads to energize until verification is complete. That is AEP's account; we have not reviewed an ERCOT notice for this article. [Source 2]

How to read the megawatts

These are CenterPoint forecasts of large load demand on its transmission system, not data center capacity, critical IT load or available space. The investor update does not say how much of the Batch Zero load is data centers rather than industrial or other large customers, and it does not name customers or projects. The 21 GW figure is Houston Electric's current system peak demand.

Status

On our status vocabulary, as of October 27, 2026, these figures describe forecast utility demand. They establish no project approval, construction, energization or availability. ERCOT's base load and studied load determinations remain pending, and by AEP's October 28 account the Batch Zero process is paused.

Buyer analysis

This is our analysis, not CenterPoint's. The useful detail is the gap between eligibility and allocation. Only about 10 GW of CenterPoint's Batch Zero submissions meet its base load definition, and even that depends on an ERCOT determination now running behind schedule. For buyers looking at new large builds in the Houston area, a provider's Batch Zero category, its study history and its security deposit status are better signals of timing than a headline megawatt figure.

The scale also matters for anyone already in the market. A potential 55% jump in peak demand over four years implies heavy transmission work on the Houston Electric system, which is consistent with the higher capital plan.

We have assigned this story to our Houston market because the forecast applies to Houston Electric's system. It is not tied to any single site.

What remains unknown

The reviewed investor update does not name Batch Zero customers or projects; say how much of the expected load is data centers; give locations within the Houston Electric territory; say whether ERCOT's pause changes its December 2026 or April 2027 expectations; or define incremental demand beyond its exclusion from base and studied load. We did not review an ERCOT notice on the pause; that account comes from AEP's 10-Q.

Sources

  1. CenterPoint Energy, Inc., Third Quarter 2026 Investor Update (Form 8-K Exhibit 99.2) · Published 2026-10-27
  2. American Electric Power Company, Inc., Form 10-Q for the quarter ended September 30, 2026 · Published 2026-10-28

Explore the market

Related reporting

Development & Power

AEP details transmission terms for a proposed 10.4 GW Piketon, Ohio data center campus and raises its contracted load forecast to 84 GW

American Electric Power said in its third quarter 10-Q, filed October 28, 2026, that its Ohio transmission subsidiary, Ohio Power and an unnamed customer executed definitive agreements in August 2026 for three 765 kV transmission lines to support a proposed 10.4 GW data center campus in Piketon, Ohio. The agreements set a project budget of about $5 billion, the lines target in-service dates at the end of 2028, 2029 and 2030, and the first 800 MW of load is expected to use existing transmission. The project still needs PJM, PUCO and FERC approvals. Separately, AEP said it signed 15 GW of new load commitments in the quarter and expects incremental contracted load to reach 84 GW by 2031. [Source 1] [Source 2]

Piketon, Ohio (campus); AEP service territory for the load figures · Piketon campus Proposed (AEP's word). Transmission agreements executed August 2026; PJM, PUCO and FERC approvals still required. First 800 MW expected to use existing transmission; three 765 kV lines targeted for end of 2028, 2029 and 2030. AEP contracted load forecast 84 GW by 2031 (ESAs or letters of agreement), alongside about 49 GW of AEP Texas letters of agreement tied in part to a paused ERCOT Batch Zero process. As of October 28, 2026.
Read the analysis
Development & Power

FirstEnergy says contracted data center demand on its system has nearly doubled to about 7.9 GW in its long range forecast, with another 19 GW in its pipeline

FirstEnergy said in an October 27, 2026 investor presentation that contracted data center demand across its five state footprint has nearly doubled since year end 2025, to about 7.9 GW of cumulative demand forecast for 2036. It counts another 19 GW of pipeline demand, says it is in active contract negotiations with about 4 GW, and lists 117 GW of large load studies outside its pipeline. Contracted means a contract to construct facilities and/or an electric service agreement. In West Virginia, it says it is negotiating with a data center customer to take the long-term output of a planned gas plant. [Source 1]

FirstEnergy service territory in Ohio, Pennsylvania, Maryland, West Virginia and New Jersey · Utility demand forecast. FirstEnergy reports about 7.9 GW of contracted cumulative data center demand forecast for 2036 (construction contracts and/or electric service agreements), 19 GW of pipeline demand and 117 GW of load studies outside the pipeline. West Virginia gas plant off-take with a data center customer under negotiation. No project level status established. As of October 27, 2026.
Read the analysis
Development & Power

A planned 11-building data center campus in Putnam County, Georgia lists about 520 MW of estimated peak connected load in its state review filing

Putnam County, Georgia filed a Development of Regional Impact review with the state on October 26, 2026 for Eatonton 379, a proposed data center development on about 543 acres with about 11 buildings totaling about 3.5 million square feet. The filing lists an estimated peak connected electrical load of about 520 MW, names Tri-County EMC or Georgia Power as the energy supplier, and gives an estimated value at build-out of about $3.5 billion with completion in 2031. The developer is seeking a rezoning and a conditional use. Putnam County has a moratorium on data center land development permits that it extended on October 21, 2026 to November 17, 2026. [Source 1] [Source 2] [Source 4]

Unincorporated Putnam County, Georgia, off Glenwood Spring Road (33.304423, -83.406540) · Proposed. Developer seeking a rezoning and a conditional use from Putnam County; Georgia DRI #4861 filed October 26, 2026 with estimated completion in 2031. Putnam County data center moratorium extended October 21, 2026 to November 17, 2026. No zoning approval, utility agreement, construction, energization or availability established. As of October 27, 2026.