FirstEnergy says contracted data center demand on its system has nearly doubled to about 7.9 GW in its long range forecast, with another 19 GW in its pipeline

FirstEnergy said in an October 27, 2026 investor presentation that contracted data center demand across its five state footprint has nearly doubled since year end 2025, to about 7.9 GW of cumulative demand forecast for 2036. It counts another 19 GW of pipeline demand, says it is in active contract negotiations with about 4 GW, and lists 117 GW of large load studies outside its pipeline. Contracted means a contract to construct facilities and/or an electric service agreement. In West Virginia, it says it is negotiating with a data center customer to take the long-term output of a planned gas plant. [Source 1]

FirstEnergy says contracted data center demand on its system has nearly doubled to about 7.9 GW in its long range forecast, with another 19 GW in its pipeline
All news & analysisDevelopment & PowerFirstEnergy service territory in Ohio, Pennsylvania, Maryland, West Virginia and New JerseyUtility demand forecast. FirstEnergy reports about 7.9 GW of contracted cumulative data center demand forecast for 2036 (construction contracts and/or electric service agreements), 19 GW of pipeline demand and 117 GW of load studies outside the pipeline. West Virginia gas plant off-take with a data center customer under negotiation. No project level status established. As of October 27, 2026.

Disclosed terms

Contracted demand
Nearly doubled to about 8 GW (7,880 MW cumulative forecast for 2036) [1]
Contracted definition
A contract to construct facilities and/or an electric service agreement [1]
Cumulative demand table
Contracted 2,190 / 6,730 / 7,880 MW; pipeline none listed / 6,390 / 19,070 MW (2026 / 2031 / 2036 forecasts) [1]
Pipeline and negotiations
19 GW pipeline; active contract negotiations with about 4 GW [1]
Load studies outside pipeline
117 GW of studies larger than 500 MW [1]
West Virginia
Contracted and pipeline demand up about six times to about 6 GW this year [1]
Maidsville off-take
Negotiating with a data center customer to take the plant's long-term output [1]
Transmission rule of thumb
About $250 million of network upgrades per 1 GW [1]

The disclosure and our analysis

Evidence dates

Evidence: FirstEnergy Corp. Strategic and Financial Highlights presentation dated October 27, 2026, filed as Exhibit 99.2 to a Form 8-K. Read October 28, 2026. The presentation's demand figures are forecasts of cumulative data center demand for 2026, 2031 and 2036.

What FirstEnergy disclosed

1. **Contracted demand:** FirstEnergy says contracted data center demand nearly doubled, to about 8 GW. Its demand table gives contracted cumulative demand of 2,190 MW for 2026, 6,730 MW for 2031 and 7,880 MW for 2036. It defines contracted as a contract to construct facilities and/or an electric service agreement. [Source 1]

2. **Pipeline:** the company counts pipeline demand of 6,390 MW by 2031 and 19,070 MW by 2036, and says it is in active contract negotiations with about 4 GW. Contracted and pipeline demand together total 26,950 MW by 2036, which the presentation describes as about a 60% increase since year end 2025. [Source 1]

3. **Load studies:** separately, it lists 117 GW of potential additions not in its pipeline. These are trailing twelve month detailed and conceptual load studies larger than 500 MW that are not contracted or included in the pipeline. [Source 1]

4. **By state, 2036 forecast:** Ohio 2,570 MW contracted and 6,790 MW pipeline; Pennsylvania 2,010 MW contracted and 3,400 MW pipeline; Maryland 3,045 MW contracted and 1,585 MW pipeline; West Virginia 175 MW contracted and 5,870 MW pipeline; New Jersey 80 MW contracted and 1,425 MW pipeline. [Source 1]

5. **West Virginia:** FirstEnergy says contracted and pipeline demand in the state is up about six times to about 6 GW since the start of the year. It says it is advancing negotiations with a data center customer to serve as the long-term off-taker of the output of a planned combined cycle gas plant at Maidsville, expects approval of the plant's certificate in the fourth quarter of 2026, and has signed a turbine reservation agreement with a 2030 delivery date. It has also issued an initial request for proposals for an additional 3 GW of combined cycle plants. The customer is not named. [Source 1]

6. **Transmission:** the company gives a rule of thumb of about $250 million of transmission network upgrades for each 1 GW, says upgrades tied to contracted demand signed since February 2026 are not in its 2026 to 2030 investment plan, and expects to raise transmission investment by at least 25% from its current $19 billion plan. [Source 1]

How to read the megawatts

These are utility forecasts of cumulative data center demand on FirstEnergy's system, not critical IT load, facility capacity or available space. Contracted demand reflects construction contracts and/or electric service agreements; the presentation does not say how much is covered by signed service agreements, and does not count agreements. Pipeline demand is not contracted, and the 117 GW of load studies sits outside both. The presentation does not name customers, projects or counties.

Status

On our status vocabulary, these figures describe utility demand forecasts as of October 27, 2026. They establish no project level approval, construction, energization or availability. The West Virginia off-take agreement is under negotiation, not signed, according to the presentation.

Buyer analysis

This is our analysis, not FirstEnergy's. The split between contracted and pipeline demand is the useful signal. Maryland and Ohio carry the most contracted load, which points to where utility capacity is already spoken for. West Virginia is the opposite: little contracted today but a large pipeline, a gas plant being negotiated around a single data center customer, and a further 3 GW generation request, which makes it the state to watch for new large campus power in the FirstEnergy footprint.

The 117 GW of load studies, set against 27 GW of contracted plus pipeline demand, shows how much requested load is still speculative. Buyers evaluating sites served by FirstEnergy utilities should ask whether a provider's power is in the contracted column, and on what schedule, rather than relying on a load study or pipeline position.

We have not assigned this story to a tracked market. FirstEnergy serves parts of five states, and the presentation does not break demand down below the state level.

What remains unknown

The reviewed presentation does not name data center customers, projects, counties or operating utilities behind the figures; count signed electric service agreements; say how much of the contracted demand is under construction or energized today; give the size or terms of the planned Maidsville plant off-take, or name its customer; or define pipeline demand beyond distinguishing it from contracted demand and load studies.

Sources

  1. FirstEnergy Corp., Strategic and Financial Highlights presentation (Form 8-K Exhibit 99.2) · Published 2026-10-27

Related reporting

Development & Power

A planned 11-building data center campus in Putnam County, Georgia lists about 520 MW of estimated peak connected load in its state review filing

Putnam County, Georgia filed a Development of Regional Impact review with the state on October 26, 2026 for Eatonton 379, a proposed data center development on about 543 acres with about 11 buildings totaling about 3.5 million square feet. The filing lists an estimated peak connected electrical load of about 520 MW, names Tri-County EMC or Georgia Power as the energy supplier, and gives an estimated value at build-out of about $3.5 billion with completion in 2031. The developer is seeking a rezoning and a conditional use. Putnam County has a moratorium on data center land development permits that it extended on October 21, 2026 to November 17, 2026. [Source 1] [Source 2] [Source 4]

Unincorporated Putnam County, Georgia, off Glenwood Spring Road (33.304423, -83.406540) · Proposed. Developer seeking a rezoning and a conditional use from Putnam County; Georgia DRI #4861 filed October 26, 2026 with estimated completion in 2031. Putnam County data center moratorium extended October 21, 2026 to November 17, 2026. No zoning approval, utility agreement, construction, energization or availability established. As of October 27, 2026.
Read the analysis
Development & Power

NiSource signs a 20-year energy agreement with Microsoft for its northwest Indiana data center campus, adding about 1,100 MW of new generation to its GenCo pool

NiSource said on October 16, 2026 that it signed a long-term energy agreement with Microsoft for Microsoft's previously announced northwest Indiana campus. Microsoft is expected to begin taking electric service in 2028 under a 20-year term. NiSource says its GenCo pool portfolio will grow by about 1,100 MW, which it describes as new generation resources, and that Microsoft fully funds the generation and transmission needed to serve its load. GenCo also contracted 600 MW of battery storage under a long-term tolling agreement. The release does not give the campus's IT load or electric demand. [Source 1]

Northwest Indiana (site not named in the NiSource release) · Announced. NiSource and Microsoft long-term energy agreement disclosed October 16, 2026; 20-year electric service expected to begin in 2028. Regulatory approval status not stated. No campus capacity, construction, energization or availability established by the reviewed sources. As of October 26, 2026.
Read the analysis
Development & Power

A planned data center campus near Metter, Georgia lists 500 MW of estimated peak load from Georgia Power in a state regional impact filing

A Development of Regional Impact filing by Candler County, Georgia describes a data center campus on about 470 acres at 2700 Airport Road near Metter, next to the Metter-Candler Airport and south of Interstate 16. The forms list five buildings of up to 250,000 square feet each, an estimated peak connected electrical load of 500 MW from Georgia Power, and an overall completion year of 2033. The applicant is Canoochee River RV Resort, LLC, and no end user is named. The regional commission opened public comment on October 22, 2026, running through November 5. A regional impact review is not a zoning or permit approval. [Source 1] [Source 2] [Source 3] [Source 4]

2700 Airport Road, unincorporated Candler County near Metter, Georgia · Proposed. Georgia DRI #4846 filed by Candler County (dated October 5, 2026 on the state list, additional form submitted); regional commission comment period October 22 to November 5, 2026. Rezoning to a planned unit development and a permit requested. Overall completion listed as 2033. No zoning approval, utility agreement, lease, construction, energization or availability established. As of October 25, 2026.
Read the analysis