A planned 11-building data center campus in Putnam County, Georgia lists about 520 MW of estimated peak connected load in its state review filing

Putnam County, Georgia filed a Development of Regional Impact review with the state on October 26, 2026 for Eatonton 379, a proposed data center development on about 543 acres with about 11 buildings totaling about 3.5 million square feet. The filing lists an estimated peak connected electrical load of about 520 MW, names Tri-County EMC or Georgia Power as the energy supplier, and gives an estimated value at build-out of about $3.5 billion with completion in 2031. The developer is seeking a rezoning and a conditional use. Putnam County has a moratorium on data center land development permits that it extended on October 21, 2026 to November 17, 2026. [Source 1] [Source 2] [Source 4]

A planned 11-building data center campus in Putnam County, Georgia lists about 520 MW of estimated peak connected load in its state review filing
All news & analysisDevelopment & PowerUnincorporated Putnam County, Georgia, off Glenwood Spring Road (33.304423, -83.406540)Proposed. Developer seeking a rezoning and a conditional use from Putnam County; Georgia DRI #4861 filed October 26, 2026 with estimated completion in 2031. Putnam County data center moratorium extended October 21, 2026 to November 17, 2026. No zoning approval, utility agreement, construction, energization or availability established. As of October 27, 2026.

Disclosed terms

Site and buildings
About 543 acres, about 11 buildings, about 3.5 million square feet [1]
Estimated peak connected load
About 520 MW (filing estimate, not IT load) [2]
Energy supplier named
Tri-County EMC or Georgia Power [2]
Estimated value at build-out
About $3.5 billion [2]
Estimated completion
2031 [1]
Moratorium
Extended October 21, 2026 to November 17, 2026 [4]

The disclosure and our analysis

Evidence dates

Evidence: Georgia Department of Community Affairs Development of Regional Impact (DRI) filing #4861, initial form submitted October 26, 2026 and additional form shown as submitted on the state's DRI list, all read October 27, 2026. Putnam County news item on its data center moratorium, posted August 12, 2026 and updated with an October 21, 2026 extension, read October 27, 2026. Putnam County proposed Chapter 53 ordinance, read October 27, 2026.

What the filing discloses

Georgia's DRI process asks the local government to describe large projects so the regional commission can review their regional effects. Putnam County submitted the forms. The state does not approve or deny the project; zoning decisions stay with the local government. [Source 1] [Source 3]

1. **Project:** Eatonton 379, described as a data center development on about 543 acres of land with about 11 buildings that total about 3,501,600 square feet. The project size field gives 3,510,000 square feet. [Source 1]

2. **Location:** unincorporated Putnam County, at GPS coordinates 33.304423, -83.406540. The traffic section names Glenwood Spring Road as the road the two driveways would use. [Source 1] [Source 2]

3. **Developer:** Eatonton 379, LLC. The filing lists separate property owners. [Source 1]

4. **Approvals sought:** a rezoning and a conditional use. The filing says the project is not a phase of a larger project and gives 2031 as the estimated completion date. [Source 1]

5. **Power:** the filing names Tri-County EMC or Georgia Power Company as the energy supplier and lists an estimated peak connected electrical load of about 520 MW. It answers yes to whether existing transmission and distribution infrastructure is sufficient. It also answers yes to planned on-site generation beyond backup diesel generators, describing it as: the development will have substations, and the developer will work with the City of Eatonton to address any on-site generation needs. [Source 2]

6. **Economics:** estimated value at build-out of about $3.5 billion, about $37.35 million in estimated annual local tax revenue, and about 100 full-time employees. These are estimates entered on the form. [Source 2]

7. **Water and wastewater:** the Eatonton-Putnam Water and Sewer Authority is named for both, with estimated water demand of 0.075 million gallons per day and sewage flow of 0.07 million gallons per day. [Source 2]

How to read the megawatts

The 520 MW figure is the filing's estimated peak connected electrical load. It is not a critical IT load, a utility service commitment or leasable capacity, and the filing does not split it by building or phase. The filing does not say whether Tri-County EMC or Georgia Power has agreed to serve the load, and it names both as possible suppliers. The answer that existing transmission is sufficient is the filer's response on the form; we found no utility statement confirming it.

Local rules in motion

Putnam County's Board of Commissioners enacted a moratorium by resolution dated August 7, 2026 on the consideration of and action on any land development permit to allow the installation, construction or establishment of data centers, battery energy storage systems and solar energy systems. It was set to run three months, to November 6, 2026. On October 21, 2026, the board extended it to November 17, 2026. [Source 4]

The county has also posted proposed changes to its code, a new Chapter 53 covering energy creation, energy storage and digital infrastructure. As drafted, data centers would be a conditional use in the Agricultural district, permitted in the I-M Industrial-Manufacturing and Public districts, and prohibited in residential and commercial districts. The draft would cap data center buildings at 75 feet, require a 200-foot buffer along property lines that abut a residential district, limit sound to 55 dBA as an hourly average at property lines with existing homes or residential zoning, and require a closed-loop cooling system. These are proposed terms; the reviewed county pages do not show the ordinance as adopted. [Source 4] [Source 5]

Status

On our status vocabulary, Eatonton 379 is Proposed as of October 27, 2026: the developer is seeking a rezoning and a conditional use from Putnam County, and a state DRI review has been filed. No zoning approval, utility agreement, construction, energization or availability is established by the reviewed sources. The county's data center moratorium was in effect through at least November 17, 2026 as of the extension.

Buyer analysis

This is our analysis, not the filer's. The useful facts are the size and the timeline. About 520 MW of estimated peak load across 3.5 million square feet with a 2031 completion date is a long dated hyperscale scale project, not near-term capacity. The filing does not name an end user or operator.

The local path is the gating item. The project needs a rezoning and a conditional use from a county that has paused data center permits while it writes new rules. If the draft Chapter 53 is adopted as posted, its buffer, height, sound and closed-loop cooling terms would shape what can be built. Buyers watching middle Georgia should track the November county actions and the regional commission's DRI finding.

We have not assigned this project to a tracked market. Putnam County lies outside the metro areas Colocation Scout covers in Georgia.

What remains unknown

The reviewed filing and county pages do not name an end user, tenant or operator; give a critical IT load, phase schedule or per-building load; confirm which utility will serve the site or that either has agreed to; describe the substations or any on-site generation in detail; or give a hearing date for the rezoning and conditional use. They also do not show whether the proposed Chapter 53 ordinance has been adopted, or how the moratorium applies to this application.

Sources

  1. Georgia Department of Community Affairs, DRI #4861 Initial Information Form (submitted by Putnam County) · Published 2026-10-26
  2. Georgia Department of Community Affairs, DRI #4861 Information Form Part 2 · Published 2026-10-27
  3. Georgia Department of Community Affairs, DRI submissions list · Published 2026-10-27
  4. Putnam County, Georgia, data center moratorium news item · Published 2026-10-21
  5. Putnam County, Georgia, proposed Chapter 53 ordinance (energy creation, energy storage and digital infrastructure) · Published 2026-10-27

Related reporting

Development & Power

NiSource signs a 20-year energy agreement with Microsoft for its northwest Indiana data center campus, adding about 1,100 MW of new generation to its GenCo pool

NiSource said on October 16, 2026 that it signed a long-term energy agreement with Microsoft for Microsoft's previously announced northwest Indiana campus. Microsoft is expected to begin taking electric service in 2028 under a 20-year term. NiSource says its GenCo pool portfolio will grow by about 1,100 MW, which it describes as new generation resources, and that Microsoft fully funds the generation and transmission needed to serve its load. GenCo also contracted 600 MW of battery storage under a long-term tolling agreement. The release does not give the campus's IT load or electric demand. [Source 1]

Northwest Indiana (site not named in the NiSource release) · Announced. NiSource and Microsoft long-term energy agreement disclosed October 16, 2026; 20-year electric service expected to begin in 2028. Regulatory approval status not stated. No campus capacity, construction, energization or availability established by the reviewed sources. As of October 26, 2026.
Read the analysis
Development & Power

A planned data center campus near Metter, Georgia lists 500 MW of estimated peak load from Georgia Power in a state regional impact filing

A Development of Regional Impact filing by Candler County, Georgia describes a data center campus on about 470 acres at 2700 Airport Road near Metter, next to the Metter-Candler Airport and south of Interstate 16. The forms list five buildings of up to 250,000 square feet each, an estimated peak connected electrical load of 500 MW from Georgia Power, and an overall completion year of 2033. The applicant is Canoochee River RV Resort, LLC, and no end user is named. The regional commission opened public comment on October 22, 2026, running through November 5. A regional impact review is not a zoning or permit approval. [Source 1] [Source 2] [Source 3] [Source 4]

2700 Airport Road, unincorporated Candler County near Metter, Georgia · Proposed. Georgia DRI #4846 filed by Candler County (dated October 5, 2026 on the state list, additional form submitted); regional commission comment period October 22 to November 5, 2026. Rezoning to a planned unit development and a permit requested. Overall completion listed as 2033. No zoning approval, utility agreement, lease, construction, energization or availability established. As of October 25, 2026.
Read the analysis
Development & Power

Loudoun County now requires utility power and site disclosures from data center applicants expecting to need 100 MW or more

Loudoun County, Virginia said on October 23, 2026 that it now requires extra documentation from land use applicants for a High Energy Use Facility, defined in a 2026 state law as a facility expected to need 100 megawatts or more from a retail electric utility. Applicants must file an affidavit with copies of their correspondence with the utility showing the energy and voltage needed at full build out, and the utility must describe the substations and transmission voltage that would serve the site. A sound and environmental site assessment is also required. The county says the rules apply to all current and future rezoning, special exception and special use permit applications, not to by right approvals. [Source 1] [Source 2]

Loudoun County, Virginia · In effect for Loudoun County legislative land use applications (rezonings, special exceptions, special use permits) as announced October 23, 2026, under Code of Virginia § 15.2-2209.5 (2026 Acts cc. 567, 568). Applies to facilities expected to need 100 MW or more from a retail utility; by right approvals excluded. Not a moratorium. As of October 25, 2026.