A planned data center campus near Metter, Georgia lists 500 MW of estimated peak load from Georgia Power in a state regional impact filing

A Development of Regional Impact filing by Candler County, Georgia describes a data center campus on about 470 acres at 2700 Airport Road near Metter, next to the Metter-Candler Airport and south of Interstate 16. The forms list five buildings of up to 250,000 square feet each, an estimated peak connected electrical load of 500 MW from Georgia Power, and an overall completion year of 2033. The applicant is Canoochee River RV Resort, LLC, and no end user is named. The regional commission opened public comment on October 22, 2026, running through November 5. A regional impact review is not a zoning or permit approval. [Source 1] [Source 2] [Source 3] [Source 4]

A planned data center campus near Metter, Georgia lists 500 MW of estimated peak load from Georgia Power in a state regional impact filing
All news & analysisDevelopment & Power2700 Airport Road, unincorporated Candler County near Metter, GeorgiaProposed. Georgia DRI #4846 filed by Candler County (dated October 5, 2026 on the state list, additional form submitted); regional commission comment period October 22 to November 5, 2026. Rezoning to a planned unit development and a permit requested. Overall completion listed as 2033. No zoning approval, utility agreement, lease, construction, energization or availability established. As of October 25, 2026.

Disclosed terms

Estimated peak connected electrical load
500 MW, Georgia Power [2]
Buildings
Five buildings of up to 250,000 square feet each [1]
Site
About 470 acres next to the Metter-Candler Airport, south of Interstate 16 [1]
Developer
Canoochee River RV Resort, LLC [1]
Overall completion
2033 [1]
Estimated value at build out
$35 billion, applicant estimate [2]
Water demand
0.2 MGD, ground water [2]
Public comment
October 22 to November 5, 2026 [4]
Target lease execution
September 1, 2027 [5]
Leasing intent
Applicant intends to lease improved portions to tenants [5]

The disclosure and our analysis

Evidence dates

Evidence: Georgia Department of Community Affairs Development of Regional Impact (DRI) #4846, initial and additional information forms, and the state DRI submissions list, which shows the filing dated October 5, 2026 with status Additional Form Submitted; the Heart of Georgia Altamaha Regional Commission request for comments dated October 22, 2026; and the applicant's zoning supplement and backup power response posted on Candler County's data center information page. All read October 25, 2026.

What the filings show

Candler County submitted the DRI forms. The project is named the Canoochee River RV Resort Data Center Project, and the developer and applicant is Canoochee River RV Resort, LLC of Savannah. The county marks rezoning and a permit as the local actions requested. [Source 1] [Source 3]

1. **Site:** about 470 acres adjacent to the Metter-Candler Airport and south of Interstate 16, at 2700 Airport Road, Metter. [Source 1]

2. **Buildings:** five buildings of up to 250,000 square feet each, with parking, mechanical yards, substations, a well site, retention ponds and access roads. [Source 1]

3. **Timing:** the initial form says the developer seeks to build in phases over 5 to 7 years, and lists 2033 as the overall completion year. [Source 1]

4. **Value:** the additional form lists an estimated value at build out of $35 billion and 200 full time employees. These are the applicant's estimates. [Source 2]

Power and water

The additional form lists Georgia Power as the energy supply provider and an estimated peak connected electrical load of 500 MW. That is the form's own basis, a peak connected electrical load for the whole development. It is not a critical IT load figure, and the form does not split it by building or phase. The form answers yes to whether existing transmission and distribution infrastructure is sufficient to serve the project. That is the applicant's answer on a state form; we did not find a Georgia Power study or service agreement in the reviewed documents. [Source 2]

Water would come from ground water, at an estimated 0.2 MGD, with on-site septic for wastewater. The applicant's own materials on the county page describe a closed loop cooling system. [Source 2] [Source 7]

In a written answer to county questions, the developer says backup generators will be chosen after detailed design, once the end user's reliability requirements are set, and that any generator must use EPA Tier 4 Final certified engines and run only for emergencies and short daytime tests. It says the team is also evaluating a battery first design. [Source 6]

Schedule and leasing intent

A supplement to the zoning application, posted on the county page, gives this schedule: an item labeled FEA/CIAC on June 1, 2027; lease execution on September 1, 2027; construction start on building 1 on October 1, 2027 and on buildings 2 to 4 on March 1, 2028; building 1 completion on October 1, 2028; and buildings 2 to 4 completion on March 1, 2029. The document does not define FEA/CIAC. In utility practice those abbreviations usually refer to a facilities extension agreement and a contribution in aid of construction; that is our reading, not the document's. [Source 5]

The same supplement says the applicant intends to lease the improved portions of the site to tenants who will occupy and use the improvements. [Source 5]

The documents do not line up exactly. The DRI forms describe five buildings and completion in 2033, while the zoning supplement's schedule covers buildings 1 through 4 and ends in March 2029. The reviewed sources do not explain the difference.

Status

On our status vocabulary, this campus is Proposed as of October 25, 2026. A rezoning to a planned unit development and a permit are being sought, and the regional commission's comment period runs from October 22 to November 5, 2026. No county zoning decision, Georgia Power agreement, lease, construction or energization is established by the reviewed sources.

Buyer analysis

This is our analysis, not the developer's. Unlike a hyperscaler self build, this filing describes a landlord model: the applicant intends to lease the buildings, with lease execution targeted for September 2027. A 500 MW peak load request in rural southeast Georgia adds to the large loads asking for Georgia Power service, and the schedule depends on a utility agreement milestone in June 2027 that is not yet in place.

For buyers, the useful dates are the November 5 comment deadline and the county's zoning hearings. A campus at this stage is not inventory. Anyone tracking capacity in the Southeast should treat the 2028 first building date as a developer target until a utility agreement and a named tenant appear.

We have not assigned this project to a tracked market. Metter is inland from Savannah and far from metro Atlanta, and Colocation Scout does not publish a market guide that covers it.

What remains unknown

The reviewed sources do not name an end user or tenant, give critical IT capacity, split the 500 MW by building or phase, show a Georgia Power study, service or facilities agreement, give the dates of the Candler County zoning hearings, define the FEA/CIAC milestone, or reconcile the five buildings and 2033 completion in the DRI forms with the four building schedule ending in 2029 in the zoning supplement. The regional commission's findings have not been issued.

Sources

  1. Georgia Department of Community Affairs, DRI #4846 initial information form (Canoochee River RV Resort Data Center Project) · Published 2026-10-05
  2. Georgia Department of Community Affairs, DRI #4846 additional information form · Published 2026-10-25
  3. Georgia Department of Community Affairs, DRI submissions list · Published 2026-10-25
  4. Heart of Georgia Altamaha Regional Commission, request for comment on DRI #4846 (posted by Candler County) · Published 2026-10-22
  5. Canoochee River RV Resort, LLC, supplement to zoning change application (posted by Candler County, undated; read October 25, 2026) · Published 2026-10-25
  6. Candler County, county questions on backup power with developer response (undated; read October 25, 2026) · Published 2026-10-25
  7. Candler County, data center information page · Published 2026-10-25

Related reporting

Development & Power

Loudoun County now requires utility power and site disclosures from data center applicants expecting to need 100 MW or more

Loudoun County, Virginia said on October 23, 2026 that it now requires extra documentation from land use applicants for a High Energy Use Facility, defined in a 2026 state law as a facility expected to need 100 megawatts or more from a retail electric utility. Applicants must file an affidavit with copies of their correspondence with the utility showing the energy and voltage needed at full build out, and the utility must describe the substations and transmission voltage that would serve the site. A sound and environmental site assessment is also required. The county says the rules apply to all current and future rezoning, special exception and special use permit applications, not to by right approvals. [Source 1] [Source 2]

Loudoun County, Virginia · In effect for Loudoun County legislative land use applications (rezonings, special exceptions, special use permits) as announced October 23, 2026, under Code of Virginia § 15.2-2209.5 (2026 Acts cc. 567, 568). Applies to facilities expected to need 100 MW or more from a retail utility; by right approvals excluded. Not a moratorium. As of October 25, 2026.
Read the analysis
Development & Power

Loudoun supervisors back a preliminary deal that would keep data centers off the former GWU campus in Ashburn that Amazon bought

Loudoun County's Board of Supervisors voted unanimously on October 20, 2026 on measures intended to eliminate potential data center uses on George Washington University's Virginia Science and Technology Campus in Ashburn, which Amazon Web Services bought earlier this year. Under terms announced at the meeting, Amazon would convey about 25 acres to the county, the board would fast track rezoning of the remaining 97 acres for housing and mixed use, and Amazon stated its intent to withdraw its data center application and forgo legal action over data centers at the site. The county says final agreements still have to be negotiated. [Source 1]

George Washington University Virginia Science and Technology Campus, Ashburn, Loudoun County, Virginia · Preliminary agreement. Board of Supervisors voted unanimously October 20, 2026 to authorize negotiations; final agreements pending. Amazon stated its intent to withdraw its data center application; withdrawal filing not confirmed in the county release. As of October 25, 2026.
Read the analysis
Development & Power

Microsoft's ATL80 data center campus in Floyd County, Georgia lists 422 MW of estimated peak load in a state regional impact filing

A Development of Regional Impact filing submitted October 20, 2026 by Floyd County, Georgia describes ATL80, a data center development by Microsoft on Huffaker Road. The forms list three buildings totaling up to 1,659,000 square feet on 349.03 acres, an overall completion year of 2032, and an estimated peak connected electrical load of 422 MW/444 MVA from Georgia Power, served through an on-site substation and a transmission line extension. The state listing shows the review as Certified Complete. A regional impact review is not a zoning or permit approval. [Source 1] [Source 2] [Source 3]

0 Huffaker Road, unincorporated Floyd County, Georgia · Proposed. Georgia DRI #4860 initial form submitted October 20, 2026; state listing shows the review as Certified Complete. A DRI review is not a zoning, permit or utility approval. Overall completion listed as 2032. No construction, energization, lease or availability established by the reviewed sources. As of October 24, 2026.
Read the analysis