Loudoun supervisors back a preliminary deal that would keep data centers off the former GWU campus in Ashburn that Amazon bought

Loudoun County's Board of Supervisors voted unanimously on October 20, 2026 on measures intended to eliminate potential data center uses on George Washington University's Virginia Science and Technology Campus in Ashburn, which Amazon Web Services bought earlier this year. Under terms announced at the meeting, Amazon would convey about 25 acres to the county, the board would fast track rezoning of the remaining 97 acres for housing and mixed use, and Amazon stated its intent to withdraw its data center application and forgo legal action over data centers at the site. The county says final agreements still have to be negotiated. [Source 1]

Loudoun supervisors back a preliminary deal that would keep data centers off the former GWU campus in Ashburn that Amazon bought
All news & analysisDevelopment & PowerGeorge Washington University Virginia Science and Technology Campus, Ashburn, Loudoun County, VirginiaPreliminary agreement. Board of Supervisors voted unanimously October 20, 2026 to authorize negotiations; final agreements pending. Amazon stated its intent to withdraw its data center application; withdrawal filing not confirmed in the county release. As of October 25, 2026.

Disclosed terms

Board vote
Unanimous, October 20, 2026 [1]
Land to county
About 25 acres, fair market value $65 million [1]
Rezoning
Remaining 97 acres fast tracked for housing and mixed use [1]
Data center application
Amazon stated intent to withdraw [1]
Housing fund
$5 million offered [1]
Status
Final agreements still to be negotiated [1]

The disclosure and our analysis

Evidence dates

Evidence: Loudoun County news release posted October 22, 2026, describing the Board of Supervisors vote at its October 20, 2026 meeting. Read October 25, 2026.

What the county announced

The county describes a tentative deal reached after negotiations between Amazon Web Services, Board Chair Phyllis J. Randall and county officials. Chair Randall and Amazon call it Project Potomac Promise. [Source 1]

1. **Land:** Amazon agreed to convey about 25 acres to the county, which the county values at a fair market value of $65 million. The county says it may use the land for an indoor sports and recreation facility and a community arts center. [Source 1]

2. **Rezoning:** the board agreed to fast track rezoning of the remaining 97 acres, which Amazon will keep, to permit a broad range of housing and mixed use development. [Source 1]

3. **Housing fund:** Amazon offered to donate $5 million to the county's housing trust fund. [Source 1]

4. **Data centers:** Amazon stated its intent to withdraw its application for data centers at the site and to forgo any legal action over data center development there. Chair Randall is quoted saying there will be no data centers or infrastructure supporting data centers on the campus. [Source 1]

The county says the university will keep operating at the site for the next four and a half years, and that AWS plans to keep using the existing university buildings for educational purposes. [Source 1]

Status

This is a preliminary agreement as of October 25, 2026. The board's vote authorizes the county administrator to keep negotiating with AWS to finalize terms in the coming weeks and months. The release says Amazon stated its intent to withdraw its data center application; it does not say the withdrawal has been filed. The housing and mixed use rezoning has not yet been approved.

The county release does not give the size, building count or power of the data center plan that would be dropped. We have not used figures from other reports because we could not confirm them in a primary source.

Buyer analysis

This is our analysis, not the county's or Amazon's. A planned Amazon data center site in Ashburn, the core of the Northern Virginia market, is set to become housing instead. The site was planned for Amazon's own use, so this does not remove colocation inventory that a buyer could have leased. It does show how hard new data center entitlements have become inside Loudoun.

For buyers, that points to existing and already approved Ashburn campuses carrying more of the market's future supply, and to more new capacity landing in neighboring counties. Buyers with Northern Virginia requirements should weight entitled and energized space over proposals that still need Loudoun approvals.

What remains unknown

The county release does not give the size, building count or power of Amazon's data center plan for the site, the application number, the purchase price, the timing of the formal withdrawal, or the schedule for the housing rezoning. Final agreements have not been published.

Sources

  1. Loudoun County, news release on preliminary agreement with Amazon for the GWU campus in Ashburn · Published 2026-10-22

Explore the market

Related reporting

Development & Power

A planned data center campus near Metter, Georgia lists 500 MW of estimated peak load from Georgia Power in a state regional impact filing

A Development of Regional Impact filing by Candler County, Georgia describes a data center campus on about 470 acres at 2700 Airport Road near Metter, next to the Metter-Candler Airport and south of Interstate 16. The forms list five buildings of up to 250,000 square feet each, an estimated peak connected electrical load of 500 MW from Georgia Power, and an overall completion year of 2033. The applicant is Canoochee River RV Resort, LLC, and no end user is named. The regional commission opened public comment on October 22, 2026, running through November 5. A regional impact review is not a zoning or permit approval. [Source 1] [Source 2] [Source 3] [Source 4]

2700 Airport Road, unincorporated Candler County near Metter, Georgia · Proposed. Georgia DRI #4846 filed by Candler County (dated October 5, 2026 on the state list, additional form submitted); regional commission comment period October 22 to November 5, 2026. Rezoning to a planned unit development and a permit requested. Overall completion listed as 2033. No zoning approval, utility agreement, lease, construction, energization or availability established. As of October 25, 2026.
Read the analysis
Development & Power

Loudoun County now requires utility power and site disclosures from data center applicants expecting to need 100 MW or more

Loudoun County, Virginia said on October 23, 2026 that it now requires extra documentation from land use applicants for a High Energy Use Facility, defined in a 2026 state law as a facility expected to need 100 megawatts or more from a retail electric utility. Applicants must file an affidavit with copies of their correspondence with the utility showing the energy and voltage needed at full build out, and the utility must describe the substations and transmission voltage that would serve the site. A sound and environmental site assessment is also required. The county says the rules apply to all current and future rezoning, special exception and special use permit applications, not to by right approvals. [Source 1] [Source 2]

Loudoun County, Virginia · In effect for Loudoun County legislative land use applications (rezonings, special exceptions, special use permits) as announced October 23, 2026, under Code of Virginia § 15.2-2209.5 (2026 Acts cc. 567, 568). Applies to facilities expected to need 100 MW or more from a retail utility; by right approvals excluded. Not a moratorium. As of October 25, 2026.
Read the analysis
Development & Power

Microsoft's ATL80 data center campus in Floyd County, Georgia lists 422 MW of estimated peak load in a state regional impact filing

A Development of Regional Impact filing submitted October 20, 2026 by Floyd County, Georgia describes ATL80, a data center development by Microsoft on Huffaker Road. The forms list three buildings totaling up to 1,659,000 square feet on 349.03 acres, an overall completion year of 2032, and an estimated peak connected electrical load of 422 MW/444 MVA from Georgia Power, served through an on-site substation and a transmission line extension. The state listing shows the review as Certified Complete. A regional impact review is not a zoning or permit approval. [Source 1] [Source 2] [Source 3]

0 Huffaker Road, unincorporated Floyd County, Georgia · Proposed. Georgia DRI #4860 initial form submitted October 20, 2026; state listing shows the review as Certified Complete. A DRI review is not a zoning, permit or utility approval. Overall completion listed as 2032. No construction, energization, lease or availability established by the reviewed sources. As of October 24, 2026.