Portland General lists 473 MW of executed data center contracts under construction, plus a separate contract for up to 420 MW

Portland General Electric said in its third quarter 2026 earnings slides, filed October 29, 2026, that 473 MW of executed 2025 and 2026 contracts with five data center customers are under construction. A further 2026 executed contract of up to 420 MW is not under construction and is expected to energize in 2028, ramping to full capacity in 2033. PGE also lists a pipeline of 1.3 GW of incremental large load requests to be energized in 2028 and beyond. PGE says the values represent customer capacity as of October 29, 2026. [Source 1]

Portland General lists 473 MW of executed data center contracts under construction, plus a separate contract for up to 420 MW
All news & analysisDevelopment & PowerPortland General Electric service area, OregonUtility contracts. 473 MW of executed 2025 and 2026 contracts with five data center customers under construction (PGE's words). Up to 420 MW 2026 executed contract not under construction, expected energization 2028, full capacity 2033. 1.3 GW of incremental large load requests for 2028 and beyond. Customer capacity as of October 29, 2026.

Disclosed terms

Under construction
473 MW of 2025 and 2026 executed contracts, five data center customers (customer capacity) [1]
2028 contract
Up to 420 MW, executed 2026, not under construction; energization expected 2028, full capacity 2033 [1]
Pipeline
1.3 GW of incremental large load requests for 2028 and beyond [1]
As of
Customer capacity as of October 29, 2026 [1]
Contract protections
Capacity deposits, collateral, minimum demand requirements, exit fees [1]
Data center rate change
Average 29.7% increase for data center customers, effective July 8, 2026 [2]

The disclosure and our analysis

Evidence dates

Evidence: Portland General Electric Company third quarter 2026 earnings presentation, filed as Exhibit 99.2 to a Form 8-K on October 29, 2026, and PGE's Form 10-Q for the quarter ended September 30, 2026, filed October 29, 2026. Read October 30, 2026. PGE states that its figures represent customer capacity as of October 29, 2026.

What PGE disclosed

1. **Under construction:** PGE lists 473 MW of 2025 and 2026 executed contracts under construction with five data center customers, included in its pipeline. [Source 1]

2. **Next contract:** PGE lists up to 420 MW under a 2026 executed contract that is not under construction, with expected energization in 2028 and a ramp to full capacity in 2033. [Source 1]

3. **Pipeline:** PGE lists an additional pipeline of 1.3 GW of incremental large load requests to be energized in 2028 and beyond. [Source 1]

4. **Contract protections:** PGE says its contractual protections include capacity deposits, collateral, minimum demand requirements and exit fees. It describes the data center class as its highest growth customer class, at about 12% CAGR, under Oregon's new large load tariff. [Source 1]

The tariff behind the contracts

PGE's 10-Q says the Public Utility Commission of Oregon approved a filing in April 2025 that let PGE form a load interconnection queue, study and allocate connection costs, and offer study and service agreements to new large load customers, subject to a continuing review in docket UM 2377. That docket also covers a data center customer classification required by Oregon's HB 3546. PGE says agreements with new large load customers may be revised based on the outcome of UM 2377. [Source 2]

The 10-Q also says the OPUC approved a new Data Center Standard Service tariff at a public meeting on July 7, 2026, with prices effective July 8, 2026, and that the overall price changes in that filing produced an average rate increase of 29.7% for data center customers. [Source 2]

How to read the megawatts

PGE labels these figures customer capacity. They are utility contract and request figures, not critical IT load, and the slides do not say how a customer's contracted capacity relates to the IT load it will deploy. The 473 MW and the 420 MW are separate contract groups at different stages. The 1.3 GW is requests, not contracts. None of these figures is space offered to new customers.

PGE does not name the five customers or the 2028 customer, and the slides do not give site locations within its service area.

Status

On our status vocabulary, as of October 29, 2026: PGE describes 473 MW of executed contracts as under construction, in its own words; the slides do not say which facilities or power blocks that covers. The 420 MW contract is executed but not under construction, with energization expected in 2028. The 1.3 GW is requests only. Nothing here establishes energization or capacity Available to new customers.

Buyer analysis

This is our analysis, not PGE's. The useful number for buyers is the date. A 2026 contract that PGE does not expect to energize until 2028, and not to reach full capacity until 2033, shows how long new large load takes to arrive in PGE territory even after a contract is signed. New requests in the 1.3 GW pipeline are slotted for 2028 and beyond.

For buyers who need capacity in the Portland and Hillsboro area sooner, that points to providers whose power is already in the 473 MW under construction or otherwise contracted. Ask any provider whether its capacity sits inside an executed PGE contract, which phase it is in, and what deposits, minimum demand or exit fee terms it passes through to tenants. Under the new data center rate, also ask how the July 2026 price change flows into power pass through charges.

We have assigned this story to our Hillsboro and Portland market because these are PGE service area figures. PGE did not disclose individual site locations.

What remains unknown

The reviewed filings do not name the five data center customers or the 2028 customer; give site locations; say what part of each facility the 473 MW under construction covers; give energization dates for the 473 MW; relate customer capacity to critical IT load; or say how many of the 1.3 GW of requests are data centers. PGE says agreements may be revised based on the outcome of OPUC docket UM 2377, which the reviewed filings do not say has concluded.

Sources

  1. Portland General Electric Company, Q3 2026 earnings presentation (Form 8-K Exhibit 99.2) · Published 2026-10-29
  2. Portland General Electric Company, Form 10-Q for the quarter ended September 30, 2026 · Published 2026-10-29

Explore the market

Related reporting

Development & Power

Exelon counts about 11 GW of high probability data center load, 9 GW of it at ComEd, with 23 GW more in cluster studies

Exelon said in its third quarter 2026 earnings slides, filed October 30, 2026, that it counts about 11 GW of high probability data center load: about 9 GW at ComEd and about 2 GW in its MidAtlantic utilities. It defines that tier as load in advanced phases of design or backed by FERC approved transmission security agreements, and says about 45% has those agreements, backed by about $1.2 billion in collateral. A further future pipeline of about 23 GW, 14 GW at ComEd and 9 GW MidAtlantic, sits within current or future cluster studies due to conclude in 2026 and 2027. [Source 1]

ComEd service area, northern Illinois; Exelon MidAtlantic utilities · Utility forecast. About 11 GW high probability data center load (ComEd about 9 GW, MidAtlantic about 2 GW), in advanced design or backed by FERC approved TSAs; about 45% with TSAs and about $1.2 billion collateral. Future pipeline about 23 GW in cluster studies concluding 2026 and 2027. As of October 30, 2026.
Read the analysis
Development & Power

AEP details transmission terms for a proposed 10.4 GW Piketon, Ohio data center campus and raises its contracted load forecast to 84 GW

American Electric Power said in its third quarter 10-Q, filed October 28, 2026, that its Ohio transmission subsidiary, Ohio Power and an unnamed customer executed definitive agreements in August 2026 for three 765 kV transmission lines to support a proposed 10.4 GW data center campus in Piketon, Ohio. The agreements set a project budget of about $5 billion, the lines target in-service dates at the end of 2028, 2029 and 2030, and the first 800 MW of load is expected to use existing transmission. The project still needs PJM, PUCO and FERC approvals. Separately, AEP said it signed 15 GW of new load commitments in the quarter and expects incremental contracted load to reach 84 GW by 2031. [Source 1] [Source 2]

Piketon, Ohio (campus); AEP service territory for the load figures · Piketon campus Proposed (AEP's word). Transmission agreements executed August 2026; PJM, PUCO and FERC approvals still required. First 800 MW expected to use existing transmission; three 765 kV lines targeted for end of 2028, 2029 and 2030. AEP contracted load forecast 84 GW by 2031 (ESAs or letters of agreement), alongside about 49 GW of AEP Texas letters of agreement tied in part to a paused ERCOT Batch Zero process. As of October 28, 2026.
Read the analysis
Development & Power

CenterPoint expects about 12 GW of ERCOT Batch Zero large load on its Houston system, pending ERCOT allocation decisions

CenterPoint Energy said in an October 27, 2026 investor update that it expects about 12 GW of new large load from ERCOT's Batch Zero process to be energized on its Houston Electric system by 2030, rising from about 3 GW in 2027. It compares that with a current system peak of 21 GW. CenterPoint says ERCOT is expected to decide how much counts as base load in December 2026 and how much is allocated as studied load in April 2027, and that actual demand may be lower. AEP's 10-Q, filed a day later, says ERCOT has paused Batch Zero classification and study work pending a state directed verification. [Source 1] [Source 2]

CenterPoint Houston Electric service territory, Greater Houston, Texas · Utility forecast. CenterPoint expects about 12 GW of Batch Zero large load energized on Houston Electric by 2030 (3 GW in 2027), against a 21 GW current peak. ERCOT base load determination expected December 2026 and studied load allocation April 2027, per CenterPoint. AEP's 10-Q says ERCOT has paused Batch Zero classification and study. No project level status established. As of October 27 and 28, 2026.
Read the analysis