A data center building near Quanah, Texas is registered with state regulators at a listed $8 billion

A Texas Department of Licensing and Regulation (TDLR) filing created October 27, 2026 registers Clocktower NWB 05, a single story data center building with an office component of 288,355 square feet at 4628 Four Corners Road, Quanah, in Hardeman County. The owner is listed as 19000-200 Holdings, LLC of Dallas. The registration lists an estimated cost of $8,000,000,000 and construction from November 1, 2026 to December 31, 2028. No tenant is assigned. [Source 1]

A data center building near Quanah, Texas is registered with state regulators at a listed $8 billion
All news & analysisDevelopment & Power4628 Four Corners Road, Quanah, Hardeman County, TexasProposed (TDLR accessibility registration created October 27, 2026; listed construction November 1, 2026 to December 31, 2028). Not a building permit. No tenant assigned. No megawatt figure disclosed.

Disclosed terms

Registration
TDLR TABS2027004544, created October 27, 2026, Project Registered [1]
Building
Single story data center with office component, 288,355 square feet [1]
Estimated cost
$8,000,000,000 as listed by the filer; scope not stated [1]
Construction dates
November 1, 2026 to December 31, 2028, as listed [1]
Owner
19000-200 Holdings, LLC, Dallas; tenant not assigned [1]

The disclosure and our analysis

Evidence dates

Evidence: TDLR Texas Architectural Barriers project registration TABS2027004544, created October 27, 2026, status Project Registered. Read November 1, 2026.

What the state filing shows

1. **Project:** The registration is titled Clocktower NWB 05, with the facility named Building 5, Network. Its scope reads: new construction of a single story data center with an office component, a pre-engineered metal building with an insulated metal panel skin, 288,355 square feet. [Source 1]

2. **Location:** 4628 Four Corners Road, Quanah, Texas 79252, Hardeman County. [Source 1]

3. **Cost and dates:** Estimated cost of $8,000,000,000. Start date November 1, 2026 and completion date December 31, 2028, as listed. Type of work is new construction, privately funded on private land. [Source 1]

4. **Parties:** Owner 19000-200 Holdings, LLC, 17000 Dallas Parkway, Suite 200, Dallas. Design firm JHET Architects of Dallas. Tenant: not assigned. The filing says the private funds are not provided by a tenant. [Source 1]

How to read the filing

TDLR registrations are filed for state accessibility review. They are not building permits and do not establish that construction has started. The estimated cost and dates are entered by the filer.

The $8 billion estimate is far larger than a single 288,355 square foot shell would usually carry. For comparison, a TDLR registration we covered for Skybox Hutto 4 near Austin listed $550 million for about 846,300 square feet of core and shell. The Quanah filing does not say whether its figure covers equipment, other buildings, power infrastructure or a wider campus. We report it as filed and do not treat it as the cost of this building.

The name Building 5 suggests other buildings may be planned. A search of TDLR records on November 1, 2026 by project name, owner and address returned only this registration.

Status

On our status vocabulary, as of October 27, 2026: Proposed. A state accessibility registration is on file with listed construction from November 2026 to December 2028. The reviewed record does not establish local approvals, construction, a power supply, energization or capacity Available to tenants.

Buyer analysis

This is our analysis. The filing gives square footage, dates and a cost figure, not megawatts, so it says nothing yet about how much IT load the site could carry or on what power basis. The location is rural north Texas, near the Oklahoma border, outside the markets we currently track.

For buyers, an unassigned tenant field two years before listed completion can mean a speculative or not yet announced project. The questions to ask the developer are who stands behind the owner entity, what utility or on-site generation would serve the site and when, how many buildings are planned, and what the $8 billion figure covers.

What remains unknown

The reviewed record does not disclose megawatts on any power basis, the utility or generation source, the companies behind 19000-200 Holdings, LLC, any end user or tenant, the number of buildings planned, what the $8 billion estimate covers, or the status of any county or other permits. We found no other public filing for the project in the sources we reviewed.

Sources

  1. Texas Department of Licensing and Regulation, TABS project registration TABS2027004544 (Clocktower NWB 05) · Published 2026-10-27

Related reporting

Development & Power

Alliant Energy reports 3.4 GW of contracted data center demand in Iowa and Wisconsin and a proposed 15 year large load tariff

Alliant Energy said on October 29, 2026 that its Iowa and Wisconsin utilities, Interstate Power and Light (IPL) and Wisconsin Power and Light (WPL), have 3.4 gigawatts of contracted demand from data centers, and it raised its 2027 to 2030 capital expenditure forecast by 19% to $15.9 billion. Its quarterly report, filed October 30, 2026, adds that WPL has asked Wisconsin regulators to approve a large load tariff requiring a 15 year initial service term for customers of 100 MW or more, and that IPL filed in October 2026 for Iowa approval of an individual customer rate for another data center. The 3.4 GW is contracted demand, not critical IT load. [Source 1] [Source 2]

Interstate Power and Light (Iowa) and Wisconsin Power and Light (Wisconsin) service territories; specific sites not disclosed · Contracted demand of 3.4 GW (utility contracted demand, not IT load) as of October 29, 2026. WPL individual customer rate Approved by the PSCW in June 2026 with conditions; WPL large load tariff (15 year term, 100 MW threshold) Proposed September 2026, decision expected first half of 2027; IPL individual customer rate Proposed October 2026, decision expected first quarter of 2027.
Read the analysis
Development & Power

TerraVolt takes options on 1,077 acres in Cassia County, Idaho for a planned behind the meter data center campus

TerraVolt Holdings said in a Form 8-K filed October 30, 2026 that on October 26, 2026 it entered two option agreements, dated October 23, 2026, to buy about 1,077 acres in Cassia County, Idaho, outside the town of Declo, at $30,000 per acre. TerraVolt says it intends to develop the site as a master-planned, behind the meter digital infrastructure campus designed to support an initial 240 MW of dedicated on-site power generation. That figure is generation capacity, not critical IT load. The options expire October 23, 2027, with a paid six month extension available. [Source 1] [Source 2]

Cassia County, Idaho, outside Declo, near State Highway 81 and Interstate 84 · Announced campus plan with land under option, as of October 30, 2026. Options on about 1,077 acres at $30,000 per acre expire October 23, 2027 (extendable six months). Initial 240 MW of planned on-site generation (generation capacity, not IT load). Permitting and design still to come.
Read the analysis
Development & Power

Oklahoma City rezones two Frisco Road parcels for a data center campus, with a potable water cap and power contract conditions

The Oklahoma City Council on October 27, 2026 adopted ordinances rezoning two parcels near I-40 and Frisco Road, about 110 acres at 3025 North Frisco Road (PUD-2105) and about 184 acres at 13921 NW 23rd Street (PUD-2124), to planned unit developments that permit data centers. Each ordinance passed 6 to 3 and was adopted without the emergency clause. The master design statements, prepared for developer BLE Landholdings, LLC, cap combined potable water use at 75,000 gallons per day for each site unless the Director of Utilities approves more, and require an Oklahoma Corporation Commission approved electric service instrument with at least a 10 year initial term before any certificate of occupancy. [Source 1] [Source 2] [Source 3]

I-40 and Frisco Road, west Oklahoma City (Canadian County), Oklahoma · Approved: rezoning of two parcels (about 110 and 184 acres) to data center PUDs by the Oklahoma City Council, October 27, 2026, subject to the technical evaluation as amended. Community benefits agreement required before building permits; Oklahoma Corporation Commission approved electric service of at least 10 years required before occupancy.
Read the analysis