Colocation Scout / News & Analysis

Michigan regulators approve DTE's 20-year power contracts for Google's Van Buren Township data center with an 80% minimum bill

The Michigan Public Service Commission approved DTE Electric's special contracts with Google on October 1, 2026 for a data center in Van Buren Township, Wayne County. The 20-year supply agreement requires Google to pay for at least 80% of contracted demand, and a separate agreement has Google pay for up to 1,600 MW of renewable energy and 480 MW of battery storage that DTE will build and own. DTE expects service to begin in December 2027 and reach maximum load by December 2028. [Source 1]

Michigan regulators approve DTE's 20-year power contracts for Google's Van Buren Township data center with an 80% minimum bill
All news & analysisDevelopment & PowerVan Buren Township, Wayne County, MichiganApproved (MPSC approved the DTE and Google special contracts on October 1, 2026, with customer protection conditions). Service expected to begin December 2027, per DTE. No construction or energization status disclosed in the reviewed sources.

Disclosed terms

Approval
MPSC approved the special contracts on October 1, 2026 (Case No. U-22058) [1]
Term
20 years, versus 5 years under the D11 rate [1]
Minimum bill
80% of contracted electric use, versus 50% to 65% under D11 [1]
Early termination
At least 15 years of minimum monthly charges [1]
Resources Google pays for
Up to 1,600 MW of renewable energy and 480 MW of battery storage, owned by DTE (generation and storage capacity, not IT load) [1]
Timing
Service expected to begin December 2027, maximum load by December 2028, per DTE [1]

The disclosure and our analysis

Evidence dates

Evidence: Michigan Public Service Commission news release, October 1, 2026 (Case No. U-22058); DTE Energy investor presentation furnished to the SEC on September 28, 2026; Michigan Attorney General release, June 11, 2026.

What the Commission approved

On October 1, 2026, the MPSC approved two special contracts between DTE Electric and Google LLC for electric service to a data center in Van Buren Township, Wayne County. The Commission says the approval is conditioned on protections meant to keep other DTE customers from bearing the project's costs. [Source 1]

The first is a primary supply agreement covering the terms of electric service. According to the Commission, it includes: [Source 1]

A 20-year term, compared with the 5-year contracts normally required under DTE's large-load D11 rate.

A minimum billing demand of 80% of contracted electric use, compared with 50% to 65% under the general D11 rate.

An early termination payment that requires Google to pay at least 15 years of minimum monthly charges if it cancels early.

Credit and collateral requirements to cover costs if Google stops operating the data center sooner than planned.

The second is a clean capacity accelerator agreement. Under it, Google pays for DTE to develop up to 1,600 MW of renewable energy and 480 MW of battery energy storage to serve the data center. DTE will develop, own and operate those resources. Those are generation and storage capacity figures, not data center load or IT capacity. [Source 1]

According to DTE, the data center is expected to begin taking service in December 2027, with maximum load reached by December 2028. DTE contends the contracts will produce a $1.7 billion benefit to other customers over the 20-year term because Google pays fixed costs that benefit the grid. That is DTE's estimate as described by the Commission. [Source 1]

The Commission notes that its authority covers only the terms of utility service. It has no authority over whether or where a data center locates. [Source 1]

How this connects to earlier disclosures

DTE told investors on September 28, 2026 that the Google contracts covered 1 GW of data center load and were still in the MPSC approval process. DTE did not state whether that figure is peak demand, contract demand or IT load. The Commission release does not give a load figure. [Source 2] [Source 4]

In June 2026 testimony, the Michigan Attorney General recommended raising Google's minimum monthly charge from 80% to no lower than 90% of anticipated demand, and raising exit fees. The approved contract terms described by the Commission keep the minimum billing demand at 80%. [Source 1] [Source 3]

Buyer analysis

This is our analysis.

**This is a single-customer utility contract, not colocation supply.** The approval settles the power terms for a Google campus. None of the reviewed sources describes capacity offered to other buyers.

**The terms are a template for Michigan large loads.** A 20-year term, an 80% minimum bill, a 15-year termination floor and collateral are now approved terms for one hyperscale load in DTE territory. Operators and developers planning large Michigan loads should expect DTE to ask for similar commitments. Smaller colocation tenants may see those costs reflected in provider contracts.

**Timing matters for the region.** Service is expected to start in December 2027 and ramp to maximum load by December 2028, per DTE. Buyers weighing Detroit area capacity in that window should ask providers how their own utility delivery dates fit alongside the Oracle and Google ramps.

What remains unknown

The Commission release does not give the data center's contracted load in MW, the dollar value of the minimum charges, the collateral amount, the early termination payment amount or the price of service. We did not review the Commission's written order in Case No. U-22058, so any conditions beyond those summarized in the release are not covered here. The 1 GW figure comes from DTE's September 28 presentation and its power basis is not specified.

Sources

  1. Michigan Public Service Commission, news release (Case No. U-22058) · Published 2026-10-01
  2. DTE Energy, investor presentation (SEC Form 8-K Exhibit 99.1) · Published 2026-09-28
  3. Michigan Department of Attorney General · Published 2026-06-11
  4. Colocation Scout, DTE Michigan data center power article · Published 2026-09-30

Explore the market

Related reporting

Development & Power

Casa Grande, Arizona approves a permit for a 954-acre data center campus planned to run on on-site gas power, per local reports

Casa Grande's Planning and Zoning Commission approved a conditional use permit for the Grande Valley Industrial Data Center Campus on October 1, 2026, according to local reports. The 954-acre campus plans on-site natural gas generation using Bloom Energy fuel cells plus battery storage, and the developer says it will not connect to the grid. The permit caps water use at 300 acre-feet a year. No MW figure has been reported. [Source 1] [Source 2]

Casa Grande, Pinal County, Arizona (near Maricopa to Casa Grande Highway and Montgomery Road) · Approved (conditional use permit granted by the Casa Grande Planning and Zoning Commission on October 1, 2026, per local reports). Other permits and construction status not reported.
Read the analysis
Development & Power

Enerflex wins a contract to build about 450 MW of on-site gas generation for a North American data center developer

Enerflex said on October 1, 2026 that it has been contracted to design, engineer, fabricate and assemble approximately 450 MW of behind-the-meter natural gas power generation units for an unnamed North American data center developer. Deliveries are scheduled to start in 2027 and finish in 2028. [Source 1]

Not disclosed (North America) · Announced (equipment contract awarded as of October 1, 2026; deliveries scheduled to start in 2027 and finish in 2028). No site, customer or power purchase terms disclosed.
Read the analysis
Development & Power

Kline Township, Pennsylvania approves Amazon's 350-acre data center plan with a nine-page list of conditions, per local reports

Kline Township supervisors in Schuylkill County, Pennsylvania unanimously approved Amazon's proposed data center plan at a special meeting on September 30, 2026, according to local reports. The roughly 350-acre site near Route 309 and Interstate 81 would hold about 2 million square feet of data center buildings. The approval carries a nine-page list of conditions, and state approvals remain. [Source 1] [Source 2]

Kline Township, Schuylkill County, Pennsylvania · Approved (township supervisors approved the plan with conditions on September 30, 2026, per local reports). Zoning permits and state approvals remain pending. No construction, power or capacity status disclosed.
Read the analysis