Casa Grande, Arizona approves a permit for a 954-acre data center campus planned to run on on-site gas power, per local reports

Casa Grande's Planning and Zoning Commission approved a conditional use permit for the Grande Valley Industrial Data Center Campus on October 1, 2026, according to local reports. The 954-acre campus plans on-site natural gas generation using Bloom Energy fuel cells plus battery storage, and the developer says it will not connect to the grid. The permit caps water use at 300 acre-feet a year. No MW figure has been reported. [Source 1] [Source 2]

Casa Grande, Arizona approves a permit for a 954-acre data center campus planned to run on on-site gas power, per local reports
All news & analysisDevelopment & PowerCasa Grande, Pinal County, Arizona (near Maricopa to Casa Grande Highway and Montgomery Road)Approved (conditional use permit granted by the Casa Grande Planning and Zoning Commission on October 1, 2026, per local reports). Other permits and construction status not reported.

Disclosed terms

Approval
Conditional use permit approved by the Planning and Zoning Commission on October 1, 2026, per local reports [2]
Site
954 acres, per local reports [1]
Power plan
On-site natural gas fuel cells and batteries; developer says no grid connection [1]
Water cap
300 acre-feet a year (about 97 million gallons) for cooling and on-site generation [1]
Applicant
Colliers Energy on behalf of LKY Development Company, per KJZZ [3]

The disclosure and our analysis

Evidence dates

Evidence: KJZZ reports dated October 1 and October 2, 2026; Casa Grande Dispatch (PinalCentral) report dated October 2, 2026. The commission meeting was held Thursday, October 1, 2026.

What local reports say

Casa Grande's Planning and Zoning Commission approved a conditional use permit for the Grande Valley Industrial Data Center Campus at its October 1, 2026 meeting, according to KJZZ and the Casa Grande Dispatch. KJZZ reported the vote as 6 to 1. The Dispatch reported it as 5 to 1. We could not confirm the count from city records. [Source 1] [Source 2]

KJZZ reports the application came from Colliers Energy on behalf of LKY Development Company. The site covers 954 acres southwest of the Maricopa to Casa Grande Highway near Montgomery Road, about 8 miles from the city center. The Dispatch describes it as southwest and southeast of the Maricopa to Casa Grande Highway and Montgomery Road intersection. [Source 2] [Source 3]

The campus plans on-site natural gas generation and battery energy storage. A Bloom Energy representative said the project would be the company's first solid oxide fuel cell installation in Arizona. The developer says the campus will not connect to the grid, to avoid shifting costs onto other customers. [Source 1] [Source 2]

The permit limits the site to 300 acre-feet of water a year, about 97 million gallons, covering both server cooling and on-site power generation. KJZZ reports there is no cap on energy use, and the application does not disclose a cap on the number of data center buildings. [Source 1] [Source 3]

This was the first data center to go through Casa Grande's conditional use permit process. The city made data centers in industrial zones a conditional use in 2025, so they can no longer be built by right. KJZZ reports that the commission's decision is final under current rules. [Source 1] [Source 3]

Buyer analysis

This is our analysis.

**A use permit is one approval.** It is not a building permit, an air permit for on-site generation or a gas supply contract. None of the reviewed reports gives a MW figure, a phase schedule or a construction start.

**Off-grid power changes the questions.** A campus that runs on its own gas fuel cells avoids a utility interconnection queue but depends on gas supply and on-site equipment for every megawatt. Buyers evaluating capacity on a site like this should ask what the backup is if generation trips, how fuel supply is contracted, and how the power cost is passed through.

**Water caps are becoming permit terms.** A fixed acre-foot limit that covers both cooling and generation shapes what cooling designs and densities the campus can support. Buyers in the Phoenix area should ask providers whether any water limit applies to their site and how it affects future expansion.

**No tenant or operator has been named.** The reports identify the applicant and its representatives, not an end user. This is not available capacity.

What remains unknown

The reviewed reports do not disclose a MW figure or its basis, the number of buildings or phases, the end user or operator, the gas supplier, the construction schedule, air permit status or the permit's full list of conditions. Local reports differ on the vote count. We did not find the city's staff report, agenda packet or minutes for the October 1 meeting online.

Sources

  1. KJZZ · Published 2026-10-02
  2. Casa Grande Dispatch (PinalCentral) · Published 2026-10-02
  3. KJZZ · Published 2026-10-01

Explore the market

Related reporting

Development & Power

Entergy Arkansas plans a second phase of service for Google's West Memphis data center campus, with about $600 million of grid work and a 440 MW solar contract paid for by Google

Entergy Arkansas announced on October 19, 2026 a second phase of electric service for Google's data center campus in West Memphis, Arkansas. The utility says the phase needs about $600 million of planned investment plus a power purchase agreement, all covered by Google: two battery systems, a 440 MW (ac) solar contract, an expanded Galet substation and two new 230 kV lines to serve the expanded campus. The expansion still has to be submitted to the Arkansas Public Service Commission; Entergy targets service in 2028 if it is approved. Entergy listed the expanded Google agreement among its third quarter highlights on November 2. [Source 1] [Source 2]

West Memphis, Crittenden County, Arkansas · Announced October 19, 2026; to be submitted to the Arkansas Public Service Commission for approval. Pending approval, Entergy expects service in 2028. Not approved as of November 2, 2026.
Read the analysis
Development & Power

San Antonio now requires a City Council vote on every new data center after a 9-2 code change

San Antonio City Council voted 9-2 on October 29, 2026 to pass data center regulations proposed by District 6 Councilmember Ric Galvan. The approach requires a Specific Use Authorization, a zoning approval voted on by council, for each new data center, rather than allowing data centers by right where they meet set standards. The mayor said the change ensures council can review each data center application. The final signed ordinance was not posted in the sources we reviewed. [Source 1] [Source 2] [Source 4]

San Antonio, Bexar County, Texas (city limits) · Approved: City Council passed the data center code change 9-2 on October 29, 2026. Final signed ordinance not reviewed.
Read the analysis
Development & Power

California ISO's board approves a large load interconnection proposal with a flexible interim service, due at FERC by November 16

The California ISO Board of Governors approved a proposal on October 28, 2026 setting new procedures for connecting large loads such as data centers to its grid. A key element is a flexible interim load interconnection that would let large loads connect to the transmission system with enforceable flexibility until network upgrades are complete. The ISO says it will file the proposal with the Federal Energy Regulatory Commission by a November 16 deadline, in response to FERC's June 2026 show cause order on large loads. The rules are not in effect until FERC acts. [Source 1] [Source 2]

California ISO grid; no specific project site · Approved by the California ISO Board of Governors on October 28, 2026 for filing at FERC by November 16, 2026. Not yet accepted by FERC; no effective date in reviewed sources.
Read the analysis