Colocation Scout / News & Analysis

DTE reports 2.4 GW of data center power agreements in Michigan and 2 GW more in advanced talks

DTE Energy told investors on September 28, 2026 that it has 2.4 GW of executed data center agreements in Michigan. It lists 1.4 GW for Oracle as approved and 1 GW for Google as still in the Michigan Public Service Commission approval process. DTE also says it is in advanced discussions with additional hyperscalers for about 2 GW more and is targeting another agreement by the end of 2026. [Source 1]

DTE reports 2.4 GW of data center power agreements in Michigan and 2 GW more in advanced talks
All news & analysisDevelopment & PowerSoutheast Michigan (Saline Township and Van Buren Township)Oracle contracts: Approved (MPSC approval, per DTE as of September 28, 2026). Google contracts: Proposed (pending MPSC approval as of September 28, 2026). Further 2 GW: in discussions, no agreement disclosed

Disclosed terms

Executed agreements
2.4 GW of data center load (DTE, as of September 28, 2026; power basis not specified) [1]
Oracle
1.4 GW; contracts approved, construction started; ramp expected 2027 to 2028 [1]
Google
1 GW; contracts pending MPSC approval; full ramp expected by end of 2028 [1]
Pipeline
About 2 GW in advanced discussions; another agreement targeted by end of 2026 [1]
Google contract minimum charge
80% proposed; Attorney General seeks at least 90% [3]

The disclosure and our analysis

Evidence dates

Evidence: DTE Energy investor presentation furnished to the SEC on September 28, 2026 (dated September 28 to 29, 2026); Michigan Attorney General releases dated March 17 and June 11, 2026.

What DTE disclosed

DTE Energy furnished an investor presentation with the SEC on September 28, 2026. It says the utility has 2.4 GW of executed data center agreements. DTE describes these figures as data center load. The presentation does not say whether they are peak demand, contract demand or IT load. [Source 1]

Oracle, 1.4 GW. DTE says the contracts were approved by the MPSC and construction has started. It expects demand to ramp in the 2027 to 2028 timeframe. DTE describes a 19-year power supply agreement with minimum monthly charges and a 15-year energy storage contract that covers the capital investment. It says termination fees, credit and collateral requirements protect existing customers. DTE plans nearly $2 billion of storage investment to support the load ramp. [Source 1] The Michigan Attorney General identifies this project as the Saline Township data center and the contract counterparty as Green Chile Ventures LLC. [Source 3]

Google, 1 GW. DTE says the contracts were filed with the MPSC and are in its approval process. DTE expects demand to fully ramp by the end of 2028. It lists up to 1,600 MW of renewable generation, 480 MW of energy storage and 350 MW of demand response to support the ramp, with about 700 MW of longer-term generation to be identified in its resource plan. DTE puts the related generation and storage capital at about $5 billion through 2032 and calls that figure preliminary. The structure is a 20-year power supply agreement with minimum monthly charges and a 20-year clean capacity acceleration agreement. [Source 1] The Attorney General identifies the site as Van Buren Township and says the contracts are being reviewed as a contested case. [Source 2] [Source 3]

The pipeline behind the signed deals

DTE says it is in advanced discussions with additional hyperscalers for about 2 GW of additional load and is targeting another agreement by the end of 2026. It lists 3 to 4 GW of further opportunities with hyperscalers and other customers. It says a large load tariff is moving through the approval process. DTE notes that new load beyond the signed deals would require new generation, renewables or storage, to be settled through its integrated resource plan. [Source 1]

DTE's five-year capital plan is now $36.5 billion, up about $6 billion from its prior plan, which it attributes mainly to the Oracle project and other customer initiatives. [Source 1]

Contract protections under review

In testimony described in a June 11, 2026 release, the Attorney General recommended raising Google's minimum monthly charge from 80% to no lower than 90% of anticipated demand and raising the proposed exit fees. The Attorney General also asked for tracking of transmission and other costs of serving the data center. [Source 3] The reviewed sources do not show an MPSC order on the Google contracts. DTE's September 28 presentation still lists them as in the approval process. [Source 1]

Buyer analysis

This is our analysis. The figures describe utility load commitments for two named hyperscale campuses. They are not colocation inventory, and none of the reviewed documents says any of this capacity is available to third parties.

For buyers looking at Southeast Michigan, the more useful signal is the utility's terms. DTE's large contracts pair long power supply terms with minimum monthly charges, exit fees and collateral. The Attorney General is pushing for higher minimums. Operators planning new Michigan campuses should expect similar terms, and a pending large load tariff may set them for smaller loads too.

The 2 GW in advanced talks and 3 to 4 GW pipeline are DTE's descriptions of discussions. They are not signed load, and their timing depends on new generation that is still going through the resource plan process. Buyers should ask any Michigan provider which utility agreement backs its capacity and what ramp schedule that agreement allows.

What remains unknown

The reviewed sources do not disclose the power basis of the 1.4 GW and 1 GW figures, the specific minimum charge percentage in the Oracle contracts, exit fee amounts, the identities of the hyperscalers in advanced discussions, or where that load would be located. We did not find an MPSC order on the Google contracts in the reviewed sources, and the Commission docket was not reviewed directly.

Sources

  1. DTE Energy, investor presentation (SEC Form 8-K Exhibit 99.1) · Published 2026-09-28
  2. Michigan Department of Attorney General · Published 2026-03-17
  3. Michigan Department of Attorney General · Published 2026-06-11

Explore the market

Related reporting

Development & Power

Entergy Arkansas plans a second phase of service for Google's West Memphis data center campus, with about $600 million of grid work and a 440 MW solar contract paid for by Google

Entergy Arkansas announced on October 19, 2026 a second phase of electric service for Google's data center campus in West Memphis, Arkansas. The utility says the phase needs about $600 million of planned investment plus a power purchase agreement, all covered by Google: two battery systems, a 440 MW (ac) solar contract, an expanded Galet substation and two new 230 kV lines to serve the expanded campus. The expansion still has to be submitted to the Arkansas Public Service Commission; Entergy targets service in 2028 if it is approved. Entergy listed the expanded Google agreement among its third quarter highlights on November 2. [Source 1] [Source 2]

West Memphis, Crittenden County, Arkansas · Announced October 19, 2026; to be submitted to the Arkansas Public Service Commission for approval. Pending approval, Entergy expects service in 2028. Not approved as of November 2, 2026.
Read the analysis
Development & Power

San Antonio now requires a City Council vote on every new data center after a 9-2 code change

San Antonio City Council voted 9-2 on October 29, 2026 to pass data center regulations proposed by District 6 Councilmember Ric Galvan. The approach requires a Specific Use Authorization, a zoning approval voted on by council, for each new data center, rather than allowing data centers by right where they meet set standards. The mayor said the change ensures council can review each data center application. The final signed ordinance was not posted in the sources we reviewed. [Source 1] [Source 2] [Source 4]

San Antonio, Bexar County, Texas (city limits) · Approved: City Council passed the data center code change 9-2 on October 29, 2026. Final signed ordinance not reviewed.
Read the analysis
Development & Power

California ISO's board approves a large load interconnection proposal with a flexible interim service, due at FERC by November 16

The California ISO Board of Governors approved a proposal on October 28, 2026 setting new procedures for connecting large loads such as data centers to its grid. A key element is a flexible interim load interconnection that would let large loads connect to the transmission system with enforceable flexibility until network upgrades are complete. The ISO says it will file the proposal with the Federal Energy Regulatory Commission by a November 16 deadline, in response to FERC's June 2026 show cause order on large loads. The rules are not in effect until FERC acts. [Source 1] [Source 2]

California ISO grid; no specific project site · Approved by the California ISO Board of Governors on October 28, 2026 for filing at FERC by November 16, 2026. Not yet accepted by FERC; no effective date in reviewed sources.
Read the analysis