Colocation Scout / News & Analysis

DTE reports 2.4 GW of data center power agreements in Michigan and 2 GW more in advanced talks

DTE Energy told investors on September 28, 2026 that it has 2.4 GW of executed data center agreements in Michigan. It lists 1.4 GW for Oracle as approved and 1 GW for Google as still in the Michigan Public Service Commission approval process. DTE also says it is in advanced discussions with additional hyperscalers for about 2 GW more and is targeting another agreement by the end of 2026. [Source 1]

DTE reports 2.4 GW of data center power agreements in Michigan and 2 GW more in advanced talks
All news & analysisDevelopment & PowerSoutheast Michigan (Saline Township and Van Buren Township)Oracle contracts: Approved (MPSC approval, per DTE as of September 28, 2026). Google contracts: Proposed (pending MPSC approval as of September 28, 2026). Further 2 GW: in discussions, no agreement disclosed

Disclosed terms

Executed agreements
2.4 GW of data center load (DTE, as of September 28, 2026; power basis not specified) [1]
Oracle
1.4 GW; contracts approved, construction started; ramp expected 2027 to 2028 [1]
Google
1 GW; contracts pending MPSC approval; full ramp expected by end of 2028 [1]
Pipeline
About 2 GW in advanced discussions; another agreement targeted by end of 2026 [1]
Google contract minimum charge
80% proposed; Attorney General seeks at least 90% [3]

The disclosure and our analysis

Evidence dates

Evidence: DTE Energy investor presentation furnished to the SEC on September 28, 2026 (dated September 28 to 29, 2026); Michigan Attorney General releases dated March 17 and June 11, 2026.

What DTE disclosed

DTE Energy furnished an investor presentation with the SEC on September 28, 2026. It says the utility has 2.4 GW of executed data center agreements. DTE describes these figures as data center load. The presentation does not say whether they are peak demand, contract demand or IT load. [Source 1]

Oracle, 1.4 GW. DTE says the contracts were approved by the MPSC and construction has started. It expects demand to ramp in the 2027 to 2028 timeframe. DTE describes a 19-year power supply agreement with minimum monthly charges and a 15-year energy storage contract that covers the capital investment. It says termination fees, credit and collateral requirements protect existing customers. DTE plans nearly $2 billion of storage investment to support the load ramp. [Source 1] The Michigan Attorney General identifies this project as the Saline Township data center and the contract counterparty as Green Chile Ventures LLC. [Source 3]

Google, 1 GW. DTE says the contracts were filed with the MPSC and are in its approval process. DTE expects demand to fully ramp by the end of 2028. It lists up to 1,600 MW of renewable generation, 480 MW of energy storage and 350 MW of demand response to support the ramp, with about 700 MW of longer-term generation to be identified in its resource plan. DTE puts the related generation and storage capital at about $5 billion through 2032 and calls that figure preliminary. The structure is a 20-year power supply agreement with minimum monthly charges and a 20-year clean capacity acceleration agreement. [Source 1] The Attorney General identifies the site as Van Buren Township and says the contracts are being reviewed as a contested case. [Source 2] [Source 3]

The pipeline behind the signed deals

DTE says it is in advanced discussions with additional hyperscalers for about 2 GW of additional load and is targeting another agreement by the end of 2026. It lists 3 to 4 GW of further opportunities with hyperscalers and other customers. It says a large load tariff is moving through the approval process. DTE notes that new load beyond the signed deals would require new generation, renewables or storage, to be settled through its integrated resource plan. [Source 1]

DTE's five-year capital plan is now $36.5 billion, up about $6 billion from its prior plan, which it attributes mainly to the Oracle project and other customer initiatives. [Source 1]

Contract protections under review

In testimony described in a June 11, 2026 release, the Attorney General recommended raising Google's minimum monthly charge from 80% to no lower than 90% of anticipated demand and raising the proposed exit fees. The Attorney General also asked for tracking of transmission and other costs of serving the data center. [Source 3] The reviewed sources do not show an MPSC order on the Google contracts. DTE's September 28 presentation still lists them as in the approval process. [Source 1]

Buyer analysis

This is our analysis. The figures describe utility load commitments for two named hyperscale campuses. They are not colocation inventory, and none of the reviewed documents says any of this capacity is available to third parties.

For buyers looking at Southeast Michigan, the more useful signal is the utility's terms. DTE's large contracts pair long power supply terms with minimum monthly charges, exit fees and collateral. The Attorney General is pushing for higher minimums. Operators planning new Michigan campuses should expect similar terms, and a pending large load tariff may set them for smaller loads too.

The 2 GW in advanced talks and 3 to 4 GW pipeline are DTE's descriptions of discussions. They are not signed load, and their timing depends on new generation that is still going through the resource plan process. Buyers should ask any Michigan provider which utility agreement backs its capacity and what ramp schedule that agreement allows.

What remains unknown

The reviewed sources do not disclose the power basis of the 1.4 GW and 1 GW figures, the specific minimum charge percentage in the Oracle contracts, exit fee amounts, the identities of the hyperscalers in advanced discussions, or where that load would be located. We did not find an MPSC order on the Google contracts in the reviewed sources, and the Commission docket was not reviewed directly.

Sources

  1. DTE Energy, investor presentation (SEC Form 8-K Exhibit 99.1) · Published 2026-09-28
  2. Michigan Department of Attorney General · Published 2026-03-17
  3. Michigan Department of Attorney General · Published 2026-06-11

Explore the market

Related reporting

Development & Power

Atlas Energy commits to 283 MW of Caterpillar generators for a frontier AI lab's data center project

Atlas Energy Solutions disclosed on September 25, 2026 that a subsidiary committed to buy 283 MW of Caterpillar natural gas generation equipment for a specific power project. A cost reimbursement agreement with an unnamed leading frontier AI lab backs the purchase, and Atlas says the lab is the intended off taker. No long-term power purchase agreement has been announced. [Source 1] [Source 2]

Not disclosed · Announced (equipment purchase commitments and cost reimbursement agreements executed as of September 25, 2026; no power purchase agreement disclosed)
Read the analysis
Development & Power

DOE selects 31 grid projects for $1.9 billion and says they will add 23 GW of transmission capacity

The U.S. Department of Energy announced on September 24, 2026 that it intends to help fund 31 grid projects across 26 states under its SPARK program. DOE says the projects total $5.25 billion, with $1.9 billion in federal funds and $3.35 billion in recipient cost share, and will make over 23 GW of additional capacity available on the grid. These are selections. DOE's list says project details are subject to change pending final financial assistance agreements. [Source 1] [Source 2]

United States (projects in 26 states and Guam) · Announced (DOE selections dated September 24, 2026; awards expected October 2026 to January 2027)
Read the analysis
Development & Power

FERC rejects ComEd's cancellation of PowerHouse Hillwood's Joliet transmission agreement

The Federal Energy Regulatory Commission issued an order on September 22, 2026 rejecting Commonwealth Edison's notice of cancellation of its transmission security agreement with PowerHouse Hillwood Holding, according to FERC's docket record in ER26-3257. Utility Dive reports the agreement supports a 1.8 GW, $20 billion data center PowerHouse Hillwood is developing in Joliet, Illinois. The underlying credit support dispute is pending in the U.S. District Court for the Northern District of Illinois. [Source 1] [Source 4]

Joliet, Illinois · Proposed project; FERC order rejecting the notice of cancellation issued September 22, 2026; contract dispute pending in federal court
Read the analysis