DOE selects 31 grid projects for $1.9 billion and says they will add 23 GW of transmission capacity

The U.S. Department of Energy announced on September 24, 2026 that it intends to help fund 31 grid projects across 26 states under its SPARK program. DOE says the projects total $5.25 billion, with $1.9 billion in federal funds and $3.35 billion in recipient cost share, and will make over 23 GW of additional capacity available on the grid. These are selections. DOE's list says project details are subject to change pending final financial assistance agreements. [Source 1] [Source 2]

DOE selects 31 grid projects for $1.9 billion and says they will add 23 GW of transmission capacity
All news & analysisDevelopment & PowerUnited States (projects in 26 states and Guam)Announced (DOE selections dated September 24, 2026; awards expected October 2026 to January 2027)

Disclosed terms

Federal funding
$1.9 billion across 31 selected projects [1]
Total project value
$5.25 billion [1]
Capacity claim
Over 23 GW of additional grid capacity (DOE estimate, transmission basis) [1]
Status
Selections, not final awards [2]
Alabama Power project
$50 million federal; $183.9 million total [2]

The disclosure and our analysis

Evidence dates

Evidence: U.S. Department of Energy announcement dated September 24, 2026 and DOE's list of selected applications for DE-FOA-0003580, dated September 2026.

The U.S. Department of Energy announced on September 24, 2026 that it intends to help fund 31 grid projects across 26 states under its SPARK program. DOE says the projects total $5.25 billion, with $1.9 billion in federal funds and $3.35 billion in recipient cost share, and will make over 23 GW of additional capacity available on the grid. These are selections. DOE's list says project details are subject to change pending final financial assistance agreements. [Source 1] [Source 2]

What DOE announced

SPARK stands for Speed to Power through Accelerated Reconductoring and other Key Advanced Transmission Technology Upgrades. DOE says recipients are expected to reconductor or rebuild more than 1,500 miles of transmission lines and deploy grid enhancing technologies across nearly 21,000 miles. [Source 1]

DOE describes the result as over 23 GW of additional electricity capacity. That is DOE's estimate of added transmission capacity across the selected projects. It is not generation, data center IT load or capacity reserved for any customer. [Source 1]

DOE's program page lists expected award dates from October 2026 to January 2027. The selections list states that its project details come from application materials and may change before agreements are final. [Source 2] [Source 3]

Where the largest federal amounts go

Figures below are federal funds requested and total project value as listed in DOE's selections document. [Source 2]

Colorado Energy Office, CO to TX Western Eastern Intertie Modernization Initiative: $250 million federal, $1.21 billion total.

Oklahoma Office of Management and Enterprise Services, Three Corners Connector linking SPP in Oklahoma with WECC in Colorado: $250 million federal, $832 million total.

State of Indiana, cross regional transfer capability across the PJM and MISO seam: $174 million federal, $349 million total. The narrative cites interconnection of new large load customers.

Public Utilities Commission of Ohio, Ohio SPARK: $136 million federal, $273 million total. The narrative cites faster interconnection of new load and generation.

Tennessee Valley Authority, Rebuilding the Transmission Backbone for Energy and AI Dominance: $80 million federal, $160 million total.

Projects that name data centers or large loads

Alabama Power's Northeast Alabama Smart Grid Deployment lists $50 million in federal funds and $184 million total. Its narrative says the project will give Northeast Alabama "the power needed for large-scale data centers, industrial manufacturers, and major commercial facilities." [Source 2]

Entergy Mississippi's project, titled Unlocking Grid Capacity for the Southeast's Next Wave of Data Center & Industrial Growth, covers Arkansas, Louisiana and Mississippi. It lists $13.7 million federal and $27.4 million total. [Source 2]

Pitch Aeronautics' project with Ameren Missouri, Ameren Illinois and Farmington Electric Utility System lists $37 million federal. Its narrative says it will enable new large load and generation interconnections. [Source 2]

Buyer analysis

This is our analysis. Reconductoring and dynamic line ratings raise the capacity of existing lines faster than new transmission can be built. Where a selected project removes a local constraint, it could shorten some interconnection timelines. None of the reviewed documents allocate the added capacity to specific sites or customers.

For site selection, the useful step is to check whether a candidate site's utility appears on the selections list and whether the project touches the lines that serve that site. Ask the utility or developer whether any interconnection study assumes SPARK funded upgrades, and what happens to the schedule if the award changes or is not finalized.

Treat the 23 GW headline as a program estimate. It should not be read as new data center capacity, and it does not change any single project's power status until the utility confirms it.

What remains unknown

The reviewed documents do not assign the 23 GW estimate to individual projects, give completion dates, or name customers or sites that would use the added capacity. Awards are not final, and DOE says project details may change. Some figures in the selections list were laid out inconsistently, so we reported only those we could read clearly.

Sources

  1. U.S. Department of Energy · Published 2026-09-24
  2. U.S. Department of Energy, SPARK selections list · Published 2026-09-24
  3. U.S. Department of Energy, SPARK program page · Published 2026-09-24

Explore the market

Related reporting

Development & Power

FERC rejects ComEd's cancellation of PowerHouse Hillwood's Joliet transmission agreement

The Federal Energy Regulatory Commission issued an order on September 22, 2026 rejecting Commonwealth Edison's notice of cancellation of its transmission security agreement with PowerHouse Hillwood Holding, according to FERC's docket record in ER26-3257. Utility Dive reports the agreement supports a 1.8 GW, $20 billion data center PowerHouse Hillwood is developing in Joliet, Illinois. The underlying credit support dispute is pending in the U.S. District Court for the Northern District of Illinois. [Source 1] [Source 4]

Joliet, Illinois · Proposed project; FERC order rejecting the notice of cancellation issued September 22, 2026; contract dispute pending in federal court
Read the analysis
Development & Power

Lambda announces Mayes County data center plan; capacity and delivery timing remain undisclosed

Lambda announced September 27 that it plans a data center at MidAmerica Industrial Park in Mayes County, Oklahoma. Its release identifies Grand River Dam Authority and MidAmerica as having selected Cloverleaf Infrastructure to prepare the site. This establishes a development announcement, not completed construction or customer availability. [1]

Mayes County, Oklahoma · Announced development
Read the analysis
Development & Power

MARA posts $100 million utility deposit as Matagorda project milestones change

MARA's September 25 SEC filing reports a September 21 amendment to its Texas project acquisition. Buyer Volt Texas LLC posted a $100 million utility security deposit. Revised milestones depend on a successful state audit and the buyer's decision to proceed after an interconnection study. The potential aggregate acquisition price remains $600 million if all milestones are met. [1]

Matagorda County, Texas · Project development; audit and interconnection conditions pending
Read the analysis