Colocation Scout / News & Analysis

FERC rejects ComEd's cancellation of PowerHouse Hillwood's Joliet transmission agreement

The Federal Energy Regulatory Commission issued an order on September 22, 2026 rejecting Commonwealth Edison's notice of cancellation of its transmission security agreement with PowerHouse Hillwood Holding, according to FERC's docket record in ER26-3257. Utility Dive reports the agreement supports a 1.8 GW, $20 billion data center PowerHouse Hillwood is developing in Joliet, Illinois. The underlying credit support dispute is pending in the U.S. District Court for the Northern District of Illinois. [Source 1] [Source 4]

FERC rejects ComEd's cancellation of PowerHouse Hillwood's Joliet transmission agreement
All news & analysisDevelopment & PowerJoliet, IllinoisProposed project; FERC order rejecting the notice of cancellation issued September 22, 2026; contract dispute pending in federal court

Disclosed terms

FERC action
Order rejecting ComEd's notice of cancellation, issued September 22, 2026 [1]
Cancellation filing
Filed July 24, 2026, proposed effective July 25, 2026 [2]
Reported project size
1.8 GW (power basis not specified in reviewed sources), $20 billion [4]
Dispute forum
U.S. District Court for the Northern District of Illinois [4]

The disclosure and our analysis

Evidence dates

Evidence: FERC order in Docket ER26-3257, issued September 22, 2026, and the docket's filing record from July 24 to September 17, 2026; Utility Dive reports dated August 24 and September 23, 2026.

The Federal Energy Regulatory Commission issued an order on September 22, 2026 rejecting Commonwealth Edison's notice of cancellation of its transmission security agreement with PowerHouse Hillwood Holding, according to FERC's docket record in ER26-3257. Utility Dive reports the agreement supports a 1.8 GW, $20 billion data center PowerHouse Hillwood is developing in Joliet, Illinois. The underlying credit support dispute is pending in the U.S. District Court for the Northern District of Illinois. [Source 1] [Source 4]

What FERC decided

FERC's docket index describes the September 22 issuance as an "Order Rejecting Notice of Cancellation re Commonwealth Edison Company under ER26-3257." Chairman Swett and Commissioner See filed a joint concurrence, and Commissioners Rosner and LaCerte filed a separate concurrence. [Source 1]

Utility Dive reports that FERC declined to assert primary jurisdiction over the contract interpretation question and left it with the federal court in Illinois, where the dispute is already pending. The Swett and See statement, as quoted by Utility Dive, says the commissioners "decline to assert primary jurisdiction over the interpretation of ambiguous contract terms involving credit support." [Source 4]

We could not open the order text itself through FERC's public file service. The procedural facts above come from FERC's docket index. The reasoning and quotes are attributed to Utility Dive's report of the order.

How the dispute got here

ComEd filed a tariff filing on July 24, 2026 titled "Cancellation of Hillwood," proposed to take effect July 25, 2026. [Source 2] PowerHouse Hillwood moved to intervene on July 27 and filed a protest on August 14, with a request for confidential treatment. [Source 3] Constellation Energy Generation also moved to intervene. ComEd and PowerHouse Hillwood then exchanged answers through September 17. [Source 1]

According to Utility Dive, the fight centers on credit support. PowerHouse Hillwood contends it met the agreement's initial credit requirement with a $1 posting. Utility Dive's August report says ComEd also canceled a pending retail service agreement at the Illinois Commerce Commission. [Source 4] [Source 5]

Utility Dive quotes Commissioner LaCerte calling the $1 security an "embarrassing legal fiction." His concurrence did not change the outcome. [Source 4]

What the capacity figure means

The 1.8 GW figure comes from Utility Dive's description of the project. The sources we reviewed do not say whether it is utility service capacity, total campus power or critical IT load. It should not be read as IT load, energized capacity or available space. [Source 4]

The reviewed sources do not disclose a tenant, delivery schedule, phasing, or the amount of credit support the agreement ultimately requires.

Buyer analysis

This is our analysis, not a finding in the order. The case shows that a signed transmission agreement can still be contested by the utility on credit terms. FERC's rejection keeps ComEd's cancellation filing from taking effect at FERC, but the contract question now moves to court. That leaves the project's power path unresolved for now.

For tenants and buyers evaluating capacity that depends on a new large load interconnection, the practical questions are about the developer's contracts with the utility. Ask whether the transmission and retail service agreements are in effect, what credit support has been posted and when more is due, and whether any agreement is in dispute before FERC, a state commission or a court.

Utility Dive reports that FERC tied the case to its pending large load interconnection show cause proceedings, with grid operator responses due by mid November 2026. Standard credit terms from that process could reduce this kind of dispute in the future. [Source 4]

What remains unknown

We could not open the order text, so FERC's reasoning is attributed to Utility Dive. The reviewed sources do not disclose the power basis of the 1.8 GW figure, a tenant, a delivery schedule, the required credit amounts or a court schedule. The protest was filed with a confidential treatment request.

Sources

  1. FERC, order in Docket ER26-3257 · Published 2026-09-22
  2. FERC eLibrary, ComEd cancellation filing · Published 2026-07-24
  3. FERC eLibrary, PowerHouse Hillwood protest · Published 2026-08-14
  4. Utility Dive · Published 2026-09-23
  5. Utility Dive · Published 2026-08-24

Explore the market

Related reporting

Development & Power

DOE selects 31 grid projects for $1.9 billion and says they will add 23 GW of transmission capacity

The U.S. Department of Energy announced on September 24, 2026 that it intends to help fund 31 grid projects across 26 states under its SPARK program. DOE says the projects total $5.25 billion, with $1.9 billion in federal funds and $3.35 billion in recipient cost share, and will make over 23 GW of additional capacity available on the grid. These are selections. DOE's list says project details are subject to change pending final financial assistance agreements. [Source 1] [Source 2]

United States (projects in 26 states and Guam) · Announced (DOE selections dated September 24, 2026; awards expected October 2026 to January 2027)
Read the analysis
Development & Power

Lambda announces Mayes County data center plan; capacity and delivery timing remain undisclosed

Lambda announced September 27 that it plans a data center at MidAmerica Industrial Park in Mayes County, Oklahoma. Its release identifies Grand River Dam Authority and MidAmerica as having selected Cloverleaf Infrastructure to prepare the site. This establishes a development announcement, not completed construction or customer availability. [1]

Mayes County, Oklahoma · Announced development
Read the analysis
Development & Power

MARA posts $100 million utility deposit as Matagorda project milestones change

MARA's September 25 SEC filing reports a September 21 amendment to its Texas project acquisition. Buyer Volt Texas LLC posted a $100 million utility security deposit. Revised milestones depend on a successful state audit and the buyer's decision to proceed after an interconnection study. The potential aggregate acquisition price remains $600 million if all milestones are met. [1]

Matagorda County, Texas · Project development; audit and interconnection conditions pending
Read the analysis