The quarter closes on 30 September. These figures were generated on 29 September 2026 from the public files already collected. They will be checked again after 7 October, and any change will be listed under revisions at the foot of this page. Declared values and megawatts are never added together across filings.
What the Q3 records show
- Five jurisdictions around New York City moved on data center moratoria. Brookhaven's Town Board adopted one unanimously on 13 August, according to its draft minutes. Orangetown adopted a town-wide moratorium on data centers and battery storage on 25 August. Newark's council adopted a resolution supporting a 12-month moratorium on 9 September, while the ordinance itself was returned to the administration. Islip held a public hearing on its moratorium law on 11 August, and Trumbull on a two-year moratorium on 9 September. The records for those two do not show the outcome.
- DataBank's Orangeburg expansion went into full environmental review, smaller. On 22 July the Orangetown Planning Board issued a positive declaration for DataBank Phase II at 2000 Corporate Drive, which means an environmental impact statement is required. The notice describes a 77,862 square foot data center, down from 146,480, with a 22,571 square foot standby power equipment yard, down from 52,095. The public scoping session was held on 9 September.
- Manhattan's carrier hotels replaced plant rather than adding floors. On 31 August the city issued a $314,200 permit at 325 Hudson Street for two 30-ton energy recovery chillers. On 13 August it issued a $2,550,000 permit at 32 Avenue of the Americas to replace five fluid coolers. On 16 September a job to replace the fuel oil fill piping at 60 Hudson Street was filed. None of these filings names the tenant it serves.
In New Jersey the state lists pending air permit changes, as of 29 September, for CoreSite NY2/NY3 at 2 Emerson Lane and Equinix at 755 Secaucus Road in Secaucus, CyrusOne at 800 Cottontail Lane in Franklin Township and PNJ1 at 101 Possumtown Road in Piscataway. A pending application has no decision date, so none of the four is in the air permit table. The largest new-source air permit in the New Jersey record since 2024 is CoreWeave's at 2000 Galloping Hill Road in Kenilworth, approved on 23 October 2025.
Coverage and cutoff
This report reads the public files that are live around New York City today. It is not a full tri-state report. A place with no file below is missing from this edition, not quiet.
- New York City building filings: all five boroughs, from the Department of Buildings job filings. A filing is included when its description says data center, or when it is at one of eight buildings already known to house data centers and describes the plant a data center runs on: chillers, coolers, fuel oil, generators or electrical equipment. Office, cafe, facade and scaffold work at those buildings is left out, because they are mostly offices.
- New Jersey construction permits: the state's construction permit reports, kept only on tax parcels that hold a known data center. These reports give no description of the work, so a permit here proves work on the parcel, not data center work. The newest permit in the state file was issued on 26 June 2026, so New Jersey building permits have no Q3 rows yet. That is a reporting lag, not a quiet quarter.
- Council, town board and planning records: Newark council legislation; Brookhaven and Islip town board agendas and minutes; Orangetown planning board and local law records; Trumbull and Wallingford agendas and minutes. These are legislation and review records, not permits, and the date shown is the meeting or posting date.
- State environmental notices: New York's Environmental Notice Bulletin, read for the New York counties around the city.
- New Jersey air permits: decisions by the state Department of Environmental Protection at facilities the state names as a data center or a data center operator.
- Not covered: municipal permit systems in New Jersey towns; building permits outside New York City and New Jersey's state reports; Westchester, Nassau and Orange County towns, where no data center record since 2024 was found; and Stamford, whose public site refuses automated access.
- Collection cutoff: 29 September 2026.
Six quarters of tri-state data center filings
Pieces of work are counted by the quarter they were filed or first posted in. The New Jersey state permits carry an issue date but no filing date, so they appear in the issued column only. Several of these sources were added this quarter and read back to 2024, so the rows are not a trend line.
| Quarter | Pieces of work filed | Of which new capacity or buildings | Permit records filed | Permits issued | State air permit documents |
|---|---|---|---|---|---|
| Q3 2026 (provisional) | 16 | 5 | 22 | 4 | 0 |
| Q2 2026 | 7 | 3 | 7 | 18 | 0 |
| Q1 2026 | 6 | 4 | 7 | 20 | 2 |
| Q4 2025 | 5 | 0 | 6 | 22 | 1 |
| Q3 2025 | 7 | 2 | 9 | 14 | 2 |
| Q2 2025 | 1 | 1 | 1 | 15 | 0 |
A piece of work is one job, however many records the city opens for it: New York City opens one filing per trade (plumbing, sprinkler, mechanical) for a job, and those count as one job when they share a headline. New Jersey state permits carry no description, so each is one item on its parcel. Council, town board, planning and state notice items are legislation and review records, not permits, dated by their meeting or posting. New capacity or buildings means a new building, a data hall fit-out, power work or a planning case. Fire systems, signs, trailers and plan revisions are counted in the first column only. 254 tri-state records held, 165 of them without a filing date. Generated 30 September 2026.
Every piece of work filed in Q3 2026
One row per job or legislative item, however many records sit behind it. Declared value is the figure the filer gave the city. It is not a price for space, and the rows are never added together.
| Filed | Where | The work | Type | Declared value | Public records |
|---|---|---|---|---|---|
| 14 July 2026 | Town of Islip, NY: no site address in the record | Authorization for the Town Clerk to advertise for a public hearing to consider enacting a... | Legislation and moratoria | Not stated | 1720 |
| 16 July 2026 | Town of Brookhaven, NY: no site address in the record | Introductory Local Law Number 11 of 2026 to Add Chapter 17 of the Town Code of the Town o... | Legislation and moratoria | Not stated | event-4070, event-4072 |
| 22 July 2026 | New York State environmental notice: 2000 Corporate Dr in the Town of Orangetown, New York | The Town of Orangetown Planning Board, as lead agency, has made the Draft Scope for the p... | Planning case | Not stated | 2026-07-22/seqr/town-of-orangetown-databank-phase-ii, 2026-09-02/seqr/town-of-orangetown-databank-orangeburg-phase-two |
| 24 July 2026 | Town of Orangetown, NY: no site address in the record | Establishing a Temporary Moratorium on Data Centers and Battery Energy Storage Systems | Legislation and moratoria | Not stated | post-47078 |
| 11 August 2026 | Town of Islip, NY: no site address in the record | To consider adopting Local Law No. 5 of 2026, Islip Town Code Chapter 68-761, entitled "M... | Legislation and moratoria | Not stated | 1736 |
| 12 August 2026 | Town of Orangetown, NY: no site address in the record | 73.15-1-19 Databank Orangeburg Phase 2 – Applicant Draft EIS Scoping Document 2026-07-24;... | Planning case | Not stated | august-12-2026-project-review-committee|73.15-1-19, august-26-2026-planning-board|73.15-1-19, september-9-2026-planning-board|73.15-1-19 |
| 26 August 2026 Issued 31 August 2026 | New York City: 325 HUDSON STREET, Manhattan, NY 10013 | Filing herewith for two 30-ton energy recovery chillers and repurpose 170-ton Dry Cooler | Mechanical and cooling | $314,200 | M01436429-I1 |
| 27 August 2026 | Town of Orangetown, NY: no site address in the record | Databank’s Positive Declaration Documents | Planning case | Not stated | post-47466 |
| 28 August 2026 | Town of Orangetown, NY: no site address in the record | LOCAL LAW 5, 2026- TEMPORARY TOWN-WIDE MORATORIUM – BATTERY ENERGY STORAGE SYSTEMS AND DA... | Legislation and moratoria | Not stated | post-47473 |
| 31 August 2026 | Town of Trumbull, CT: no site address in the record | RESOLUTION TC31-65: To consider and act upon a resolution which would amend the Trumbull... | Legislation and moratoria | Not stated | Agenda/_08312026-6198, Agenda/_09092026-6197 |
| 31 August 2026 | Town of Trumbull, CT: no site address in the record | Isaac, seconded by Mallozzi BE IT RESOLVED AND ORDAINED That the Trumbull Municipal Code... | Legislation and moratoria | Not stated | Minutes/_08312026-6198 |
| 1 September 2026 | Town of Wallingford, CT: no site address in the record | We need to update the ordinance before any data centers are built. | Legislation and moratoria | Not stated | 12153 |
| 2 September 2026 | Newark: no site address in the record | Data Centers Moratorium: AN ORDINANCE AMENDING TITLE 41, ZONING AND LAND USE REGULATIONS,... | Legislation and moratoria | Not stated | 26-1273 |
| 3 September 2026 Issued 9 September 2026 | Newark: no site address in the record | Resolution of Support for a temporary moratorium of twelve (12) months on the development... | Legislation and moratoria | Not stated | 26-1288 |
| 16 September 2026 | New York City: 60 HUDSON STREET, Manhattan, NY 10013 | Replacement Of The Fuel Oil Fill Spill Containers, Fuel Oil Fill Piping And Vent Piping.... | Electrical and power | $100,000 | M01428117-I1, M01428117-S1 |
| 23 September 2026 | Town of Orangetown, NY: no site address in the record | 2026-09-22_DEIS Scoping Document_Data Center Phase 2 | Planning case | Not stated | september-23-2026-planning-board|2026-09-22_DEIS Scoping Document_Data Center Phase 2 |
Permits issued in Q3 2026
Approvals dated in the quarter, whenever they were applied for.
| Issued | Applied for | The permit | Type | Declared value |
|---|---|---|---|---|
| 12 August 2026 | 9 July 2025 | Structural work as shown on plans filed herewith. Steel framing support of new mechanical... | Electrical and power | $175,000 |
| 13 August 2026 | 22 April 2026 | Modification to existing Mechanical systems as per plans filed herewith; Replacement of f... | Mechanical and cooling | $2.5 million |
| 31 August 2026 | 26 August 2026 | Filing herewith for two 30-ton energy recovery chillers and repurpose 170-ton Dry Cooler | Mechanical and cooling | $314,200 |
| 9 September 2026 | 3 September 2026 | Resolution of Support for a temporary moratorium of twelve (12) months on the development... | Legislation and moratoria | Not stated |
New Jersey air permits for data centers
A data center needs a state air permit to run its backup generators, so this record often shows work before a building permit does. Each row is one decision by the state, since January 2024.
| Date | Facility, as the state names it | What happened | Permit |
|---|---|---|---|
| 26 March 2026 | Equinix | Approved | PCP240002 |
| 27 February 2026 | Equinix Llc | Approved | PCP240002 |
| 23 October 2025 | Coreweave | Approved | PCP250001 |
| 12 September 2025 | 205 Minnisink Road Data Center | Approved | Not stated |
| 24 July 2025 | Cologix Nnj3 | Approved | PCP240001 |
| 4 March 2025 | Cyrus-One Nj Llc | Approved | Not stated |
| 6 February 2025 | Bloomberg Piscataway Data Ctr | Approved | Not stated |
| 7 November 2024 | QTS Investments Properties Princeton Llc | Approved | PCP240001 |
| 19 October 2024 | Centersquare Ewr3 | Approved | Not stated |
| 10 September 2024 | Centersquare Ewr2 Campus | Renewed | PCP240004 |
| 4 September 2024 | 201 Main Ave Data Center | Approved | Not stated |
| 3 September 2024 | Centersquare Ewr2 Campus | Approved | Not stated |
| 13 June 2024 | Equinix | Approved | PCP230002 |
| 6 June 2024 | PNJ1 | Approved | Not stated |
| 10 January 2024 | Equinix Llc | Approved | PCP230001 |
| 9 January 2024 | Iron Mountain | Renewed | PCP230001 |
New Jersey Department of Environmental Protection air permit activities at facilities the state names as a data center or a data center operator. None fall in Q3 2026. A generator permit rating is backup plant, not the capacity a customer can use, so no rating is shown as megawatts of space. Each link opens the state's own record of the permit activity. Pending applications carry no decision date and are not in this table.
Buildings certified as finished
None of these jurisdictions has recorded a certificate of occupancy at an address that carries a data center permit. A certificate marks a building or tenant space being finished, never capacity being available.
New York's statewide pause
On 14 July 2026 New York issued Executive Order 62. It pauses discretionary state environmental permits for data centers able to draw 50 MW or more, until the state finishes a generic environmental impact statement. Applications the state had already deemed complete are not caught by it. This comes from the order, not from the permit records above, and it is summarised by Davis Wright Tremaine and DLA Piper. The records above cannot show whether it changed what was filed.
What it means for a buyer
- Plant replacement is not new capacity. New chillers, coolers and fuel systems in a carrier hotel keep existing floors running. They do not show that space is coming free.
- A permit is not available space. It records that work was filed or issued. Whether any capacity is uncommitted is a question only the operator can answer.
- An air permit comes before generators run. A pending modification in Secaucus or Franklin Township shows an operator changing its backup plant. An environmental review like Orangeburg's comes before any building permit. It does not say how much IT load a customer could sign for.
- Moratoria change what can be built next, not what already runs. The moratoria above stop new data center approvals in those towns for a period. They do not close buildings already operating there.
What to watch next
- The outcomes in Islip and Trumbull. Both held public hearings on data center moratoria this quarter, and neither record yet shows a vote.
- DataBank Orangeburg Phase II's draft environmental impact statement, the next step after the 9 September scoping session.
- Whether Newark brings the moratorium ordinance back after the council's 9 September resolution of support.
- State decisions on the four pending New Jersey air permit changes, and New Jersey's state permit reports for July to September, which towns file in arrears.
- Wallingford. Its Ordinance Committee said on 1 September that the town needs to update its ordinance before any data centers are built.
Sources and revisions
Every row links to the public record it came from: the city's job filing, the state's permit record, the town's agenda, minutes or notice, the state's environmental notice, or the state's air permit record. Brookhaven's 13 August vote is taken from the town's draft minutes and will be re-checked against the approved minutes. Counts are generated from those records. When this edition is finalised its figures are frozen: a later correction is added below with its date and reason, and the original figure stays visible.
Colocation Scout is run by a colocation sourcing consultant; the permit data is public and every row links to its filing. How we publish these reports.
Revisions: none yet. Edition status: provisional.