Rockingham, North Carolina rezones 165 acres for a four-building Terra Nexus data center campus

Rockingham City Council approved a conditional rezoning of about 165.07 acres at 316 Old Cheraw Highway for a data center campus, according to the Richmond County Daily Journal. The paper reported a 4 to 1 vote, with Councilwoman Holly Howe opposed. The applicant is Terra Nexus Land Fund I, LLC. [Source 1] [Source 3]

Rockingham, North Carolina rezones 165 acres for a four-building Terra Nexus data center campus
All news & analysisDevelopment & PowerRockingham, Richmond County, North CarolinaConditional rezoning approved

Disclosed terms

Rezoned area
About 165.07 acres, R-7 to I-1 CZ [1]
Buildings
Four one-story buildings of about 155,875 sq ft each [2]
Stated investment
$1.2 billion at completion [1]

The disclosure and our analysis

Evidence dates

Evidence: City of Rockingham agenda packet for the September 8, 2026 council meeting, a March 2026 operational noise study posted by the city, and local reports dated September 13 and 17, 2026.

Rockingham City Council approved a conditional rezoning of about 165.07 acres at 316 Old Cheraw Highway for a data center campus, according to the Richmond County Daily Journal. The paper reported a 4 to 1 vote, with Councilwoman Holly Howe opposed. The applicant is Terra Nexus Land Fund I, LLC. [Source 1] [Source 3]

What was approved

The city's September 8 agenda scheduled a public hearing on rezoning the site from High Density Residential (R-7) to Conditional Light Industrial (I-1 CZ). The Planning Board recommended approval unanimously on August 4, 2026. [Source 1]

Status: Approved, for a conditional rezoning only. Under the conditions, the site's use is limited to a data center that conforms to the submitted site plan. The conditions run with the land. They do not establish a building permit, utility service agreement or construction start. [Source 1]

What the city record describes

The staff report calls the project a $1.2 billion investment at completion, with no city financial incentives. It says the project will be phased, with the first building completed in 9 to 12 months before the next phase begins. That timing is the developer's plan as reported by staff, not a construction milestone. [Source 1]

The applicant's noise study describes four one-story buildings of about 155,875 square feet each and an on-site substation area of about 16 acres. It lists 48 rooftop chillers and 48 diesel backup generators per building. [Source 2]

On power, the staff report says two Duke Energy transmission lines cross the site, which it calls critical to supplying the data center. It also says no on-site or bridge power will be used, so no air quality permit is required. [Source 1]

The cooling design changed to a closed-loop system during review. Staff says average daily water use will be generally limited to domestic use for about 30 employees, down from an original estimate of 75,000 gallons per day. [Source 1]

Capacity and material unknowns

Local reports describe the campus at 460 MW of total capacity. The city documents we reviewed do not state a megawatt figure. The reports do not specify whether 460 MW is utility service, critical IT load or another basis. Treat it as an unverified campus figure, not IT load. [Source 3] [Source 4]

The reviewed sources do not name an end user or operator, disclose a Duke Energy service agreement or energization date, or state the remaining permits required. The September 8 minutes were not yet posted when we checked on September 22.

Buyer analysis

This is an early-stage entitlement in Richmond County, outside the major North Carolina data center markets. The notable detail is the power plan: grid service from existing transmission crossing the site, with no on-site generation. That makes Duke Energy's service timeline the key question for anyone tracking when capacity could actually exist.

The conditions also show what communities now ask for. They limit generator testing to weekday business hours, cap noise at 55 dBA at residential property lines with an annual noise study, widen vegetative buffers and require closed-loop cooling. Operators planning similar sites should expect comparable terms. [Source 1]

What remains unknown

City documents reviewed do not state a megawatt figure; the 460 MW in local reports has no stated basis. No end user, Duke Energy service agreement, energization date or remaining permit list is disclosed.

Sources

  1. City of Rockingham council agenda packet · Published 2026-09-08
  2. Operational noise study posted by the City of Rockingham · Published 2026-03-01
  3. Richmond County Daily Journal · Published 2026-09-13
  4. Star 102.5 · Published 2026-09-17

Related reporting

Development & Power

Soluna reports conditional ERCOT Base Load status for 266 MW across two Texas wind campuses

Soluna Holdings says ERCOT has conditionally classified its 100 MW Project Dorothy campus in Briscoe County, Texas as Base Load in Batch Zero. A week earlier it reported the same conditional classification for the full 166 MW Project Kati campus in Willacy County, Texas. The company totals the two at 266 MW. [Source 1] [Source 2]

Briscoe County and Willacy County, Texas · Conditional ERCOT Base Load classification
Read the analysis