Colocation Scout / News & Analysis

Texas adopts large load grid rules with a $100,000 study fee and $50,000 per MW in security

The Public Utility Commission of Texas has adopted new rule 16 TAC §25.194, setting the standards large loads must meet to connect to the ERCOT grid. The rule implements PURA §37.0561, enacted by Senate Bill 6. The adoption order was filed September 18, 2026. The Texas Register acknowledgment lists an October 2 issue date and an October 8, 2026 effective date. Status: Approved, as an adopted rule not yet in effect as of September 26. [Source 1] [Source 2]

Texas adopts large load grid rules with a $100,000 study fee and $50,000 per MW in security
All news & analysisDevelopment & PowerTexas (ERCOT region)Approved (rule adopted September 18, 2026; effective October 8, 2026)

Disclosed terms

Threshold
New or expanded interconnections of 75 MW or more at a single site (non-coincident peak demand) [1]
Study fee
$100,000 flat [1]
Intermediate security
$50,000 per MW of requested peak demand [1]
Agreement stage security
Greater of $50,000 per MW of contracted peak demand or allocated system upgrade costs [1]
Milestone trigger
24 months behind the phased energization schedule as a whole [1]
Effective date
October 8, 2026 [2]

The disclosure and our analysis

Evidence dates

Evidence: Public Utility Commission of Texas adoption order in Project No. 58481, filed September 18, 2026, and the Texas Register acknowledgment filed the same day.

The Public Utility Commission of Texas has adopted new rule 16 TAC §25.194, setting the standards large loads must meet to connect to the ERCOT grid. The rule implements PURA §37.0561, enacted by Senate Bill 6. The adoption order was filed September 18, 2026. The Texas Register acknowledgment lists an October 2 issue date and an October 8, 2026 effective date. Status: Approved, as an adopted rule not yet in effect as of September 26. [Source 1] [Source 2]

Who it applies to

The rule applies to a large load customer that has not energized by the effective date and seeks a new interconnection of 75 MW or more at a single site. It also covers an expansion that reaches 75 MW for the first time, an expansion of a site already above 75 MW by 75 MW or more, and co-location with a generation resource. For expansions, it applies to the added load. [Source 1]

These thresholds are measured in non-coincident peak demand requested from the utility at a single site. That is a utility service figure. It is not critical IT load.

What a project must do before it is studied

Before a request enters an ERCOT interconnection study, the customer must sign and fund an intermediate agreement with its utility. The agreement requires four sets of disclosures. [Source 1]

Site control, through a deed, a lease running at least five years past the date the load reaches its requested peak demand, or a signed option to buy or lease.

Any substantially similar request elsewhere in Texas whose approval would lead it to change, delay or withdraw this one. The rule defines a material change as a delay of a year or more, a 20% or greater change in requested demand, or a move of the interconnection point.

The development schedule, progress on site studies, and the state and local approvals still needed.

How it plans to buy power, whether it has on-site generation that can run in parallel with ERCOT, and whether it plans to register as a controllable load resource.

The customer pays a $100,000 study fee, with any unused portion returned within 60 days after the study ends. ERCOT protocols may add a separate flat fee. It also posts financial security of $50,000 per MW of requested peak demand, or of the added demand for an expansion. Both amounts are indexed to inflation every five years starting in 2032. [Source 1]

After ERCOT allocates capacity

Within 60 days after ERCOT issues a study report allocating transmission capacity, the customer must sign and fund a standard large load interconnection agreement. Security at that stage is the greater of $50,000 per MW of contracted peak demand or the system upgrade costs allocated to the customer. The customer also pays contribution in aid of construction for direct interconnection costs, which the rule says is not refundable. [Source 1]

The order says the commission removed the interconnection fee that had been proposed at this stage. It describes the remaining security as protection against stranded costs, not a fee. [Source 1]

Milestones and refunds

If a customer is 24 months behind its phased energization schedule, the utility must report the unused capacity to ERCOT within 30 days. The 24 months apply to the schedule as a whole, not to each milestone. Within 60 days the utility draws on the security for amounts owed, keeps 20% of the security tied to the unused capacity, and returns the rest. [Source 1]

For a project that energizes, the order says 20% of the security is returned at energization. The remainder comes back in 20% steps as the customer meets the minimum billing milestones in its agreement. A customer allocated 0 MW gets its security back after amounts owed are collected. [Source 1]

What the reviewed order does not settle

The order says eligibility for ERCOT's transitional Batch Zero study is governed by Planning Guide Revision Request 145, approved June 18, 2026, and not by this rule. It says the path for loads under 75 MW is outside the rule's scope. [Source 1] We reviewed the order's rule text and summary sections, not every one of its 270 pages of responses to comments. The order does not publish per project cost estimates or queue positions.

Buyer analysis

The rule's obligations fall on the large load customer, usually the developer or operator, not on a colocation tenant. But they shape which Texas capacity is real. A developer that posts $50,000 per MW has money at risk behind its request. By our arithmetic, a 200 MW request means $10 million of intermediate security, before any upgrade costs.

When a provider pitches future ERCOT capacity, ask where the site stands: intermediate agreement signed, ERCOT allocation received, or standard agreement signed. Ask for the allocated contracted peak demand, the phased energization schedule in that agreement, and how far the project sits from the 24-month trigger. A site with allocated capacity and a signed agreement is further along than one that has only filed a request. None of those steps makes capacity available for lease on its own.

What remains unknown

The reviewed order does not publish project level costs or queue positions. Batch Zero eligibility sits in PGRR 145, and loads under 75 MW are outside the rule. We reviewed the rule text and summary sections, not every response to comments.

Sources

  1. Public Utility Commission of Texas, adoption order · Published 2026-09-18
  2. Texas Register acknowledgment, PUCT filing · Published 2026-09-18

Related reporting

Development & Power

Entergy Arkansas plans a second phase of service for Google's West Memphis data center campus, with about $600 million of grid work and a 440 MW solar contract paid for by Google

Entergy Arkansas announced on October 19, 2026 a second phase of electric service for Google's data center campus in West Memphis, Arkansas. The utility says the phase needs about $600 million of planned investment plus a power purchase agreement, all covered by Google: two battery systems, a 440 MW (ac) solar contract, an expanded Galet substation and two new 230 kV lines to serve the expanded campus. The expansion still has to be submitted to the Arkansas Public Service Commission; Entergy targets service in 2028 if it is approved. Entergy listed the expanded Google agreement among its third quarter highlights on November 2. [Source 1] [Source 2]

West Memphis, Crittenden County, Arkansas · Announced October 19, 2026; to be submitted to the Arkansas Public Service Commission for approval. Pending approval, Entergy expects service in 2028. Not approved as of November 2, 2026.
Read the analysis
Development & Power

San Antonio now requires a City Council vote on every new data center after a 9-2 code change

San Antonio City Council voted 9-2 on October 29, 2026 to pass data center regulations proposed by District 6 Councilmember Ric Galvan. The approach requires a Specific Use Authorization, a zoning approval voted on by council, for each new data center, rather than allowing data centers by right where they meet set standards. The mayor said the change ensures council can review each data center application. The final signed ordinance was not posted in the sources we reviewed. [Source 1] [Source 2] [Source 4]

San Antonio, Bexar County, Texas (city limits) · Approved: City Council passed the data center code change 9-2 on October 29, 2026. Final signed ordinance not reviewed.
Read the analysis
Development & Power

California ISO's board approves a large load interconnection proposal with a flexible interim service, due at FERC by November 16

The California ISO Board of Governors approved a proposal on October 28, 2026 setting new procedures for connecting large loads such as data centers to its grid. A key element is a flexible interim load interconnection that would let large loads connect to the transmission system with enforceable flexibility until network upgrades are complete. The ISO says it will file the proposal with the Federal Energy Regulatory Commission by a November 16 deadline, in response to FERC's June 2026 show cause order on large loads. The rules are not in effect until FERC acts. [Source 1] [Source 2]

California ISO grid; no specific project site · Approved by the California ISO Board of Governors on October 28, 2026 for filing at FERC by November 16, 2026. Not yet accepted by FERC; no effective date in reviewed sources.
Read the analysis