Prince William County ends by-right approval for new data centers and rejects the Vint Hill substation

Prince William County's Board of County Supervisors voted 8 to 0 on September 22, 2026 to end by-right data center development for new projects, according to InsideNova and FOX 5 DC. Future data centers will need a special use permit and a board vote. The same day, the board unanimously rejected Dominion Energy's proposed Vint Hill substation expansion, FOX 5 reported. [Source 3] [Source 4]

Prince William County ends by-right approval for new data centers and rejects the Vint Hill substation
All news & analysisDevelopment & PowerPrince William County, VirginiaApproved September 22, 2026 per local reports; adopted text not yet posted

Disclosed terms

Board vote
8 to 0 (reported) [3]
New path for data centers outside qualifying parcels
Special use permit [2]
Planning Commission recommendation
Approval on September 9 with a 120-day window and 500-foot setback [1]
Vint Hill substation
Rejected unanimously (reported) [4]

The disclosure and our analysis

Evidence dates

Evidence: September 9 Planning Commission recommendation, ordinance text posted for the September 22 hearing, and local reports of the September 22 votes.

Prince William County's Board of County Supervisors voted 8 to 0 on September 22, 2026 to end by-right data center development for new projects, according to InsideNova and FOX 5 DC. Future data centers will need a special use permit and a board vote. The same day, the board unanimously rejected Dominion Energy's proposed Vint Hill substation expansion, FOX 5 reported. [Source 3] [Source 4]

What the amendment does

The change is zoning text amendment DPA2026-00006, which revises the Data Center Opportunity Zone Overlay District. The county's project page says it limits the overlay to parcels meeting one or more of five eligibility pathways and closes the overlay to future expansion. [Source 1]

The ordinance text posted for the hearing works this way. Parcels stay in the overlay, with by-right data center rights, only if they were already in the overlay and meet at least one test. The tests cover accepted proffers for a data center rezoning, an approved preliminary or final site plan or plat, a final zoning determination, or an application accepted for review within a set window after adoption. In each case the applicant must be pursuing the project in good faith with substantial expenses. [Source 2]

Everywhere else, data centers in office, industrial and B-1 districts now need a special use permit. They remain prohibited in agricultural, residential and several business districts. After adoption, the board will not consider adding properties to the overlay. [Source 2]

Status as of September 22, 2026: Approved, per local reports. The adopted text and final minutes were not yet posted when we checked on September 23, and the county's board staff report did not load for us. We describe the mechanism from the text posted for the hearing.

The grace period

The Planning Commission recommended approval on September 9 with a 120-day filing window and a 500-foot setback from homes and schools. [Source 1] InsideNova reports the board adopted a 90-day grace period without the buffer. It reports the 500-foot setback is on a separate track, with Planning Commission review in November and a board vote in January 2027. [Source 3] Treat the 90-day figure as reported until the adopted ordinance is posted.

Vint Hill substation

Dominion's application, SUP2025-00009, sought to expand its substation at 13405 Vint Hill Road near Nokesville on a 23.4-acre site. It would have become a 500 kV gas-insulated facility with two 30-foot buildings. The board had deferred the decision on June 23. [Source 5] [Source 6]

Dominion said projects like Vint Hill are "essential to maintaining a reliable grid," according to FOX 5. [Source 4] The reviewed sources do not say what data center load the project was meant to serve or what Dominion will do next.

Material unknowns

The reviewed sources do not say how many parcels or acres remain in the overlay, or how much planned data center capacity falls outside it. Before the vote, Supervisor Tom Gordy said no data center company had filed an application in over two years "because there's no power." That is his characterization, reported by InsideNova. [Source 5]

Buyer analysis

Prince William is one of the core Northern Virginia supply markets. This vote does not remove existing buildings or projects with qualifying approvals. It does change the path for everything else, from an administrative review to a public board decision.

For buyers, the practical effect is on future supply timing, not current inventory. Projects already approved or filed in time keep their route. New sites face a slower and less certain process. The Vint Hill rejection adds a second constraint on power delivery in the county's western area.

When a provider quotes future Prince William capacity, ask two things. Does the site qualify under the grandfathering tests, or does it still need a special use permit? And which substation and transmission projects does its power date depend on?

What remains unknown

The adopted ordinance text and minutes were not posted as of September 23. The reviewed sources do not state how many parcels or acres remain in the overlay or what load the Vint Hill substation would have served.

Sources

  1. Prince William County DPA2026-00006 project page · Published 2026-09-09
  2. Prince William County staff revised ordinance text · Published 2026-09-22
  3. InsideNova · Published 2026-09-22
  4. FOX 5 DC via Yahoo News · Published 2026-09-22
  5. InsideNova via WTOP · Published 2026-09-22
  6. Hoodline · Published 2026-09-21

Explore the market

Related reporting

Development & Power

Entergy Arkansas plans a second phase of service for Google's West Memphis data center campus, with about $600 million of grid work and a 440 MW solar contract paid for by Google

Entergy Arkansas announced on October 19, 2026 a second phase of electric service for Google's data center campus in West Memphis, Arkansas. The utility says the phase needs about $600 million of planned investment plus a power purchase agreement, all covered by Google: two battery systems, a 440 MW (ac) solar contract, an expanded Galet substation and two new 230 kV lines to serve the expanded campus. The expansion still has to be submitted to the Arkansas Public Service Commission; Entergy targets service in 2028 if it is approved. Entergy listed the expanded Google agreement among its third quarter highlights on November 2. [Source 1] [Source 2]

West Memphis, Crittenden County, Arkansas · Announced October 19, 2026; to be submitted to the Arkansas Public Service Commission for approval. Pending approval, Entergy expects service in 2028. Not approved as of November 2, 2026.
Read the analysis
Development & Power

San Antonio now requires a City Council vote on every new data center after a 9-2 code change

San Antonio City Council voted 9-2 on October 29, 2026 to pass data center regulations proposed by District 6 Councilmember Ric Galvan. The approach requires a Specific Use Authorization, a zoning approval voted on by council, for each new data center, rather than allowing data centers by right where they meet set standards. The mayor said the change ensures council can review each data center application. The final signed ordinance was not posted in the sources we reviewed. [Source 1] [Source 2] [Source 4]

San Antonio, Bexar County, Texas (city limits) · Approved: City Council passed the data center code change 9-2 on October 29, 2026. Final signed ordinance not reviewed.
Read the analysis
Development & Power

California ISO's board approves a large load interconnection proposal with a flexible interim service, due at FERC by November 16

The California ISO Board of Governors approved a proposal on October 28, 2026 setting new procedures for connecting large loads such as data centers to its grid. A key element is a flexible interim load interconnection that would let large loads connect to the transmission system with enforceable flexibility until network upgrades are complete. The ISO says it will file the proposal with the Federal Energy Regulatory Commission by a November 16 deadline, in response to FERC's June 2026 show cause order on large loads. The rules are not in effect until FERC acts. [Source 1] [Source 2]

California ISO grid; no specific project site · Approved by the California ISO Board of Governors on October 28, 2026 for filing at FERC by November 16, 2026. Not yet accepted by FERC; no effective date in reviewed sources.