Colocation Scout / News & Analysis

TVA's data center rate is now in effect; a PowerCompute filing says new or expanded load above 5 MW faces a capacity charge of about $1.5 million per MW

The Tennessee Valley Authority's separate data center rate took effect on October 1, 2026, after its Board approved it on August 20. The first company filing under it gives specifics: PowerCompute says new or expanded data center load above the first 5 MW now faces a Capacity Commitment Charge of about $1.5 million per MW, that load under contract before October 1 is exempt, and that fiscal 2027 has a 2,000 MW cohort available first come, first served. PowerCompute moved its Columbus, Mississippi site to the new rate and raised contracted demand from 8.5 MW to 11 MW before the deadline. [Source 1] [Source 2] [Source 3]

TVA's data center rate is now in effect; a PowerCompute filing says new or expanded load above 5 MW faces a capacity charge of about $1.5 million per MW
All news & analysisPricing & EconomicsTennessee Valley Authority service territory; PowerCompute site in Columbus, MississippiApproved. The TVA Board approved a separate data center rate on August 20, 2026, effective October 1, 2026 (TVA fiscal year 2027) and phased in over three fiscal years. As of October 6, 2026.

Disclosed terms

Capacity charge
About $1.5 million per MW for new or expanded data center load above the first 5 MW, per PowerCompute [2]
Exemption
Load under contract effective before October 1, 2026, per PowerCompute [2]
Fiscal 2027 cohort
2,000 MW available first come, first served, per PowerCompute [2]
Board approval
TVA Board approved the rate structure change on August 20, 2026 [3]
PowerCompute contract
Up to 11,000 kW firm power at Columbus, Mississippi under Schedule DCB, term to September 16, 2030 [1]

The disclosure and our analysis

Evidence dates

Evidence: PowerCompute Form 8-K and press release dated October 6, 2026, reporting a power contract signed September 30, 2026; TVA news release distributed August 20, 2026; TVA letter to local power companies dated February 18, 2026; Action News 5 report dated August 20, 2026.

What TVA approved

On August 20, 2026, the TVA Board approved changes to its wholesale rate structure that, in TVA's words, protect residential and manufacturing customers from subsidizing costs tied to data center load growth. TVA tied the change to its signing of the Ratepayer Protection Pledge. The same meeting approved the 2026 Integrated Resource Plan, which says the region may need 11 to 32 GW of additional generation by 2040, and a Board item on loads greater than 100 MW. TVA's release does not give rate figures. [Source 3]

TVA's February 18, 2026 letter to local power companies laid out the plan. It proposed removing data centers from the manufacturing service rate class they had been allowed into since December 2008, when TVA had excess capacity. It also proposed a new class for large customers with "pricing and capacity commitment requirements" and a "capacity commitment charge" requiring upfront customer investment to cover TVA's cost of serving certain new facilities. [Source 4]

Local reporting on the August 20 meeting quoted TVA Chief Financial Officer Tom Rice describing an average increase of about 10% for data center customers, phased in over three years, and an upfront capacity commitment charge for new data centers paid over three to five years. [Source 5]

What PowerCompute's filing adds

PowerCompute, which runs bitcoin mining and some GPU compute, is the first company we found describing the tariff in an SEC filing. Its description, which we attribute to the company: [Source 2]

TVA adopted the Large Data Service rate in August 2026 and removed data center load from the general industrial rate class. Bitcoin mining counts as data center load.

From fiscal 2027, which began October 1, 2026, a Capacity Commitment Rider charges about $1.5 million per MW for new or expanded data center load above the first 5 MW of contracted demand.

Load under a contract effective before October 1 is not subject to the charge.

For fiscal 2027 there is a 2,000 MW cohort threshold of capacity, available first come, first served.

Eligibility covers delivery points whose main use falls under NAICS subsectors 518 or 519, NAICS 522320 or 541214, or, in TVA's sole judgment, computational equipment.

The PowerCompute contract

PowerCompute's subsidiary signed a new industrial power contract with Columbus Light and Water on September 30, 2026, effective as of September 16, for up to 11,000 kW of firm power at its Columbus, Mississippi data center, up from 8.5 MW. Power is priced under the utility's Large Data Service Rate, Schedule DCB, subject to scheduled increases and TVA adjustments. The term runs to September 16, 2030, with a five-year renewal if both parties agree. PowerCompute's estimated share of the utility's capital costs is $0. [Source 1]

PowerCompute says it was not assessed a capacity charge on any of the 11 MW, and that its $300,000 deposit is being returned and replaced with a utility bond. CEO Bruce Rodgers said a company building 11 MW of new data center load in the TVA region today would face a charge of about $1.5 million per MW above the first 5 MW. That is a company claim. [Source 2]

Buyer analysis

This is our analysis.

**New capacity in the TVA region just got more expensive to power.** On PowerCompute's description, a new 50 MW load would face about $67.5 million in capacity charges on the 45 MW above the first 5 MW, paid over three to five years per local reports. That is our arithmetic on the reported rate. We did not review the rider text, which may contain exceptions, credits or caps.

**Contracted power signed before October 1 now carries a premium.** Load under contract before the deadline is exempt, according to PowerCompute. Providers with existing TVA contracts hold an advantage over new entrants. Expect that advantage to show up in pricing.

**Ask who pays on expansions.** If you take space in a TVA region facility, ask whether its capacity was contracted before October 1, whether your phase counts as expanded load, and whether any capacity charge will be passed through in your rate or as a one-time cost.

**The 2,000 MW cohort is a queue.** If the fiscal 2027 cohort fills, later projects may wait. Ask providers whether their planned phases have a place in it.

What remains unknown

The reviewed sources do not include the text of TVA's rate schedules or the Capacity Commitment Rider. TVA's release does not state the $1.5 million figure, the 5 MW threshold or the 2,000 MW cohort; those come from PowerCompute's filing and local reports. The sources do not disclose how the charge is refunded or credited, how the cohort is allocated among local power companies, or energy rates under Schedule DCB.

Sources

  1. PowerCompute, Inc., Form 8-K · Published 2026-10-06
  2. PowerCompute, Inc., press release (Form 8-K Exhibit 99.1) · Published 2026-10-06
  3. Tennessee Valley Authority, news release · Published 2026-08-20
  4. Tennessee Valley Authority, rate change letter to local power companies (copy published by WATE) · Published 2026-02-18
  5. Action News 5 · Published 2026-08-20

Related reporting

Pricing & Economics

Nscale says its Ward County, Texas AI data center is live; landlord Ionic Digital's filings show $182.5 million a year in rent for 234 MW

Nscale said on October 1, 2026 that its Ward County, Texas site, an empty steel shell nine months earlier, is now a live AI data center delivering thousands of GPUs. The landlord, Ionic Digital, discloses in SEC filings that Nscale leases the site's full 234 MW of energy capacity under a 126-month triple-net lease. After an 18-month ramp, annual fixed rent at 234 MW is $182.5 million. Nscale is obligated to lease another 89 MW at the same price per MW when it becomes available. [Source 1] [Source 5]

Ward County, Texas · Leased (234 MW of energy capacity leased to Nscale, per Ionic Digital filings through September 2026). Operating, per Nscale's October 1, 2026 statement. Expansion to 700 MW proposed; ERCOT classification provisional.
Read the analysis
Pricing & Economics

SharonAI signs a $356 million GPU-backed debt facility at 7.25% to 9.95% to fund contracted compute

SharonAI disclosed that two Australian subsidiaries signed a senior secured term loan facility of up to US$356 million on September 28, 2026. Proceeds fund GPUs, servers and related equipment at contracted data center facilities for a customer GPU compute contract. Facility A carries 7.25% rising to as much as 9.95%. Facility B carries a fixed 9.95%. [Source 1] [Source 2]

Australia (borrowers are Australian subsidiaries; deployment sites not disclosed) · Facility agreement signed September 28, 2026. Drawdown status not disclosed as of October 1, 2026.
Read the analysis
Pricing & Economics

CleanSpark closes $2.276 billion financing for Sandersville data center

CleanSpark's subsidiary CSDC Finance I LLC completed a $2.276 billion senior secured notes offering on September 25. The debt carries a 7.875% coupon, was issued at 98.5% of principal and matures October 1, 2031. The filing locates the financed facility in Sandersville, Georgia. [1]

Sandersville, Georgia · Financing closed; facility delivery not established
Read the analysis