Colocation Scout / News & Analysis

TVA's data center rate is now in effect; a PowerCompute filing says new or expanded load above 5 MW faces a capacity charge of about $1.5 million per MW

The Tennessee Valley Authority's separate data center rate took effect on October 1, 2026, after its Board approved it on August 20. The first company filing under it gives specifics: PowerCompute says new or expanded data center load above the first 5 MW now faces a Capacity Commitment Charge of about $1.5 million per MW, that load under contract before October 1 is exempt, and that fiscal 2027 has a 2,000 MW cohort available first come, first served. PowerCompute moved its Columbus, Mississippi site to the new rate and raised contracted demand from 8.5 MW to 11 MW before the deadline. [Source 1] [Source 2] [Source 3]

TVA's data center rate is now in effect; a PowerCompute filing says new or expanded load above 5 MW faces a capacity charge of about $1.5 million per MW
All news & analysisPricing & EconomicsTennessee Valley Authority service territory; PowerCompute site in Columbus, MississippiApproved. The TVA Board approved a separate data center rate on August 20, 2026, effective October 1, 2026 (TVA fiscal year 2027) and phased in over three fiscal years. As of October 6, 2026.

Disclosed terms

Capacity charge
About $1.5 million per MW for new or expanded data center load above the first 5 MW, per PowerCompute [2]
Exemption
Load under contract effective before October 1, 2026, per PowerCompute [2]
Fiscal 2027 cohort
2,000 MW available first come, first served, per PowerCompute [2]
Board approval
TVA Board approved the rate structure change on August 20, 2026 [3]
PowerCompute contract
Up to 11,000 kW firm power at Columbus, Mississippi under Schedule DCB, term to September 16, 2030 [1]

The disclosure and our analysis

Evidence dates

Evidence: PowerCompute Form 8-K and press release dated October 6, 2026, reporting a power contract signed September 30, 2026; TVA news release distributed August 20, 2026; TVA letter to local power companies dated February 18, 2026; Action News 5 report dated August 20, 2026.

What TVA approved

On August 20, 2026, the TVA Board approved changes to its wholesale rate structure that, in TVA's words, protect residential and manufacturing customers from subsidizing costs tied to data center load growth. TVA tied the change to its signing of the Ratepayer Protection Pledge. The same meeting approved the 2026 Integrated Resource Plan, which says the region may need 11 to 32 GW of additional generation by 2040, and a Board item on loads greater than 100 MW. TVA's release does not give rate figures. [Source 3]

TVA's February 18, 2026 letter to local power companies laid out the plan. It proposed removing data centers from the manufacturing service rate class they had been allowed into since December 2008, when TVA had excess capacity. It also proposed a new class for large customers with "pricing and capacity commitment requirements" and a "capacity commitment charge" requiring upfront customer investment to cover TVA's cost of serving certain new facilities. [Source 4]

Local reporting on the August 20 meeting quoted TVA Chief Financial Officer Tom Rice describing an average increase of about 10% for data center customers, phased in over three years, and an upfront capacity commitment charge for new data centers paid over three to five years. [Source 5]

What PowerCompute's filing adds

PowerCompute, which runs bitcoin mining and some GPU compute, is the first company we found describing the tariff in an SEC filing. Its description, which we attribute to the company: [Source 2]

TVA adopted the Large Data Service rate in August 2026 and removed data center load from the general industrial rate class. Bitcoin mining counts as data center load.

From fiscal 2027, which began October 1, 2026, a Capacity Commitment Rider charges about $1.5 million per MW for new or expanded data center load above the first 5 MW of contracted demand.

Load under a contract effective before October 1 is not subject to the charge.

For fiscal 2027 there is a 2,000 MW cohort threshold of capacity, available first come, first served.

Eligibility covers delivery points whose main use falls under NAICS subsectors 518 or 519, NAICS 522320 or 541214, or, in TVA's sole judgment, computational equipment.

The PowerCompute contract

PowerCompute's subsidiary signed a new industrial power contract with Columbus Light and Water on September 30, 2026, effective as of September 16, for up to 11,000 kW of firm power at its Columbus, Mississippi data center, up from 8.5 MW. Power is priced under the utility's Large Data Service Rate, Schedule DCB, subject to scheduled increases and TVA adjustments. The term runs to September 16, 2030, with a five-year renewal if both parties agree. PowerCompute's estimated share of the utility's capital costs is $0. [Source 1]

PowerCompute says it was not assessed a capacity charge on any of the 11 MW, and that its $300,000 deposit is being returned and replaced with a utility bond. CEO Bruce Rodgers said a company building 11 MW of new data center load in the TVA region today would face a charge of about $1.5 million per MW above the first 5 MW. That is a company claim. [Source 2]

Buyer analysis

This is our analysis.

**New capacity in the TVA region just got more expensive to power.** On PowerCompute's description, a new 50 MW load would face about $67.5 million in capacity charges on the 45 MW above the first 5 MW, paid over three to five years per local reports. That is our arithmetic on the reported rate. We did not review the rider text, which may contain exceptions, credits or caps.

**Contracted power signed before October 1 now carries a premium.** Load under contract before the deadline is exempt, according to PowerCompute. Providers with existing TVA contracts hold an advantage over new entrants. Expect that advantage to show up in pricing.

**Ask who pays on expansions.** If you take space in a TVA region facility, ask whether its capacity was contracted before October 1, whether your phase counts as expanded load, and whether any capacity charge will be passed through in your rate or as a one-time cost.

**The 2,000 MW cohort is a queue.** If the fiscal 2027 cohort fills, later projects may wait. Ask providers whether their planned phases have a place in it.

What remains unknown

The reviewed sources do not include the text of TVA's rate schedules or the Capacity Commitment Rider. TVA's release does not state the $1.5 million figure, the 5 MW threshold or the 2,000 MW cohort; those come from PowerCompute's filing and local reports. The sources do not disclose how the charge is refunded or credited, how the cohort is allocated among local power companies, or energy rates under Schedule DCB.

Sources

  1. PowerCompute, Inc., Form 8-K · Published 2026-10-06
  2. PowerCompute, Inc., press release (Form 8-K Exhibit 99.1) · Published 2026-10-06
  3. Tennessee Valley Authority, news release · Published 2026-08-20
  4. Tennessee Valley Authority, rate change letter to local power companies (copy published by WATE) · Published 2026-02-18
  5. Action News 5 · Published 2026-08-20

Related reporting

Pricing & Economics

Columbiana, Alabama data center rent: Cerebras to pay Digi Power X $195 per kW a month for 15 MW

Cerebras Systems will pay Digi Power X a fixed, take-or-pay colocation fee of $195 per kW per month, escalating 3% a year, for the purpose-built Tier III data center in Columbiana, Alabama, according to Digi Power X's Form 10-Q for the quarter ended September 30, 2026, filed with the SEC on November 13, 2026. The 10-Q puts that at about $2.925 million a month for Phase 1, which is 15 MW of IT load. The company's November 13 results release says Phase 1 fees should average about $40 million a year over the ten-year term, about $402 million in total, with tenant access expected December 15, 2026 and billing from January 2027. The other 25 MW, Phase 2, is conditioned on the company securing adequate financing. [Source 1] [Source 2]

Columbiana, Shelby County, Alabama · Under construction (Phase 1) and leased to Cerebras, with the lease not yet commenced, as of September 30, 2026 per the 10-Q. Phase 2 (25 MW) is conditional on financing. Not available to other buyers.
Read the analysis
Pricing & Economics

Tampa Electric data center tariff: $18.98 per kW generation charge and $2M per MW security in proposed LLCS-1

Tampa Electric's proposed large load tariff for Florida data centers of 50 MW or more would bill an $18.98 per kW Incremental Generation Charge, a $4.78 per kW demand charge and other per kW charges against contracted demand, under a contract of at least 20 years. Customers without an investment grade credit rating would post security of $2.0 million per MW of contracted capacity. The company filed the tariff with the Florida Public Service Commission on September 30, 2026 in Docket No. 20260146-EI. On November 3, 2026 the Commission suspended it pending review and set a hearing for March 30 to April 2, 2027. [Source 1] [Source 3] [Source 4]

Tampa Electric service territory: Hillsborough County and parts of Polk, Pinellas and Pasco counties, Florida · Proposed: filed September 30, 2026; suspended by the Florida PSC on November 3, 2026 pending review; hearing set for March 30 to April 2, 2027. No rate is approved.
Read the analysis
Pricing & Economics

Spartanburg County data center agreements: $9M and $12.6M community payments for 65 and 50 IT MW projects

Spartanburg County, South Carolina put three data center development agreements to second reading at a special called council meeting on November 3, 2026. The draft agreements in the county's meeting packet commit 300 Jones Road Associates LLC to $9 million in community benefit payments over six installments for a data center of up to 65 IT MW at 430 Jones Road, and AIB CLT1 LLC to at least $12.6 million over a 12-year initial term for a 50 IT MW data center at 389 Tyger River Industrial Drive. A third draft, for Numara LLC and Valara Holdings LLC at 4000 S Pine Street, describes a 457 MW project with at least $2.76 billion of investment and lists no community benefit payment. [Source 1]

Spartanburg County, South Carolina (430 Jones Road; 389 Tyger River Industrial Drive, Moore; 4000 S Pine Street, Spartanburg) · Proposed: second reading and public hearings on the November 3, 2026 Spartanburg County Council agenda; final reading pending as of that packet. No construction, energization or availability is established for the new buildings.
Read the analysis