Colocation Scout / News & Analysis

Hallador sells six years of Indiana power from its Merom plant to a MISO Zone 6 utility at what it calls its highest capacity price yet

Hallador Energy said on October 8, 2026 that its subsidiary Hallador Power Company signed six-year capacity and energy agreements on October 7 with an unnamed, investment-grade MISO Zone 6 utility. The deals cover deliveries from the Merom Generating Station in Sullivan County, Indiana from June 1, 2029 through May 31, 2035. The utility will buy an annual average of 225 MW of Merom's accredited capacity for about $271 million, and an annual average base energy quantity of 200 MW that Hallador estimates at about $422 million of revenue. Hallador says the capacity price is the highest it has contracted and more than 20% above its March 2026 capacity contract. The agreements took effect on signing and need no regulatory approval. [Source 1] [Source 2]

Hallador sells six years of Indiana power from its Merom plant to a MISO Zone 6 utility at what it calls its highest capacity price yet
All news & analysisPricing & EconomicsMerom Generating Station, Sullivan County, IndianaSigned. Capacity and energy agreements executed October 7, 2026 and effective on signing, with no regulatory approval required according to Hallador. Deliveries scheduled June 1, 2029 through May 31, 2035. As of October 8, 2026.

Disclosed terms

Capacity sale
Annual average of 225 MW of Merom accredited capacity, about $271 million over the term [1]
Energy sale
Annual average base quantity of 200 MW, unit contingent; about $422 million estimated revenue [1]
Term
June 1, 2029 through May 31, 2035 [1]
Counterparty
Unnamed investment-grade MISO Zone 6 utility [1]
Price claim
Highest capacity price Hallador has contracted; more than 20% above its March 2026 contract [1]
Approvals
Effective on signing; no regulatory approval required [1]

The disclosure and our analysis

Evidence dates

Evidence: Hallador Energy Company press release furnished with a Form 8-K, dated October 8, 2026, describing agreements executed October 7, 2026. Forward sales figures are as of September 30, 2026 and include the October 7 contract. The plant's county comes from a Hoosier Energy release dated February 15, 2022.

What Hallador disclosed

**Counterparty and term:** Hallador Power Company, a wholly owned subsidiary of Hallador Energy (Nasdaq: HNRG), signed six-year capacity and energy agreements with an investment-grade MISO Zone 6 utility. The release does not name the utility. Deliveries come from the Merom Generating Station and run from June 1, 2029 through May 31, 2035. [Source 1]

**Capacity:** The utility will buy an annual average of 225 MW of Merom's accredited capacity, for about $271 million of capacity revenue over the term. Hallador says this is its third capacity agreement announced in 2026, the highest capacity price it has contracted to date, and more than 20% above the capacity contract it announced in March. [Source 1]

**Energy:** The energy agreement has an annual average base energy quantity of 200 MW, subject to seasonal reduction rights. The utility can reduce the base quantity to zero for up to 90 days a year. Hallador estimates about $422 million of energy revenue over the term at current forward prices. It estimates energy quantities of 0.9 million MWh for 2029, 1.4 million MWh for 2030 and 6.1 million MWh for 2031 to 2035. Hallador labels these figures as estimates that could vary materially. [Source 1]

**Risk allocation:** The energy sale is unit contingent. Deliveries follow the actual output of Merom's two units, and Hallador has no obligation to buy replacement power when a unit is offline or in required maintenance. Energy pricing includes a fuel price floor and recovery of qualifying excess fuel costs. Hallador notes that unit contingent sales price lower than firm sales because they carry no replacement power risk. [Source 1]

**Approvals:** Hallador says the agreements are effective on signing and require no regulatory approval. Separately, it says certain other contracted positions in its forward book are subject to Indiana Utility Regulatory Commission approval. [Source 1]

The forward price curve

Hallador published its total contracted position by year, as of September 30, 2026 and including this contract. These are portfolio averages across all of its executed contracts, not the price of this deal alone. [Source 1]

**Average contracted accredited capacity price:** $244 per MW-day for 2026, $262 for 2027, $324 for 2028, $478 for 2029, $502 for 2030, $499 for 2031 to 2035 and $480 for 2036 to 2040.

**Combined capacity and energy revenue per MWh:** $46.07 for 2026, rising to $73.26 for 2030 and $75.35 for 2031 to 2035. Hallador computes this by spreading capacity revenue over an assumed 5.2 million MWh of annual generation and adding the average contracted energy price.

**Average contracted energy price:** $42.93 per MWh for 2026, $47.73 for 2030 and $50.91 for 2031 to 2035.

**Coverage:** About 95% of Merom's accredited capacity is under contract through 2035, and about two thirds for 2036 to 2040. The total forward sales book is about $3 billion at the segment level.

The release headline describes the sale as priced at more than $80 per MWh. On our arithmetic, the company's $271 million capacity figure plus its $422 million energy estimate, divided by its 8.4 million MWh energy estimate, comes to about $82 per MWh, which is consistent with that claim. The same arithmetic puts the capacity component at roughly $550 per MW-day, based on the 225 MW annual average. Both are our calculations from averages, not disclosed contract prices.

Turtle Creek and data center demand

Hallador says it submitted an air permit application on September 25 for its 460 MW Turtle Creek natural gas project at Merom, which it says would expand its generating capacity by more than 40% once approved. Turtle Creek still needs an interconnection agreement and a final investment decision, according to the release's risk factors. [Source 1]

The release ties demand to data centers only in general terms. CEO Brent Bilsland is quoted saying that as data center projects shift or are delayed in other states, investment is flowing into Indiana. No data center customer is named or party to these agreements. [Source 1]

Buyer analysis

This is our analysis.

**This is a wholesale power deal, not data center capacity.** No megawatt here is a data center load, IT load or leasable space. The 225 MW is accredited generating capacity sold to a utility, and the 200 MW is an average energy delivery quantity.

**It is a public price point for firm capacity in Indiana.** Hallador's average contracted capacity price rises about 80% from 2027 to 2029. Utilities buy accredited capacity to meet reserve obligations, and those costs generally flow into retail and large load rates over time. Buyers and operators planning Indiana or wider MISO deployments for 2029 and later should expect capacity costs to be a larger share of delivered power price than today, and should ask how their utility tariff or contract passes those costs through.

**The risk terms matter as much as the price.** The utility accepted unit contingent energy, a fuel floor and fuel cost recovery. That shows how much leverage owners of existing, accredited generation currently have. Operators negotiating their own supply should not assume firm, fixed price terms are on offer at similar levels.

**Watch Turtle Creek.** New gas capacity at Merom would be one of the few named additions in the area. It is proposed, not permitted.

What remains unknown

The reviewed sources do not name the utility, disclose the exact capacity price per MW-day or energy price per MWh for this contract, or identify any data center load the utility is serving with this purchase. Energy revenue is a company estimate at current forward prices and depends on Merom's output. The agreements themselves were not reviewed. Turtle Creek's permits, interconnection agreement and investment decision are pending.

Sources

  1. Hallador Energy Company, press release (Form 8-K Exhibit 99.1) · Published 2026-10-08
  2. Hallador Energy Company, Form 8-K · Published 2026-10-08
  3. Hoosier Energy, press release · Published 2022-02-15

Explore the market

Related reporting

Pricing & Economics

Duke Energy settles North Carolina large load terms with Amazon, Google, Meta and Microsoft, extending upfront payment rules to loads of 50 MW and up

Duke Energy said on October 7, 2026 that its two North Carolina utilities reached a settlement with the North Carolina Public Staff, Amazon, Google, Meta, Microsoft, the Carolina Industrial Group for Fair Utility Rates and the U.S. Department of Defense on terms for data centers and other large loads. If the North Carolina Utilities Commission approves it, the terms would apply to customers of 50 MW or more with an 80% load factor that sign an electric service agreement after June 1, 2026, down from the 100 MW threshold Duke previously applied. Those customers would make nonrefundable upfront payments for dedicated grid facilities, post deposits and security for shared upgrades such as transmission, and take service on a High Load Factor rate schedule. Duke expects a decision by mid-November. [Source 1]

North Carolina (Duke Energy Carolinas and Duke Energy Progress service territories) · Proposed. Settlement announced October 7, 2026; pending North Carolina Utilities Commission approval, with a decision expected by mid-November according to Duke. As of October 9, 2026.
Read the analysis
Pricing & Economics

TVA's data center rate is now in effect; a PowerCompute filing says new or expanded load above 5 MW faces a capacity charge of about $1.5 million per MW

The Tennessee Valley Authority's separate data center rate took effect on October 1, 2026, after its Board approved it on August 20. The first company filing under it gives specifics: PowerCompute says new or expanded data center load above the first 5 MW now faces a Capacity Commitment Charge of about $1.5 million per MW, that load under contract before October 1 is exempt, and that fiscal 2027 has a 2,000 MW cohort available first come, first served. PowerCompute moved its Columbus, Mississippi site to the new rate and raised contracted demand from 8.5 MW to 11 MW before the deadline. [Source 1] [Source 2] [Source 3]

Tennessee Valley Authority service territory; PowerCompute site in Columbus, Mississippi · Approved. The TVA Board approved a separate data center rate on August 20, 2026, effective October 1, 2026 (TVA fiscal year 2027) and phased in over three fiscal years. As of October 6, 2026.
Read the analysis
Pricing & Economics

Nscale says its Ward County, Texas AI data center is live; landlord Ionic Digital's filings show $182.5 million a year in rent for 234 MW

Nscale said on October 1, 2026 that its Ward County, Texas site, an empty steel shell nine months earlier, is now a live AI data center delivering thousands of GPUs. The landlord, Ionic Digital, discloses in SEC filings that Nscale leases the site's full 234 MW of energy capacity under a 126-month triple-net lease. After an 18-month ramp, annual fixed rent at 234 MW is $182.5 million. Nscale is obligated to lease another 89 MW at the same price per MW when it becomes available. [Source 1] [Source 5]

Ward County, Texas · Leased (234 MW of energy capacity leased to Nscale, per Ionic Digital filings through September 2026). Operating, per Nscale's October 1, 2026 statement. Expansion to 700 MW proposed; ERCOT classification provisional.
Read the analysis