TeraWulf doubles contracted utility power at its Muskie campus in eastern Kentucky to 1 GW and pulls the second 500 MW phase forward a year

TeraWulf said on October 5, 2026 that its subsidiary signed amended and restated agreements with Kentucky Power on October 1 that raise contracted power capacity at its Muskie Data Campus in eastern Kentucky from 500 MW to 1 GW. The second 500 MW phase moves from 2030 to 2029, subject to Kentucky Public Service Commission approval and Kentucky Power's construction schedule. The first 500 MW phase remains targeted to begin ramping in 2028. No tenant has been disclosed. [Source 1] [Source 2]

TeraWulf doubles contracted utility power at its Muskie campus in eastern Kentucky to 1 GW and pulls the second 500 MW phase forward a year
All news & analysisDevelopment & PowerGrayson, KentuckyProposed AI and HPC campus. Contracted utility service increased to 1 GW under amended Kentucky Power agreements executed October 1, 2026. First 500 MW targeted to begin ramping in 2028; second 500 MW targeted for 2029, subject to Kentucky PSC approval. No tenant disclosed as of October 5, 2026.

Disclosed terms

Contracted utility power
Raised from 500 MW to 1 GW under amended agreements executed October 1, 2026 [1]
Second phase timing
500 MW moved from 2030 to 2029, subject to Kentucky PSC approval and Kentucky Power's construction schedule [1]
First phase timing
500 MW targeted to begin ramping in 2028 [1]
Original service term
20 years from in-service date, no earlier than October 13, 2028, with minimum monthly charges tied to contracted capacity [3]
Utility collateral
$310.7 million under the service agreement plus up to $320.2 million under the transmission letter of agreement; $360.7 million of letters of credit posted July 2026 [3]
Acquisition price
$30.0 million cash, $50.0 million deferred, up to $90.0 million at $90,000 per MW delivered [3]

The disclosure and our analysis

Evidence dates

Evidence: TeraWulf Form 8-K dated October 1, 2026 and filed October 5, 2026, with its October 5, 2026 press release; TeraWulf Form 10-Q for the quarter ended June 30, 2026, filed August 5, 2026; TeraWulf acquisition release dated May 26, 2026.

What TeraWulf disclosed

TeraWulf's wholly owned subsidiary, DB Long Hunts Data LLC, executed amended and restated transmission infrastructure and energy service agreements with Kentucky Power, an American Electric Power company, on October 1, 2026. The 8-K says the agreements increase the company's contracted power capacity at Muskie from 500 MW to 1 GW. [Source 1]

The second 500 MW phase is now planned for 2029 instead of 2030, subject to Kentucky Public Service Commission approval and Kentucky Power's construction schedule. The first 500 MW phase remains targeted to begin ramping in 2028. [Source 1]

TeraWulf says Kentucky Power is developing a 765 kV / 345 kV substation connected to the regional transmission network to serve the site. The company says it continues to evaluate the campus's potential to support up to 2 GW over time, subject to additional utility planning, infrastructure and agreements. It also says development will proceed consistent with Governor Beshear's Executive Order on Data Center Development (2026-494). [Source 2]

Chairman and CEO Paul Prager said customer interest in Muskie has been tremendous and that securing the next 500 MW gives the company greater flexibility to meet prospective customers' deployment needs. That is a company claim. Neither the 8-K nor the release names a customer or lease. [Source 2]

The site and the original power deal

TeraWulf closed the Muskie acquisition on May 22, 2026. Its 10-Q says the seller owned or held rights to about 308 acres in Grayson, Kentucky, and that TeraWulf completed the purchase of the final 144 acres in August 2026. The May release described the site as about 285 acres within the 1,000-acre EastPark Industrial Park and said it was already zoned for its intended use, with permitting underway. [Source 3] [Source 4]

The 10-Q describes the original electric service agreement as covering up to 500 MW under Kentucky Power's Industrial General Service tariff for large loads, with an initial 20-year term from the in-service date, but no earlier than October 13, 2028. Energy service was expected to start in the fourth quarter of 2028. After service starts, TeraWulf pays monthly capacity and energy charges subject to minimum monthly charges tied to contracted capacity. [Source 3]

The same filing says the electric service agreement required $310.7 million of collateral and a separate transmission letter of agreement requires up to $320.2 million more in installments through the third quarter of 2028. TeraWulf posted $360.7 million of letters of credit in July 2026 to cover the first requirement and the first $50.0 million installment. [Source 3]

One note on the filings: the 10-Q's financial statement notes describe the original agreement as up to 500 MW, while its management discussion describes 1,000 MW of contracted electric service. The October 8-K is the clearest statement: contracted capacity was 500 MW and is now 1 GW. [Source 1] [Source 3]

Acquisition economics

The 10-Q puts the Muskie price at $30.0 million in cash at closing, $50.0 million deferred to the first anniversary, and contingent consideration of up to $90.0 million at $90,000 per MW of power capacity delivered under the Kentucky Power agreement, capped at 1,000 MW, within 15 years. A further $50.0 million could be due at $100,000 per MW of capacity contracted under future data center leases, up to 500 MW above the first 1,000 MW. [Source 3]

Financing

The 8-K says TeraWulf intends to increase its senior secured revolving credit facility and is seeking additional senior secured debt to support letter of credit needs under its long-term power agreements with utilities. It says there is no assurance it will obtain the financing. [Source 1]

Buyer analysis

This is our analysis.

**This is utility service, not data center capacity.** The 1 GW is contracted electric service from Kentucky Power. It is not critical IT load, not built space and not leased capacity. IT load at full build will be lower than utility service after cooling and other overhead, and TeraWulf has not disclosed an IT load figure for Muskie.

**Timelines are 2028 and 2029 at the earliest.** Power ramps from 2028 for the first phase and 2029 for the second, if the PSC approves and Kentucky Power builds on schedule. Buyers needing capacity before then should not treat Muskie as near-term supply.

**Collateral is now a real cost of getting power.** TeraWulf posted $360.7 million of letters of credit in July for the first 500 MW and is raising debt to cover more. Developers that must post this kind of security will look for creditworthy anchor tenants and long terms. Smaller buyers should expect less flexibility on campuses built this way.

**A benchmark for powered land.** If every milestone is met, TeraWulf's cash, deferred and delivery-linked payments total $170 million for 1,000 MW of delivered utility capacity, about $170,000 per MW. That is our arithmetic on the 10-Q figures. It covers land and the power position only, before any construction, and assumes the full 1,000 MW is delivered.

**Questions to ask if you are offered space at Muskie.** Which phase and delivery date, what critical IT load per building, what redundancy level, and whether the capacity is already committed to an anchor tenant.

What remains unknown

The reviewed sources do not disclose the amended agreements' minimum charges, rates or added collateral for the second 500 MW phase, the Kentucky PSC docket or decision timing, any tenant or lease for Muskie, planned critical IT load, building count or construction start. TeraWulf's May release and 10-Q give different acreage figures (285 and 308 acres).

Sources

  1. TeraWulf, Form 8-K · Published 2026-10-05
  2. TeraWulf, press release (Form 8-K Exhibit 99.1) · Published 2026-10-05
  3. TeraWulf, Form 10-Q for the quarter ended June 30, 2026 · Published 2026-08-05
  4. TeraWulf, acquisition release (Form 8-K Exhibit 99.1) · Published 2026-05-26

Related reporting

Development & Power

Skybox registers a $550 million fourth building at its Hutto campus near Austin with Texas regulators

A September 30, 2026 filing with the Texas Department of Licensing and Regulation registers Skybox Hutto 4, a $550 million core and shell data center building of about 846,300 square feet at 3399 County Road 132 in Hutto, Williamson County. Construction is listed from January 20, 2027 to October 30, 2028. No tenant is assigned. Skybox markets the campus as PowerCampus Austin, with 600 MW of total load from on-site Oncor substations. [Source 1] [Source 3]

3399 County Road 132, Hutto, Williamson County, Texas · Proposed (state accessibility registration filed September 30, 2026; listed construction January 2027 to October 2028). Not a building permit. No tenant assigned.
Read the analysis
Development & Power

Oracle plans to subscribe to part of Point Beach nuclear output through We Energies, taking on about $300 million in fuel costs; Wisconsin regulators must approve

Oracle and We Energies announced on October 2, 2026 that Oracle will subscribe to a portion of the power We Energies is required to buy from the Point Beach Nuclear Plant. We Energies says the deal is expected to save its other customers about $300 million in fuel costs. Oracle ties the commitment to Project Lighthouse, its data center development in Port Washington, Wisconsin. The arrangement needs Public Service Commission of Wisconsin approval, and We Energies says full details will be filed in the coming months. [Source 1] [Source 2]

Port Washington, Wisconsin (data center); Point Beach Nuclear Plant, Manitowoc County, Wisconsin · Announced October 2, 2026. Oracle's subscription to part of the Point Beach purchase power arrangement is proposed and subject to Public Service Commission of Wisconsin approval; full terms not yet filed.
Read the analysis
Development & Power

US and Korea select Project Star, a $22.3 billion, 6.47 GW gas power campus in Encinal, Texas planned to serve a 5 GW data center campus

The U.S. Department of Commerce and the Government of the Republic of Korea selected Project Star, a $22.3 billion natural gas power campus with 6.47 GW of generation capacity in Encinal, Texas, according to a September 30, 2026 release from NextEra Energy. Related Companies and NextEra Energy Resources plan to develop, build and operate the generation, with Lewis Energy Group bringing associated infrastructure including gas. At full scale it is planned to support a privately funded 5 GW data center campus that Related Digital is developing on an adjacent site. The release says it will be developed in phases, with initial generation as early as 2029, subject to permits and approvals. No data center tenant has been named. [Source 1]

Encinal, La Salle County, Texas · Announced (selected by the U.S. Department of Commerce and the Government of Korea, per the September 30, 2026 release). Permits and approvals pending; initial power targeted as early as 2029. The adjacent data center campus is announced only.
Read the analysis