Skybox registers a $550 million fourth building at its Hutto campus near Austin with Texas regulators

A September 30, 2026 filing with the Texas Department of Licensing and Regulation registers Skybox Hutto 4, a $550 million core and shell data center building of about 846,300 square feet at 3399 County Road 132 in Hutto, Williamson County. Construction is listed from January 20, 2027 to October 30, 2028. No tenant is assigned. Skybox markets the campus as PowerCampus Austin, with 600 MW of total load from on-site Oncor substations. [Source 1] [Source 3]

Skybox registers a $550 million fourth building at its Hutto campus near Austin with Texas regulators
All news & analysisDevelopment & Power3399 County Road 132, Hutto, Williamson County, TexasProposed (state accessibility registration filed September 30, 2026; listed construction January 2027 to October 2028). Not a building permit. No tenant assigned.

Disclosed terms

Registration
TDLR TABS2027002367, registered September 30, 2026 [1]
Building
About 846,300 square feet core and shell, future data center use [1]
Estimated cost
$550 million [1]
Construction dates
January 20, 2027 to October 30, 2028, as listed [1]
Campus load
600 MW of total load from on-site Oncor substations, per Skybox marketing [3]

The disclosure and our analysis

Evidence dates

Evidence: Texas Department of Licensing and Regulation (TDLR) project registration TABS2027002367, registered September 30, 2026; TDLR registration TABS2024018308 for Hutto 3; Skybox PowerCampus Austin brochure, undated, accessed October 4, 2026.

What the state filing shows

The TDLR registration, titled Skybox Hutto 4 Core/Shell, covers site improvements and a new core and shell building with a future use as a data center at 3399 County Road 132, Building 4, in Hutto. It describes a one story data center of about 844,300 square feet with an attached office of about 20,000 square feet, 846,300 square feet in total. [Source 1]

The filing lists an estimated cost of $550 million, a start date of January 20, 2027 and a completion date of October 30, 2028. The owner is Hutto Data Center Campus, LLC of Dallas. The design firm is Corgan. The tenant field reads not assigned, and the filing says the funds are not provided by a tenant. [Source 1]

TDLR registrations are filed for state accessibility review. They are not building permits and do not establish that construction has started.

The earlier building

A 2024 TDLR registration for Skybox Hutto 3 at the same address lists a $283.0 million core and shell building of 492,350 square feet, with construction dates of July 1, 2024 to June 1, 2026. Its owner is listed as Hutto Data Center 3, LLC. [Source 2]

The campus

Skybox markets the site as PowerCampus Austin, developed with Prologis. Its brochure describes 600 MW of total load supplied by on-site Oncor substations, two private 300 MW substations, 3,880,000 square feet of facilities and design densities of 300 to 1,000 watts per square foot. The brochure is undated, so we treat those figures as the company's marketed campus plan, not a current status. [Source 3]

Buyer analysis

This is our analysis.

**Shell cost per square foot is rising.** The filings imply about $650 per square foot for Hutto 4 and about $575 for Hutto 3. That is our arithmetic on registration estimates for core and shell work. It excludes the electrical and mechanical fit-out that drives most data center cost, and it is not a rent.

**No MW figure for the building.** The filing gives square footage and cost, not power. The campus 600 MW is a total load figure from marketing material and should not be divided across buildings.

**Unassigned tenant means a possible spec or pre-lease opportunity.** A building with no named tenant two years from delivery may still be open to a large user. Buyers in the Austin market who need capacity in late 2028 or 2029 should ask Skybox directly what power is allocated to Building 4 and when.

What remains unknown

The reviewed sources do not disclose the MW allocated to Building 4 or its power basis, any tenant or pre-lease, the status of local permits, the completion status of Hutto 3, or the current energized load at the campus. The TDLR records do not name Prologis; the partnership is described in Skybox's brochure.

Sources

  1. Texas Department of Licensing and Regulation, TABS2027002367 · Published 2026-09-30
  2. Texas Department of Licensing and Regulation, TABS2024018308 · Published 2024-07-01
  3. Skybox Datacenters, PowerCampus Austin brochure (undated; accessed) · Published 2026-10-04

Explore the market

Related reporting

Development & Power

TeraWulf doubles contracted utility power at its Muskie campus in eastern Kentucky to 1 GW and pulls the second 500 MW phase forward a year

TeraWulf said on October 5, 2026 that its subsidiary signed amended and restated agreements with Kentucky Power on October 1 that raise contracted power capacity at its Muskie Data Campus in eastern Kentucky from 500 MW to 1 GW. The second 500 MW phase moves from 2030 to 2029, subject to Kentucky Public Service Commission approval and Kentucky Power's construction schedule. The first 500 MW phase remains targeted to begin ramping in 2028. No tenant has been disclosed. [Source 1] [Source 2]

Grayson, Kentucky · Proposed AI and HPC campus. Contracted utility service increased to 1 GW under amended Kentucky Power agreements executed October 1, 2026. First 500 MW targeted to begin ramping in 2028; second 500 MW targeted for 2029, subject to Kentucky PSC approval. No tenant disclosed as of October 5, 2026.
Read the analysis
Development & Power

Oracle plans to subscribe to part of Point Beach nuclear output through We Energies, taking on about $300 million in fuel costs; Wisconsin regulators must approve

Oracle and We Energies announced on October 2, 2026 that Oracle will subscribe to a portion of the power We Energies is required to buy from the Point Beach Nuclear Plant. We Energies says the deal is expected to save its other customers about $300 million in fuel costs. Oracle ties the commitment to Project Lighthouse, its data center development in Port Washington, Wisconsin. The arrangement needs Public Service Commission of Wisconsin approval, and We Energies says full details will be filed in the coming months. [Source 1] [Source 2]

Port Washington, Wisconsin (data center); Point Beach Nuclear Plant, Manitowoc County, Wisconsin · Announced October 2, 2026. Oracle's subscription to part of the Point Beach purchase power arrangement is proposed and subject to Public Service Commission of Wisconsin approval; full terms not yet filed.
Read the analysis
Development & Power

US and Korea select Project Star, a $22.3 billion, 6.47 GW gas power campus in Encinal, Texas planned to serve a 5 GW data center campus

The U.S. Department of Commerce and the Government of the Republic of Korea selected Project Star, a $22.3 billion natural gas power campus with 6.47 GW of generation capacity in Encinal, Texas, according to a September 30, 2026 release from NextEra Energy. Related Companies and NextEra Energy Resources plan to develop, build and operate the generation, with Lewis Energy Group bringing associated infrastructure including gas. At full scale it is planned to support a privately funded 5 GW data center campus that Related Digital is developing on an adjacent site. The release says it will be developed in phases, with initial generation as early as 2029, subject to permits and approvals. No data center tenant has been named. [Source 1]

Encinal, La Salle County, Texas · Announced (selected by the U.S. Department of Commerce and the Government of Korea, per the September 30, 2026 release). Permits and approvals pending; initial power targeted as early as 2029. The adjacent data center campus is announced only.
Read the analysis