Riot's Corsicana lease: $130 per kW a month for 910 MW of powered land, and its 10-Q names Anthropic as the tenant

Riot Platforms disclosed in its quarterly report filed November 4, 2026 that the tenant at its Corsicana Facility in Navarro County, Texas will pay base rent of $130.0 per kilowatt of critical IT load capacity per month for each delivered block, escalating 3% a year, under a triple net powered land lease for 910 MW of critical IT load capacity. The 10-Q names the tenant as Anthropic PBC; Riot's earnings release calls it a leading Frontier AI Lab. The lease was signed October 28, 2026 and became effective November 4, 2026. Delivery is targeted in three phases from June 28, 2027 to July 30, 2028. [Source 1] [Source 2]

Riot's Corsicana lease: $130 per kW a month for 910 MW of powered land, and its 10-Q names Anthropic as the tenant
All news & analysisPricing & EconomicsCorsicana Facility, Navarro County, TexasLeased: lease signed October 28, 2026 and effective November 4, 2026 for 910 MW of critical IT load capacity. Delivery targeted in phases from June 28, 2027 to July 30, 2028.

Disclosed terms

Base rent
$130.0 per kW of critical IT load per month, escalating 3% annually [1]
Tenant
Anthropic PBC [1]
Capacity
910 MW of critical IT load capacity in 40 blocks, three phases [1]
Lease type
Triple net; tenant bears taxes, insurance, site expenses and electricity [1]
Module reimbursement
Up to $4.0 million per MW, or rent credits at 12% interest [1]
Effective date
Signed October 28, 2026; effective November 4, 2026 [1]
Utilization
Rent payable on the full 910 MW irrespective of utilization (Riot statement) [2]
Rockdale equipment loan
$573.0 million, Term SOFR plus 2.75%, matures December 31, 2026 [3]

The disclosure and our analysis

Evidence dates

Evidence: Riot Platforms quarterly report on Form 10-Q for the quarter ended September 30, 2026, filed November 4, 2026; Riot third quarter 2026 earnings release, Form 8-K Exhibit 99.1, November 4, 2026; credit agreement dated August 10, 2026, filed as Exhibit 10.1 to the 10-Q on November 4, 2026. All read November 6, 2026. Lease terms and status are as of November 4, 2026.

What Riot disclosed

Riot Corsicana, LLC, a wholly owned Riot subsidiary, entered into a long-term powered land lease (the Corsicana Lease) with Anthropic PBC on October 28, 2026. It became effective and binding on November 4, 2026, after Riot's board approved it and Riot Corsicana's third-party consultants approved the technical specifications for the premises. [Source 1]

1. **Rent:** base rent of $130.0 per kilowatt of critical IT load capacity per month for each delivered block of capacity, escalating 3% annually. [Source 1]

2. **Structure:** a triple net lease. The tenant bears taxes, insurance, site expenses and the cost of electricity consumed at the premises. Riot Corsicana leases land, powered pads and related infrastructure, and at its own cost builds and delivers the power and site infrastructure and operates and maintains the power infrastructure for the term. [Source 1]

3. **Capacity and delivery:** the premises are expected to provide 910 MW of critical IT load capacity in 40 blocks across three phases. Phase 1 is 400 MW, with the first block targeted for June 28, 2027 and the full phase for September 11, 2027. Phase 2 is 200 MW, with the first block targeted for December 24, 2027 and the full phase for January 28, 2028. Phase 3 is 310 MW, targeted for July 30, 2028. [Source 1]

4. **Term:** the initial term starts with the first block and runs to the end of the month of the 15th anniversary of Phase 3 commencement, with two five-year extension options for the tenant. [Source 1]

5. **Module reimbursement:** Riot Corsicana will reimburse the tenant for certain data center module costs of up to $4.0 million per MW of critical IT power actually achieved, subject to Riot obtaining financing on market terms reasonably acceptable to it. If that financing is not available, Riot will instead give rent credits that amortize the amount, plus interest at 12% a year, over the rest of the initial term. [Source 1]

Riot's earnings release adds its own figures: about $28 billion of total contract value and about $1.8 billion of average annual rent including escalators over the initial term, about $54 billion if both extensions are exercised, a contiguous 332-acre parcel, and a capital requirement of about $6 million per IT MW, or $5.5 billion overall. Riot says it funds $2 million per IT MW for site work and electrical infrastructure and reimburses the remaining $4 million per IT MW to the tenant in phases. The release says rent on each phase starts no later than 60 days after delivery of its powered pads and is payable on the full 910 MW irrespective of utilization. These are Riot's statements. [Source 2]

What the 910 MW means

Riot labels the 910 MW as critical IT load capacity, and the rent is quoted per kilowatt of that critical IT load. It is not utility service capacity, and it is leased capacity, not inventory open to other buyers. The 10-Q says the Corsicana Facility currently provides up to about 400 MW of developed capacity for bitcoin mining and is expected, on completion, to have about 1 GW of developed capacity for high-density compute. The reviewed sources do not say how much utility service capacity backs the 910 MW. [Source 1]

Economics

This is our analysis. At $130 per kW per month, first-year base rent is $1,560 per kW, or about $1.56 million per MW of critical IT load per year. Across all 910 MW at the starting rate that is about $1.42 billion a year before escalators. Riot's stated $1.8 billion average includes the 3% escalators over an initial term of roughly 15 years, so the two figures are consistent in direction. We have not rebuilt Riot's total contract value calculation.

The $130 figure is rent for powered land, not a turnkey colocation rate. The tenant procures, installs, owns and operates the modular compute deployment and pays for power, according to the release. Riot builds the high and medium voltage infrastructure and powered pads, and also funds up to $4.0 million per MW toward the tenant's modules if it can finance that. A buyer should not compare $130 per kW per month directly with a wholesale or retail quote that includes the building, cooling and operations. [Source 1] [Source 2]

The same 10-Q gives terms for the earlier Rockdale lease with the same tenant: 191 MW of critical IT load capacity, an initial 96 MW targeted for December 2027 and the rest for June 2028, with a 20-year initial term starting on full deployment. Riot DC Logistics, LLC signed a $573.0 million senior secured delayed-draw term loan with Morgan Stanley Senior Funding as administrative agent on August 10, 2026 to buy long-lead and project equipment for that 191 MW project in Milam County. Loans bear interest at Term SOFR plus 2.75% or base rate plus 1.75%, carry a 0.50% undrawn fee and mature December 31, 2026. $20.8 million was outstanding at September 30, 2026. The 10-Q does not disclose the Rockdale rent. [Source 1] [Source 3]

Status

On our status vocabulary, as of November 4, 2026: Leased. The 10-Q confirms a binding, effective lease commitment for 910 MW of critical IT load capacity at the Corsicana Facility. Delivery dates are Riot's targets. The reviewed sources do not establish that construction for the data center phases has started, that any block is Energized, or that any capacity is Available to other buyers. [Source 1]

Buyer analysis

This is our analysis. This filing gives a rare disclosed price for the powered land model, where the landlord delivers power and pads and the tenant brings its own modular data center. For buyers, $130 per kW per month with 3% escalators, triple net, is a reference point for what a large AI tenant committed to for powered land in Texas at this scale. Rent is owed on the full 910 MW regardless of use, which puts utilization risk on the tenant. A buyer weighing a powered land offer against a turnkey lease should price the modules, cooling, operations and power on top of the rent, ask who funds the modules, and get the delivery date for each block in writing.

What remains unknown

The reviewed sources do not disclose the utility service capacity or serving utility for the 910 MW, the interconnection status for the new phases, any curtailment or demand response terms, remedies for late delivery, the rent under the Rockdale lease, the terms of the Backstop Agreement referenced in the Rockdale credit agreement (redacted in the exhibit), or how Riot will finance the module reimbursement. We did not review ERCOT, PUCT or Navarro County records for this site. We did not find the Corsicana Lease itself filed as an exhibit.

Sources

  1. Riot Platforms, quarterly report on Form 10-Q for the quarter ended September 30, 2026 · Published 2026-11-04
  2. Riot Platforms, third quarter 2026 earnings release, Form 8-K Exhibit 99.1 · Published 2026-11-04
  3. Riot DC Logistics, LLC credit agreement with Morgan Stanley Senior Funding, Exhibit 10.1 to Form 10-Q · Published 2026-11-04

Related reporting

Pricing & Economics

HIVE's BUZZ HPC borrows about $129 million at 9% fixed to buy 2,303 Nvidia GB200 GPUs for a Cohere contract in Canada

HIVE Digital Technologies said on October 27, 2026 that a BUZZ HPC subsidiary entered into a fixed rate credit facility of about $129 million from an unnamed institutional lender. The loan carries 9.0% interest over a three year amortizing term at about 80% loan to cost, and funds a $165 million cluster of 2,303 Nvidia GB200 GPUs contracted to Cohere under a three year, $225 million contract. HIVE says the compute stays in Canada and GPU delivery is expected toward the end of Q4 2026. [Source 1]

Canada (facility not disclosed) · Financing agreement entered into (per HIVE, October 27, 2026); Cohere contract signed June 2026. GPU delivery expected toward the end of Q4 2026. No facility, megawatt or availability status disclosed.
Read the analysis
Pricing & Economics

Duke Energy settles North Carolina large load terms with Amazon, Google, Meta and Microsoft, extending upfront payment rules to loads of 50 MW and up

Duke Energy said on October 7, 2026 that its two North Carolina utilities reached a settlement with the North Carolina Public Staff, Amazon, Google, Meta, Microsoft, the Carolina Industrial Group for Fair Utility Rates and the U.S. Department of Defense on terms for data centers and other large loads. If the North Carolina Utilities Commission approves it, the terms would apply to customers of 50 MW or more with an 80% load factor that sign an electric service agreement after June 1, 2026, down from the 100 MW threshold Duke previously applied. Those customers would make nonrefundable upfront payments for dedicated grid facilities, post deposits and security for shared upgrades such as transmission, and take service on a High Load Factor rate schedule. Duke expects a decision by mid-November. [Source 1]

North Carolina (Duke Energy Carolinas and Duke Energy Progress service territories) · Proposed. Settlement announced October 7, 2026; pending North Carolina Utilities Commission approval, with a decision expected by mid-November according to Duke. As of October 9, 2026.
Source: Duke Energy, press release
Pricing & Economics

Hallador sells six years of Indiana power from its Merom plant to a MISO Zone 6 utility at what it calls its highest capacity price yet

Hallador Energy said on October 8, 2026 that its subsidiary Hallador Power Company signed six-year capacity and energy agreements on October 7 with an unnamed, investment-grade MISO Zone 6 utility. The deals cover deliveries from the Merom Generating Station in Sullivan County, Indiana from June 1, 2029 through May 31, 2035. The utility will buy an annual average of 225 MW of Merom's accredited capacity for about $271 million, and an annual average base energy quantity of 200 MW that Hallador estimates at about $422 million of revenue. Hallador says the capacity price is the highest it has contracted and more than 20% above its March 2026 capacity contract. The agreements took effect on signing and need no regulatory approval. [Source 1] [Source 2]

Merom Generating Station, Sullivan County, Indiana · Signed. Capacity and energy agreements executed October 7, 2026 and effective on signing, with no regulatory approval required according to Hallador. Deliveries scheduled June 1, 2029 through May 31, 2035. As of October 8, 2026.
Source: Hallador Energy Company, press release (Form 8-K Exhibit 99.1)