HIVE's BUZZ HPC borrows about $129 million at 9% fixed to buy 2,303 Nvidia GB200 GPUs for a Cohere contract in Canada

HIVE Digital Technologies said on October 27, 2026 that a BUZZ HPC subsidiary entered into a fixed rate credit facility of about $129 million from an unnamed institutional lender. The loan carries 9.0% interest over a three year amortizing term at about 80% loan to cost, and funds a $165 million cluster of 2,303 Nvidia GB200 GPUs contracted to Cohere under a three year, $225 million contract. HIVE says the compute stays in Canada and GPU delivery is expected toward the end of Q4 2026. [Source 1]

HIVE's BUZZ HPC borrows about $129 million at 9% fixed to buy 2,303 Nvidia GB200 GPUs for a Cohere contract in Canada
All news & analysisPricing & EconomicsCanada (facility not disclosed)Financing agreement entered into (per HIVE, October 27, 2026); Cohere contract signed June 2026. GPU delivery expected toward the end of Q4 2026. No facility, megawatt or availability status disclosed.

Disclosed terms

Facility
About $129 million, fixed 9.0% per year, three year amortizing term [1]
Loan to cost
About 80% [1]
Cluster
2,303 Nvidia GB200 GPUs for $165 million [1]
Customer contract
Cohere, three year fixed, $225 million total contract value [1]
Security
GPUs and related assets; limited recourse guarantee from BUZZ HPC; equity pledge [1]
Location
Canada; facility not named [1]
Delivery
Expected toward the end of Q4 2026 [1]

The disclosure and our analysis

Evidence dates

Evidence: HIVE Digital Technologies Ltd. news release dated October 27, 2026, furnished as Exhibit 99.1 to a Form 8-K filed October 29, 2026. Read October 30, 2026. All amounts are in US dollars, per the release.

What HIVE disclosed

1. **Borrower and lender:** BUZZ Alpha Cloud Inc., an indirect subsidiary of HIVE held through BUZZ High Performance Computing Inc., entered into the facility with an institutional lender the release does not name. [Source 1]

2. **Terms:** about $129 million at a fixed 9.0% per year over a three year term, with principal and interest amortizing over the life of the loan. HIVE calls it about 80% loan to cost. [Source 1]

3. **Security:** the facility is secured by the GPUs and related assets of BUZZ Alpha Cloud, supported by a limited recourse guarantee from BUZZ HPC and a pledge of BUZZ HPC's equity in BUZZ Alpha Cloud. HIVE says BUZZ HPC is not otherwise liable, and that at the end of the term HIVE will own the GPUs outright with no residual payment. [Source 1]

4. **What it buys:** HIVE's chief executive says the financing is applied to a $165 million cluster of Nvidia GB200 GPUs, which the release elsewhere gives as 2,303 GPUs, including GB200 NVL72 systems. The balance is funded from HIVE equity, which the release ties to proceeds of a 0% convertible bond. [Source 1]

5. **The contract:** the GPUs are contracted to Cohere on a three year fixed contract with a total contract value of $225 million, which HIVE says includes GPU compute plus connectivity and storage revenue. A footnote says the previously disclosed $220 million covered GPU compute only. The contract was announced June 18, 2026. [Source 1]

6. **Location and timing:** HIVE says the infrastructure financed by the facility will keep compute within Canadian borders. It does not name the facility or city. Delivery of the GPUs is expected toward the end of Q4 2026. [Source 1]

Economics and what they show

On HIVE's figures, the $225 million contract value is about 1.36 times the $165 million cluster cost over three years, before power, facility, staffing and financing costs, none of which the release breaks out. The loan amortizes over the same three years as the contract, so the lender is underwriting the Cohere revenue rather than any residual value of the GPUs. Those ratios are our arithmetic from HIVE's disclosed figures, not HIVE's statements.

HIVE also says it has signed $600 million of total contract value for GPU cloud deals this year across three GPU off take contracts. The release does not itemize the other two in this passage.

What is not disclosed

The release gives no megawatt figure, no facility location, no lender name and no closing or drawdown date. It does not say what data center will house the cluster or whether that capacity is owned or leased by HIVE. Covenants include required debt service coverage ratios, but their levels are not disclosed.

Status

On our status vocabulary, as of October 27, 2026: the financing agreement has been entered into and the customer contract is signed. Neither establishes construction, energization or capacity Available to other customers. The GPUs have not yet been delivered.

Buyer analysis

This is our analysis, not HIVE's. A 9% fixed rate at about 80% loan to cost, secured by the GPUs and limited recourse to the parent, is a useful data point for how lenders now price GPU debt when a named customer contract sits behind it. For AI buyers, it also shows the structure many GPU clouds use: the term of the customer contract matches the amortization of the hardware loan. A buyer asking for a shorter term or more flexible exit should expect that to affect price, because it breaks that match.

For buyers with data residency requirements, HIVE is marketing the cluster on Canadian sovereignty. The release does not identify the facility, so any buyer would need to confirm the site and its power and cooling directly with the provider.

We have not assigned this story to a tracked market. HIVE says only that the compute will be in Canada.

What remains unknown

The reviewed release does not name the lender; give the facility location, its megawatts or whether HIVE owns or leases it; give a closing or drawdown date; state covenant levels; or itemize the other GPU contracts within the $600 million HIVE cites.

Sources

  1. HIVE Digital Technologies Ltd., news release (Form 8-K Exhibit 99.1) · Published 2026-10-29

Related reporting

Pricing & Economics

Duke Energy settles North Carolina large load terms with Amazon, Google, Meta and Microsoft, extending upfront payment rules to loads of 50 MW and up

Duke Energy said on October 7, 2026 that its two North Carolina utilities reached a settlement with the North Carolina Public Staff, Amazon, Google, Meta, Microsoft, the Carolina Industrial Group for Fair Utility Rates and the U.S. Department of Defense on terms for data centers and other large loads. If the North Carolina Utilities Commission approves it, the terms would apply to customers of 50 MW or more with an 80% load factor that sign an electric service agreement after June 1, 2026, down from the 100 MW threshold Duke previously applied. Those customers would make nonrefundable upfront payments for dedicated grid facilities, post deposits and security for shared upgrades such as transmission, and take service on a High Load Factor rate schedule. Duke expects a decision by mid-November. [Source 1]

North Carolina (Duke Energy Carolinas and Duke Energy Progress service territories) · Proposed. Settlement announced October 7, 2026; pending North Carolina Utilities Commission approval, with a decision expected by mid-November according to Duke. As of October 9, 2026.
Read the analysis
Pricing & Economics

Hallador sells six years of Indiana power from its Merom plant to a MISO Zone 6 utility at what it calls its highest capacity price yet

Hallador Energy said on October 8, 2026 that its subsidiary Hallador Power Company signed six-year capacity and energy agreements on October 7 with an unnamed, investment-grade MISO Zone 6 utility. The deals cover deliveries from the Merom Generating Station in Sullivan County, Indiana from June 1, 2029 through May 31, 2035. The utility will buy an annual average of 225 MW of Merom's accredited capacity for about $271 million, and an annual average base energy quantity of 200 MW that Hallador estimates at about $422 million of revenue. Hallador says the capacity price is the highest it has contracted and more than 20% above its March 2026 capacity contract. The agreements took effect on signing and need no regulatory approval. [Source 1] [Source 2]

Merom Generating Station, Sullivan County, Indiana · Signed. Capacity and energy agreements executed October 7, 2026 and effective on signing, with no regulatory approval required according to Hallador. Deliveries scheduled June 1, 2029 through May 31, 2035. As of October 8, 2026.
Read the analysis
Pricing & Economics

TVA's data center rate is now in effect; a PowerCompute filing says new or expanded load above 5 MW faces a capacity charge of about $1.5 million per MW

The Tennessee Valley Authority's separate data center rate took effect on October 1, 2026, after its Board approved it on August 20. The first company filing under it gives specifics: PowerCompute says new or expanded data center load above the first 5 MW now faces a Capacity Commitment Charge of about $1.5 million per MW, that load under contract before October 1 is exempt, and that fiscal 2027 has a 2,000 MW cohort available first come, first served. PowerCompute moved its Columbus, Mississippi site to the new rate and raised contracted demand from 8.5 MW to 11 MW before the deadline. [Source 1] [Source 2] [Source 3]

Tennessee Valley Authority service territory; PowerCompute site in Columbus, Mississippi · Approved. The TVA Board approved a separate data center rate on August 20, 2026, effective October 1, 2026 (TVA fiscal year 2027) and phased in over three fiscal years. As of October 6, 2026.
Read the analysis