PG&E reports 12,870 MW of data center load in its pipeline and lists large load beyond an initial 1.8 GW as work to be delayed or deferred

PG&E's third quarter 2026 earnings presentation, furnished October 22, 2026, shows 12,870 MW of new data center load in its pipeline as of September 2026, up from 12,710 MW in June. Most of it, 8,350 MW, is at the application and preliminary engineering stage. PG&E says it has energized 174 MW of new data center projects since 2024. A capital plan slide lists large load beyond an initial 1.8 GW among work that will be delayed or deferred. [Source 1] [Source 2]

PG&E reports 12,870 MW of data center load in its pipeline and lists large load beyond an initial 1.8 GW as work to be delayed or deferred
All news & analysisDevelopment & PowerPG&E service territory, Northern and Central California (no project sites disclosed)Mixed pipeline as reported by PG&E as of September 2026: 8,350 MW at application and preliminary engineering, 3,880 MW in final engineering, 400 MW with an executed interconnection construction agreement, 240 MW in construction; 174 MW energized since 2024. Large load beyond an initial 1.8 GW listed as delayed or deferred work. None of this establishes available colocation capacity. As of October 22, 2026.

Disclosed terms

Data center pipeline
12,870 MW as of September 2026, up from 12,710 MW in June 2026 [1]
Application and preliminary engineering
8,350 MW; 27 projects as of September 30, 2026 [1]
Final engineering
3,880 MW; 18 projects as of September 30, 2026 [1]
Construction agreement and construction
400 MW with executed agreement (3 projects); 240 MW in construction [1]
Energized since 2024
174 MW of new data center projects [2]
Deferred work
Large load beyond an initial 1.8 GW, per PG&E's capital plan slide [1]
Pipeline scope
Applications for new data center load requesting 20 MW or more [1]

The disclosure and our analysis

Evidence dates

Evidence: PG&E Corporation third quarter 2026 earnings presentation and earnings release, both furnished with a Form 8-K on October 22, 2026 and read October 23, 2026. Pipeline figures are as of June 2026 and September 2026; project counts are as of September 30, 2026.

What PG&E disclosed

PG&E's pipeline covers applications to serve new data center load requesting 20 megawatts or more. The presentation does not say whether the megawatts are peak demand, contracted load or another measure, so we describe them as requested data center load as PG&E counts it. They are not critical IT figures. [Source 1]

The pipeline by stage, in MW, June 2026 then September 2026: [Source 1]

1. **Application and preliminary engineering:** 8,200 then 8,350. PG&E says 27 projects were in this stage as of September 30, 2026. Entry requires an application and payment of a $500,000 preliminary engineering study fee.

2. **Final engineering:** 3,880 then 3,880. 18 projects as of September 30, 2026. Entry requires a signed work performance agreement and payment covering design and procurement, which PG&E puts at 10% of total estimated project cost.

3. **Interconnection construction agreement executed:** 490 then 400. 3 projects as of September 30, 2026.

4. **Construction:** 140 then 240. PG&E says this stage ends after customer energization.

5. **Total:** 12,710 then 12,870.

The earnings release says PG&E has energized 174 megawatts of new data center projects since 2024. The presentation's pipeline table also includes an online since 2024 row showing 88 and 174, without separate labels. [Source 1] [Source 2]

The deferral line

On a slide presenting its 2026 to 2027 capital plan, with 2028 to 2030 marked as pending the outcome of its strategic review, PG&E lists work that will be delayed or deferred. The list includes connecting new housing projects, interconnecting new renewable generation projects, technology upgrades, and large load beyond initial 1.8 GWs. The presentation does not define what the 1.8 GW includes, which pipeline projects fall beyond it, or how long any delay would last. The release separately says PG&E is implementing a previously announced $2 billion reduction to its 2027 capital plan. [Source 1] [Source 2]

PG&E attributes a customer benefit to the load. It says that with appropriate pricing, every one gigawatt of new data center load could help customers save 1% or more on their monthly electric bill. That is a company estimate with stated assumptions, not a measured result. [Source 1] [Source 2]

Buyer analysis

This is our analysis, not a PG&E statement. The pipeline is large but early. About 65% of the September total sits at the application and preliminary engineering stage, and only 640 MW had reached an executed interconnection construction agreement or construction. Energized load since 2024 is 174 MW. A pipeline megawatt is a utility service request, not leasable colocation space.

The deferral line matters most for new projects in PG&E territory. If load beyond an initial 1.8 GW is deferred, later entrants may wait longer for service. Buyers evaluating a planned Northern California facility served by PG&E should ask the provider which pipeline stage its service request is in, whether it has a signed work performance agreement or construction agreement, and what energization date PG&E has committed to in writing.

Existing facilities with energized service are not described by these figures. Buyers should not read the pipeline as a forecast of new colocation supply.

What remains unknown

The reviewed sources do not identify the projects, developers or sites in the pipeline, their locations within PG&E's territory, the measurement basis for pipeline megawatts, what the initial 1.8 GW comprises, which projects fall beyond it, or the length of any deferral. They do not give energization dates for projects in construction.

Sources

  1. PG&E Corporation, third quarter 2026 earnings presentation (SEC Exhibit to Form 8-K) · Published 2026-10-22
  2. PG&E Corporation, third quarter 2026 earnings release (SEC Exhibit to Form 8-K) · Published 2026-10-22

Related reporting

Development & Power

Applied Digital and Soluna sign an agreement to form a joint venture for a planned 50 MW critical IT AI data center at Dorothy 3 in Briscoe County, Texas

Soluna Holdings disclosed on October 21, 2026 that it signed a subscription agreement on October 20 with affiliates of Applied Digital to form a jointly owned project company. The company would develop a planned 50 MW critical IT data center for AI and high performance computing at Soluna's Project Dorothy 3 site near Silverton in Briscoe County, Texas, next to the Briscoe Wind Farm, which Soluna describes as a 150 MW wind farm. Applied would hold 51% and Soluna 49%. Closing is conditional, including a county tax abatement vote, and is expected on or before December 1, 2026. ChronoScale, which Soluna says Applied majority owns, has signed only a nonbinding letter of intent to lease the facility. [Source 1] [Source 2]

Project Dorothy 3, near Silverton, Briscoe County, Texas · Proposed. Subscription agreement signed October 20, 2026; joint venture closing conditional on a Briscoe County tax abatement vote and other conditions, expected on or before December 1, 2026. Tenant is a nonbinding letter of intent only. The filing says some site development work has begun; reviewed sources do not establish building construction, energization, a lease or availability. As of October 23, 2026.
Read the analysis
Development & Power

FERC accepts PJM's 50 MW large load definition and registry but rejects its plan to connect new large loads ahead of new capacity

The Federal Energy Regulatory Commission on October 9, 2026 accepted two parts of PJM Interconnection's large load proposal: a definition of Large Load as 50 MW or more of cumulative peak load at a single electrical site, and a Large Load Registry, both effective October 12, 2026. It rejected the rest, including the Interim Resource Adequacy Service that would have let new large loads connect before matching new capacity in exchange for curtailment exposure. [Source 1]

PJM Interconnection region · Approved in part. FERC accepted the Large Load definition and Large Load Registry effective October 12, 2026 and directed a PJM compliance filing within 30 days. IRAS, the new capacity designation requirement, Bring Your Own New Capacity rules and the demand curve exclusion were rejected. As of October 9, 2026.
Read the analysis
Development & Power

Stafford County, Virginia approves the Accokeek Center data center rezoning, with about 122 MW of Dominion service planned at full build-out

Stafford County supervisors voted 4-3 on October 7, 2026 to rezone about 121 acres for the Accokeek Center data center campus and to approve a Dominion substation permit, according to local reports. County documents describe up to 590,000 square feet in two buildings between U.S. 1 and Interstate 95. The applicant says the project is expected to need about 122 MW of electrical service at full build-out. [Source 1] [Source 3] [Source 4]

West side of Richmond Highway (U.S. 1), about 2,500 feet north of Eskimo Hill Road, Falmouth District, Stafford County, Virginia · Approved. Rezoning to M-2 and the substation conditional use permit approved 4-3 on October 7, 2026, per local reports; county minutes were not yet posted when checked on October 14, 2026. Site plan and utility approvals remain. The applicant's fiscal analysis expects the first building to operate in 2029. Not available. As of October 14, 2026.
Read the analysis