Colocation Scout / News & Analysis

Amazon data centers in northern Indiana and Mississippi: Blackstone trust values 647 MW at $5.0B, a 7.0% cap rate

Blackstone Digital Infrastructure Trust (NYSE: BXDC) has agreed to buy a 75.1% controlling interest in two joint ventures that will own 13 newly constructed Amazon data centers with 647 megawatts of aggregate IT power capacity, nine buildings in northern Indiana and four in Mississippi, according to a Form 8-K filed November 16, 2026. The filing puts the aggregate gross value at $5.0 billion at an initial capitalization rate of 7.0%. At closing, Amazon Data Services will lease back 100% of both campuses on triple net leases with a weighted average initial term of 12 years and a 2.75% annual rent escalator. The deal had not closed as of the filing; either side may terminate if it does not close by December 31, 2026. [Source 1] [Source 2]

Amazon data centers in northern Indiana and Mississippi: Blackstone trust values 647 MW at $5.0B, a 7.0% cap rate
All news & analysisDeals & LeasingNorthern Indiana (greater Chicago market) and Mississippi; exact sites not disclosedAnnounced as of November 16, 2026: contribution agreement signed November 11, 2026, closing pending and expected in Q4 2026. To be 100% leased to Amazon Data Services at closing. Not available to other buyers.

Disclosed terms

Value
$5.0 billion aggregate gross value at a 7.0% initial cap rate [1]
Capacity
647 MW of aggregate IT power capacity across 13 buildings [1]
Locations
Nine buildings in northern Indiana, four in Mississippi [1]
Lease
Triple net, 12 year weighted average initial term, 2.75% annual escalator [1]
Ownership
Trust 75.1%, Amazon affiliates 24.9% ($0.6 billion) [1]
Financing
$1.9 billion of IPO cash plus about $2.5 billion of non-recourse mortgage loans [1]
Termination fee
$150.0 million if a party fails to close; outside date December 31, 2026 [1]

The disclosure and our analysis

Evidence dates

Evidence: Blackstone Digital Infrastructure Trust Form 8-K for an event on November 11, 2026, filed November 16, 2026, with the contribution agreement (Exhibit 2.1) and press release (Exhibit 99.1); the trust's transaction summary presentation, filed as Exhibit 99.2 to a second Form 8-K on November 16, 2026. Reviewed November 18, 2026.

What the filings disclose

On November 11, 2026, Jade IN Member LLC and Jade MS Member LLC, wholly owned indirect subsidiaries of the trust, signed a contribution agreement with Jade SMIN LLC and Jade SMMS LLC, affiliates of Amazon Data Services, Inc. The trust's side agreed to acquire a 75.1% controlling interest in each of two limited liability companies that will own the two campuses. Amazon's side will contribute the properties and keep a 24.9% non-controlling interest, which the 8-K values at $0.6 billion, plus a cash distribution. [Source 1]

The 8-K describes the properties as 13 newly constructed data centers with 647 megawatts of aggregate information technology power capacity: one campus of nine buildings in northern Indiana, which the filing places in the greater Chicago data center market, and one campus of four buildings in Mississippi. The transaction summary calls them powered shell data center campuses and says more than two thirds of the value is in northern Indiana and less than one third in Mississippi. The contribution agreement refers to the two sites as the SBN Property, whose owner is in good standing in Indiana, and the JAN Property, whose owner is in good standing in Mississippi. The reviewed filings do not give a city, county or street address for either campus, and they do not split the 647 MW between them. [Source 1] [Source 2] [Source 4]

Lease terms, per the filings

At closing each campus will be 100% leased to Amazon Data Services on a long term triple net lease, with payment obligations guaranteed by Amazon.com, Inc. The 8-K gives a weighted average initial lease term of 12 years, a weighted average fully extended term of 32 years and an annual rent escalator of 2.75%. The transaction summary says the extended term reflects two renewal options of 10 years each and describes the guarantor's credit rating as S&P AA. [Source 1] [Source 2]

The transaction summary defines the 7.0% initial cap rate as base rent for the initial year of the lease term divided by the aggregate gross value, which includes transaction costs. The filings do not state the rent in dollars. [Source 2]

How the deal is funded

The 8-K says the trust expects to contribute $1.9 billion of cash from its initial public offering for its 75.1% interest. The rest, including transaction costs, is expected to come from approximately $2.5 billion of new non-recourse mortgage loans secured by the properties, for which the trust has debt commitment letters. The closing is subject to a minimum cash distribution to the Amazon parties and other conditions, and the 8-K says the transaction may not be completed on its contemplated terms, or at all. [Source 1]

Either side may terminate if the closing does not occur by December 31, 2026, unless extended. If one side fails to close when required, the other is entitled to a $150.0 million termination fee as its sole remedy. The trust's press release says the transaction is expected to close in the fourth quarter of 2026. [Source 1] [Source 3]

Status

As of November 16, 2026: Announced, with a definitive contribution agreement signed November 11, 2026 and closing pending. The leases to Amazon Data Services are to be entered at closing, so the campuses are not offered to other tenants. The filings describe the buildings as newly constructed but do not establish when each was energized or how much of the 647 MW is in service. [Source 1]

Buyer and operator analysis

This is our arithmetic, from the filed figures only. A 7.0% initial cap rate on a $5.0 billion gross value implies first year base rent of roughly $350 million at 100% ownership. Spread over 647 MW of IT power capacity, that is roughly $541,000 per MW a year, or about $45 per kW a month. The gross value works out to about $7.7 million per MW. Both figures are approximate: the gross value includes transaction costs and is rounded, and the rent is not disclosed directly.

That $45 is the rent for a powered shell on a triple net lease, where the tenant pays the building's operating costs. It is not a colocation price. Retail and wholesale colocation quotes usually bundle the cooling, electrical fit out and operations that a hyperscaler supplies for itself inside a powered shell. Compare it with other hyperscale shell and land leases, not with a per kW colocation quote.

For operators and landlords, the deal shows what one public buyer will pay for a long Amazon lease: a 7.0% yield on a 12 year initial term, with 2.75% annual increases. For buyers, it is another sign that much new capacity in northern Indiana is being built for one hyperscaler and financed against that lease, rather than offered as open inventory.

What remains unknown

The reviewed filings do not disclose the annual rent in dollars, the split of the 647 MW or the value between the two campuses, the city, county or address of either campus, the utilities serving them, the energization dates, the size of the cash distribution to Amazon, or the lenders and terms of the mortgage loans. Several values in the contribution agreement, including each property's contribution value and the utility power supplied to the Mississippi property, are redacted. We read the 8-K, the press release, the transaction summary and searched the contribution agreement; the leases themselves are not filed.

Sources

  1. Blackstone Digital Infrastructure Trust, Form 8-K (Item 1.01), event November 11, 2026 · Published 2026-11-16
  2. Blackstone Digital Infrastructure Trust, transaction summary, Form 8-K Exhibit 99.2 · Published 2026-11-16
  3. Blackstone Digital Infrastructure Trust, press release, Form 8-K Exhibit 99.1 · Published 2026-11-16
  4. Contribution agreement dated November 11, 2026, Form 8-K Exhibit 2.1 · Published 2026-11-16

Explore the market

Related reporting

Deals & Leasing

Gainesville, Virginia data center sells for $779.5M: Blue Owl trust buys 54 MW hyperscaler building with a $512.6M loan

Blue Owl Digital Infrastructure Trust paid approximately $779.5 million on November 10, 2026 for a 54 megawatt data center in Gainesville, Virginia that its filing says is 100% leased to a hyperscaler customer. The property is 13720 University Boulevard, according to the purchase agreement. Citibank and Wells Fargo lent approximately $512.6 million against it at one-month Term SOFR plus 2.00%. The trust disclosed the deal in a Form 8-K filed with the SEC. [Source 1] [Source 2]

13720 University Boulevard, Gainesville, Prince William County, Virginia · Leased: the 8-K says the 54 MW building is 100% leased to a hyperscaler customer as of November 10, 2026, when the sale closed.
Read the analysis
Deals & Leasing

Hut 8 will pay $100 million at closing for two West Texas data center sites from Poolin's Chapter 11 sale, with up to $80 million more tied to signing an AI or HPC lease

Hut 8 disclosed on November 4, 2026 the terms of its agreement to buy two data center sites in West Texas from affiliates of Poolin Technology through a Chapter 11 sale. Consideration is up to $180.0 million: $100.0 million payable at closing and up to $80.0 million contingent on a qualifying data center lease or transfer for AI or HPC use. The U.S. Bankruptcy Court for the District of New Jersey approved the sale on October 2, 2026. Hut 8 says the sites have up to 230 MW of utility capacity at full energization, subject to final power approvals and infrastructure development. Closing is scheduled for December 2026. [Source 1] [Source 2]

West Texas (sites not named in the reviewed Hut 8 filings) · Approved: the U.S. Bankruptcy Court for the District of New Jersey approved the sale on October 2, 2026. Closing scheduled for December 2026, subject to seller extension rights and remaining closing conditions. Not closed as of November 4, 2026.
Read the analysis
Development & Power

Exelon counts about 11 GW of high probability data center load, 9 GW of it at ComEd, with 23 GW more in cluster studies

Exelon said in its third quarter 2026 earnings slides, filed October 30, 2026, that it counts about 11 GW of high probability data center load: about 9 GW at ComEd and about 2 GW in its MidAtlantic utilities. It defines that tier as load in advanced phases of design or backed by FERC approved transmission security agreements, and says about 45% has those agreements, backed by about $1.2 billion in collateral. A further future pipeline of about 23 GW, 14 GW at ComEd and 9 GW MidAtlantic, sits within current or future cluster studies due to conclude in 2026 and 2027. [Source 1]

ComEd service area, northern Illinois; Exelon MidAtlantic utilities · Utility forecast. About 11 GW high probability data center load (ComEd about 9 GW, MidAtlantic about 2 GW), in advanced design or backed by FERC approved TSAs; about 45% with TSAs and about $1.2 billion collateral. Future pipeline about 23 GW in cluster studies concluding 2026 and 2027. As of October 30, 2026.
Read the analysis