Cipher lifts its Barber Lake cost estimate to about $2.94 billion and plans an $850 million note sale that will help fund it

Cipher Digital now estimates that its Barber Lake data center in Colorado City, Texas will cost $2,941 million to $2,966 million to complete, against an original budget of $2,157 million, according to an investor presentation filed with the SEC on October 13, 2026. The cost estimate is dated October 6, 2026. The same filing shows two of the facility's five data halls with rent commencement moved from the fourth quarter of 2026 to the first quarter of 2027, and announces a proposed $850 million private offering of convertible notes whose proceeds will partly fund additional equity in the project. [Source 1] [Source 2]

Cipher lifts its Barber Lake cost estimate to about $2.94 billion and plans an $850 million note sale that will help fund it
All news & analysisDevelopment & PowerColorado City, TexasUnder construction. Cipher says construction is on track to meet amended delivery milestones, with rent commencement on Data Halls 1 and 2 in Q4 2026, Data Halls 3 and 4 in Q1 2027 (originally Q4 2026) and Data Hall 5 in Q1 2027. Leased to Fluidstack, with a follow-on AI lab commitment. Not available. As of September 30, 2026, with the cost estimate as of October 6, 2026.

Disclosed terms

Original budget
$2,157 million [1]
Estimate at completion
$2,941 million to $2,966 million, as of October 6, 2026 [1]
Net cost to Cipher
$2,704 million to $2,716 million [1]
Data Halls 3 and 4
Rent commencement amended from Q4 2026 to Q1 2027 [1]
Proposed notes
$850 million of 0.00% convertible senior notes due 2032, plus a $150 million option [2]
Contracted gross HPC capacity
700 MW, gross basis, as of September 30, 2026 [1]

The disclosure and our analysis

Evidence dates

Evidence: Cipher Digital investor presentation (Form 8-K Exhibit 99.1) and offering release (Exhibit 99.2), both filed October 13, 2026. The presentation states figures as of September 30, 2026 unless noted, and dates its cost to complete estimate October 6, 2026. Background: Cipher's lease amendment release of September 25, 2026 and its Barber Lake disclosures of September 25, 2025 and November 20, 2025.

What Cipher discloses

**Cost.** A chart in the presentation shows an original Barber Lake budget of $2,157 million and a current estimate at completion of $2,941 million to $2,966 million. Cipher defines estimate at completion as the current estimated all in development cost once the project is completed. The chart shows $359 million of change orders and $375 million to $400 million of additional costs to complete. After $50 million of change orders it labels as reimbursed and $187 million to $200 million of costs it says the tenant will repay as additional rent, the chart puts Cipher's net cost at $2,704 million to $2,716 million. [Source 1]

**Delivery.** The presentation's schedule table lists five data halls. Data Halls 1 and 2 keep Q4 2026 rent commencement. Data Halls 3 and 4 show Q4 2026 originally and Q1 2027 as amended. Data Hall 5 stays at Q1 2027. Cipher says construction remains on track to meet the amended milestones, that no rent credits have been incurred to date, that critical equipment is fully secured and that the tenant is deploying compute throughout the facility. [Source 1]

**Financing.** Cipher announced a proposed private offering of $850 million of 0.00% convertible senior notes due November 1, 2032, with an option for initial purchasers to buy up to $150 million more. Pricing was expected after market close on October 13. Net proceeds are to fund capped call transactions, additional equity investment in Barber Lake, the build out of its high performance computing pipeline, more development sites and general corporate purposes. Cipher also plans to exchange part of its 1.75% convertible notes due 2030 for stock. [Source 2] The presentation describes about $750 million of additional project equity to support the 10 year lease extension and the added cost sharing. [Source 1]

**Lease economics, as Cipher states them.** Cipher says the September amendment raises contracted revenue at Barber Lake from $3.8 billion to over $9 billion, with a 20 year base lease term. It says the tenant will repay 50% of costs above the initial $359 million threshold as additional rent over the lease, including a return on capital, and that rentalizing $187 million of costs adds about $480 million of revenue. [Source 1] [Source 3]

**Portfolio, as of September 30, 2026.** Cipher reports 907 MW of operating and contracted capacity, defined as gross MW for executed HPC leases plus operating bitcoin self mining capacity, and 700 MW of contracted gross HPC capacity. It reports $16.6 billion of contracted revenue and a 17.3 year weighted average lease term. It also lists a 1 GW Texas site called Colchis with conditional base load status in ERCOT's Batch Zero process and a new site called Apollo with target energization in 2028. [Source 1]

Capacity, as previously disclosed

The October filing does not restate Barber Lake's megawatts. Cipher's September 2025 filing described a Fluidstack lease for 168 MW of critical IT load, and its November 2025 release added 39 MW of critical IT load. [Source 4] [Source 5] Those two critical IT figures total 207 MW, our arithmetic. They should not be combined with Cipher's portfolio gross MW figures.

Buyer analysis

This is our analysis.

**Cost growth on a signed AI build is now quantified.** By Cipher's own chart, the estimate at completion is about 36% to 38% above the original budget, our arithmetic. Most of that sits with the developer, not the tenant. Buyers should expect developers to price this experience into new deals through higher rents, tighter change order clauses or larger cost sharing asks.

**The cost sharing clause is worth copying, carefully.** Cipher bears the first $359 million above budget. The tenant then pays half of further overruns through rent, with a return on capital. A tenant negotiating a large build should ask for a fixed first loss on the provider and a clear cap on any pass through.

**Hall level dates matter.** Two halls slipped one quarter while Cipher reports no rent credits incurred. Buyers should tie rent start to acceptance of each hall and write delay credits that begin at a stated date.

**This is committed capacity.** Barber Lake is leased for up to 20 years across two tenants. It is not open inventory for other buyers.

What remains unknown

The reviewed filings do not disclose rent per kW, the AI lab's identity, final note pricing, how much of the offering will go to Barber Lake, or the megawatts of each data hall. The cost chart is read from the filed presentation; Cipher's later filings may refine these ranges. The September 2025 and November 2025 critical IT figures were not restated in the October filing.

Sources

  1. Cipher Digital, Project Compass investor presentation, Form 8-K Exhibit 99.1 · Published 2026-10-13
  2. Cipher Digital, proposed convertible notes offering release, Form 8-K Exhibit 99.2 · Published 2026-10-13
  3. Cipher Digital, Barber Lake lease amendment release · Published 2026-09-25
  4. Cipher Mining, Form 8-K on the Fluidstack lease · Published 2025-09-25
  5. Cipher Mining, additional 39 MW Fluidstack agreement release · Published 2025-11-20

Related reporting

Development & Power

CleanSpark's 585 MW Sealy and Brazoria, Texas sites: tenant exclusivity expired, conditional ERCOT Batch Zero status

CleanSpark said on November 24, 2026 that the exclusivity period covering its Sealy and Brazoria, Texas campuses has expired, and that commercialization is proceeding with its existing Sandersville tenant and others. In the same fiscal fourth quarter release, the company reported a Conditional Batch Zero Baseload designation on 585 MW: 285 MW at Sealy and 300 MW at Brazoria Phase 1. It disclosed no Texas lease. [Source 1]

Sealy and Brazoria campuses, Texas · Announced sites with conditional grid designations (CleanSpark reports Conditional Batch Zero Baseload designation on 585 MW and Conditional Batch Zero Studied Load for Brazoria Phase 2, up to 300 MW, as of November 24, 2026). Tenant exclusivity expired. No lease disclosed. Not available capacity.
Read the analysis
Development & Power

Denton, Texas data center permit S26-0006 seeks a Specific Use Permit for 23.8 acres off E. University Dr.

A Specific Use Permit application for a data center on 23.8 acres in Denton, Texas, south of E. University Dr. and west of Geesling Rd., was submitted to the City of Denton on November 9, 2026. The city's planning record lists it as case S26-0006, project name Birddog, on land zoned Light Industrial and not platted. Its status was Under Review as of November 13, 2026. The record lists no megawatts, end user or hearing date. [Source 1]

South of E. University Dr. and west of Geesling Rd., Denton, Denton County, Texas · Proposed (Specific Use Permit application S26-0006 submitted November 9, 2026; city status Under Review as of November 13, 2026). No hearing date set in the record. No megawatt figure, tenant or end user disclosed.
Read the analysis
Development & Power

Entergy Arkansas plans a second phase of service for Google's West Memphis data center campus, with about $600 million of grid work and a 440 MW solar contract paid for by Google

Entergy Arkansas announced on October 19, 2026 a second phase of electric service for Google's data center campus in West Memphis, Arkansas. The utility says the phase needs about $600 million of planned investment plus a power purchase agreement, all covered by Google: two battery systems, a 440 MW (ac) solar contract, an expanded Galet substation and two new 230 kV lines to serve the expanded campus. The expansion still has to be submitted to the Arkansas Public Service Commission; Entergy targets service in 2028 if it is approved. Entergy listed the expanded Google agreement among its third quarter highlights on November 2. [Source 1] [Source 2]

West Memphis, Crittenden County, Arkansas · Announced October 19, 2026; to be submitted to the Arkansas Public Service Commission for approval. Pending approval, Entergy expects service in 2028. Not approved as of November 2, 2026.
Read the analysis