Cipher lifts its Barber Lake cost estimate to about $2.94 billion and plans an $850 million note sale that will help fund it

Cipher Digital now estimates that its Barber Lake data center in Colorado City, Texas will cost $2,941 million to $2,966 million to complete, against an original budget of $2,157 million, according to an investor presentation filed with the SEC on October 13, 2026. The cost estimate is dated October 6, 2026. The same filing shows two of the facility's five data halls with rent commencement moved from the fourth quarter of 2026 to the first quarter of 2027, and announces a proposed $850 million private offering of convertible notes whose proceeds will partly fund additional equity in the project. [Source 1] [Source 2]

Cipher lifts its Barber Lake cost estimate to about $2.94 billion and plans an $850 million note sale that will help fund it
All news & analysisDevelopment & PowerColorado City, TexasUnder construction. Cipher says construction is on track to meet amended delivery milestones, with rent commencement on Data Halls 1 and 2 in Q4 2026, Data Halls 3 and 4 in Q1 2027 (originally Q4 2026) and Data Hall 5 in Q1 2027. Leased to Fluidstack, with a follow-on AI lab commitment. Not available. As of September 30, 2026, with the cost estimate as of October 6, 2026.

Disclosed terms

Original budget
$2,157 million [1]
Estimate at completion
$2,941 million to $2,966 million, as of October 6, 2026 [1]
Net cost to Cipher
$2,704 million to $2,716 million [1]
Data Halls 3 and 4
Rent commencement amended from Q4 2026 to Q1 2027 [1]
Proposed notes
$850 million of 0.00% convertible senior notes due 2032, plus a $150 million option [2]
Contracted gross HPC capacity
700 MW, gross basis, as of September 30, 2026 [1]

The disclosure and our analysis

Evidence dates

Evidence: Cipher Digital investor presentation (Form 8-K Exhibit 99.1) and offering release (Exhibit 99.2), both filed October 13, 2026. The presentation states figures as of September 30, 2026 unless noted, and dates its cost to complete estimate October 6, 2026. Background: Cipher's lease amendment release of September 25, 2026 and its Barber Lake disclosures of September 25, 2025 and November 20, 2025.

What Cipher discloses

**Cost.** A chart in the presentation shows an original Barber Lake budget of $2,157 million and a current estimate at completion of $2,941 million to $2,966 million. Cipher defines estimate at completion as the current estimated all in development cost once the project is completed. The chart shows $359 million of change orders and $375 million to $400 million of additional costs to complete. After $50 million of change orders it labels as reimbursed and $187 million to $200 million of costs it says the tenant will repay as additional rent, the chart puts Cipher's net cost at $2,704 million to $2,716 million. [Source 1]

**Delivery.** The presentation's schedule table lists five data halls. Data Halls 1 and 2 keep Q4 2026 rent commencement. Data Halls 3 and 4 show Q4 2026 originally and Q1 2027 as amended. Data Hall 5 stays at Q1 2027. Cipher says construction remains on track to meet the amended milestones, that no rent credits have been incurred to date, that critical equipment is fully secured and that the tenant is deploying compute throughout the facility. [Source 1]

**Financing.** Cipher announced a proposed private offering of $850 million of 0.00% convertible senior notes due November 1, 2032, with an option for initial purchasers to buy up to $150 million more. Pricing was expected after market close on October 13. Net proceeds are to fund capped call transactions, additional equity investment in Barber Lake, the build out of its high performance computing pipeline, more development sites and general corporate purposes. Cipher also plans to exchange part of its 1.75% convertible notes due 2030 for stock. [Source 2] The presentation describes about $750 million of additional project equity to support the 10 year lease extension and the added cost sharing. [Source 1]

**Lease economics, as Cipher states them.** Cipher says the September amendment raises contracted revenue at Barber Lake from $3.8 billion to over $9 billion, with a 20 year base lease term. It says the tenant will repay 50% of costs above the initial $359 million threshold as additional rent over the lease, including a return on capital, and that rentalizing $187 million of costs adds about $480 million of revenue. [Source 1] [Source 3]

**Portfolio, as of September 30, 2026.** Cipher reports 907 MW of operating and contracted capacity, defined as gross MW for executed HPC leases plus operating bitcoin self mining capacity, and 700 MW of contracted gross HPC capacity. It reports $16.6 billion of contracted revenue and a 17.3 year weighted average lease term. It also lists a 1 GW Texas site called Colchis with conditional base load status in ERCOT's Batch Zero process and a new site called Apollo with target energization in 2028. [Source 1]

Capacity, as previously disclosed

The October filing does not restate Barber Lake's megawatts. Cipher's September 2025 filing described a Fluidstack lease for 168 MW of critical IT load, and its November 2025 release added 39 MW of critical IT load. [Source 4] [Source 5] Those two critical IT figures total 207 MW, our arithmetic. They should not be combined with Cipher's portfolio gross MW figures.

Buyer analysis

This is our analysis.

**Cost growth on a signed AI build is now quantified.** By Cipher's own chart, the estimate at completion is about 36% to 38% above the original budget, our arithmetic. Most of that sits with the developer, not the tenant. Buyers should expect developers to price this experience into new deals through higher rents, tighter change order clauses or larger cost sharing asks.

**The cost sharing clause is worth copying, carefully.** Cipher bears the first $359 million above budget. The tenant then pays half of further overruns through rent, with a return on capital. A tenant negotiating a large build should ask for a fixed first loss on the provider and a clear cap on any pass through.

**Hall level dates matter.** Two halls slipped one quarter while Cipher reports no rent credits incurred. Buyers should tie rent start to acceptance of each hall and write delay credits that begin at a stated date.

**This is committed capacity.** Barber Lake is leased for up to 20 years across two tenants. It is not open inventory for other buyers.

What remains unknown

The reviewed filings do not disclose rent per kW, the AI lab's identity, final note pricing, how much of the offering will go to Barber Lake, or the megawatts of each data hall. The cost chart is read from the filed presentation; Cipher's later filings may refine these ranges. The September 2025 and November 2025 critical IT figures were not restated in the October filing.

Sources

  1. Cipher Digital, Project Compass investor presentation, Form 8-K Exhibit 99.1 · Published 2026-10-13
  2. Cipher Digital, proposed convertible notes offering release, Form 8-K Exhibit 99.2 · Published 2026-10-13
  3. Cipher Digital, Barber Lake lease amendment release · Published 2026-09-25
  4. Cipher Mining, Form 8-K on the Fluidstack lease · Published 2025-09-25
  5. Cipher Mining, additional 39 MW Fluidstack agreement release · Published 2025-11-20

Related reporting

Development & Power

Serverfarm tops out ARK1 at its Clarksville, Arkansas campus, a building the company lists at 108 MW

Serverfarm has topped out ARK1, the first building at its Clarksville, Arkansas data center campus, DCD reported on October 12, 2026, citing a LinkedIn post by chief executive Avner Papouchado the previous week. [Source 1] Serverfarm's own campus page lists four buildings, ARK1 through ARK4, each with 108 MW of building capacity across 300,000 square feet on two floors, and says the first two buildings are expected to be complete by January 2028. The page does not say whether 108 MW is critical IT load or utility capacity. [Source 2]

Clarksville, Johnson County, Arkansas · Under construction. ARK1 topped out, per DCD on October 12, 2026 citing a CEO post the prior week. Serverfarm targets its first two buildings for January 2028. Not energized or available per the reviewed sources. As of October 12, 2026.
Read the analysis
Development & Power

Anne Arundel County passes a data center moratorium that stops new applications but lets filed plans and adjacent expansions proceed

The Anne Arundel County Council passed Bill 63-26 by a 7-0 vote on October 5, 2026, according to the county's legislation page. [Source 1] The amended bill text posted by the county bars the county from accepting new applications of any type for a proposed data storage center during an Effective Period that runs from the bill's effective date until the earlier of January 31, 2028 or the effective date of comprehensive rules based on a work group's recommendations. Plans filed before that period begins, and future phases of existing data centers on adjacent or adjoining properties, may proceed. [Source 2] The bill also repeals the county's personal property tax assessment reduction for qualified data storage centers. [Source 1]

Anne Arundel County, Maryland · Approved. Bill 63-26 passed by the Anne Arundel County Council, 7-0, on October 5, 2026; moratorium runs from the effective date to the earlier of January 31, 2028 or comprehensive rules. Effective date not stated on the county page. As of October 12, 2026.
Read the analysis