Galaxy says Helios I Phase II is under construction for CoreWeave, with 830 MW of approved Helios II capacity not yet leased

Galaxy Digital said on October 27, 2026 that Phase II of Helios I, its CoreWeave leased data center at the Helios campus in Dickens County, Texas, is fully financed and under construction, with data hall deliveries scheduled to begin in the second quarter of 2027. All 133 MW of Phase I critical IT load was delivered to CoreWeave by the end of the second quarter. Galaxy says it is in discussions with prospective tenants for 830 MW of approved capacity at Helios II that is not yet under lease, and that its Texas power pipeline now totals over 5.7 GW of potential capacity. [Source 1] [Source 2]

Galaxy says Helios I Phase II is under construction for CoreWeave, with 830 MW of approved Helios II capacity not yet leased
All news & analysisDeals & LeasingHelios campus, Dickens County, Texas, about 60 miles from LubbockHelios I Phase I Leased, 133 MW critical IT delivered to CoreWeave by end of Q2 2026 (company statement). Phase II Under construction (company statement), 260 MW contracted critical IT, data hall deliveries scheduled to begin Q2 2027. Phase III Leased, 133 MW critical IT, rent from 2028. Helios II: 830 MW of approved power capacity not yet leased. No capacity Available to new customers established. As of October 27, 2026.

Disclosed terms

Phase I delivered
133 MW critical IT load, delivered to CoreWeave by end of Q2 2026 [1]
Phase II status
Fully financed and under construction (company statement) [1]
Phase II timing
Data hall deliveries scheduled to begin in Q2 2027 [1]
Phase II contracted critical IT
260 MW [2]
CoreWeave leased total
526 MW critical IT across three phases (about 800 MW gross power) [2]
Unleased approved capacity
830 MW at Helios II (approved power capacity, not IT load) [1]
Phase II financing
$3.5 billion senior secured notes [1]
Texas power pipeline
Over 5.7 GW of potential capacity, assuming full approval and allocation [2]

The disclosure and our analysis

Evidence dates

Evidence: Galaxy Digital Inc. third quarter 2026 press release and investor overview, filed as exhibits to a Form 8-K on October 27, 2026. Read October 28, 2026. Capacity and status figures below are as of that filing unless noted.

What Galaxy disclosed

1. **Phase I delivered:** Galaxy says all 133 MW of critical IT load under the Helios I, Phase I lease was delivered to CoreWeave by the end of the second quarter of 2026. The third quarter was the first full quarter of revenue from that lease. [Source 1]

2. **Phase II under construction:** Galaxy says Helios I, Phase II is fully financed and under construction, with both buildings and the supporting substation on schedule and within budget, and data hall deliveries scheduled to begin in the second quarter of 2027. The investor overview lists 260 MW of contracted critical IT load for Phase II with initial rent commencement in Q2 2027. [Source 1] [Source 2]

3. **Phase III leased:** the overview lists a third CoreWeave phase of 133 MW of contracted critical IT load with initial rent commencement in 2028. Across the three phases, Galaxy says CoreWeave has leased 526 MW of critical IT capacity. [Source 2]

4. **Financing:** Galaxy says it completed a $3.5 billion offering of senior secured notes to fund construction of Helios I, Phase II. The overview gives an estimated Phase II construction cost of $4.0 billion, labeled an internal estimate, and a Phase I construction cost of $1.8 billion. [Source 1] [Source 2]

5. **Unleased capacity:** Galaxy says it continues to advance discussions with prospective tenants for the additional 830 MW of approved capacity at Helios II not yet under lease. [Source 1]

6. **Campus and pipeline:** the overview describes Helios as over 2,200 contiguous acres in Dickens County, West Texas, about 60 miles from Lubbock, with 1,630 MW of total approved power capacity, 800 MW of gross leased capacity and more than 3,600 MW of total potential power capacity. Across Texas, Galaxy says its power pipeline now totals over 5.7 GW of potential capacity at eight named sites. That total assumes full approval and allocation of identified potential capacity. [Source 2]

How to read the megawatts

Galaxy uses two different bases, and they should not be combined. The 133 MW, 260 MW and 133 MW phase figures, and the 526 MW total, are critical IT load. The 800 MW leased figure is gross power capacity: the overview says the three CoreWeave phases represent about 200 MW, 400 MW and 200 MW of gross power capacity. The 830 MW at Helios II and the 1,630 MW campus figure are approved power capacity, also a gross power basis, not critical IT load. The reviewed filing does not say how much critical IT load 830 MW of approved power would support. [Source 2]

The 5.7 GW pipeline is potential capacity. Galaxy's own categories within it range from capacity contracted under executed options or leases, to capacity that has completed development milestones, to capacity conditionally classified as Batch Zero Studied Load subject to ERCOT's ongoing audit and community impact review, to expansion opportunities. It is not approved or available capacity. [Source 2]

Disclosed economics

The overview lists annual base revenue of $315 million for Phase I and $675 million for Phase II, and says the three phases together are anticipated to generate average annual revenue of over $1 billion. Galaxy says these figures reflect anticipated annual revenue at full turnover, including annual escalators, and that each data hall is leased through a 15-year base term that begins when the final data hall is turned over. It gives a total potential contract value of over $30 billion, which assumes two five-year extension options are exercised. These are company projections. [Source 2]

Status

On our status vocabulary, as of October 27, 2026: Helios I Phase I is Leased to CoreWeave, and Galaxy says its 133 MW of critical IT load has been delivered. Phase II is Under construction according to Galaxy, with data hall deliveries scheduled to begin in Q2 2027. Phase III is Leased, with rent expected to begin in 2028. The 830 MW at Helios II is described by Galaxy as approved capacity; the reviewed filing does not name the approving authority or its conditions, and it is not leased. None of this establishes capacity Available to new customers under our definition.

Buyer analysis

This is our analysis, not Galaxy's. The useful number is the 830 MW. It is the unleased approved power at a campus that has already delivered a first phase on schedule, by Galaxy's account, which makes it a large block of approved power that a large AI tenant could still contract. It is gross power, so the IT load a tenant could use would be lower, and Galaxy has not given a delivery schedule for it.

For buyers below hyperscale size, Helios is not a colocation option: the leased phases are dedicated to CoreWeave. Its relevance is as a signal of where large AI capacity is being built in West Texas and how long delivery takes. Phase II deliveries begin about a year after Phase I finished.

We have not assigned this project to a tracked market. Dickens County lies outside the metro areas Colocation Scout covers in Texas.

What remains unknown

The reviewed filings do not give a delivery schedule, tenant or critical IT equivalent for the 830 MW at Helios II; name the authority that approved Helios power capacity or its conditions; break the 5.7 GW pipeline down by site in text, or give the locations of sites other than Helios; describe the terms of the $3.5 billion notes; or say how many data halls Phase II contains. Revenue figures are Galaxy projections and we have not derived per megawatt pricing from them.

Sources

  1. Galaxy Digital Inc., third quarter 2026 press release (Form 8-K exhibit) · Published 2026-10-27
  2. Galaxy Digital Inc., third quarter 2026 investor overview (Form 8-K Exhibit 99.2) · Published 2026-10-27

Related reporting

Deals & Leasing

Forum Edge AI signs Fireworks to a $94.4 million, 36-month GPU capacity contract at a Dallas data center, with deployment expected around year end

Forum Markets said on October 26, 2026 that Forum Edge AI, its joint venture with Edge Node, signed a definitive agreement with Fireworks for a 36-month reservation of Nvidia B300 GPU capacity at a powered data center in Dallas. The combined total contract value is about $94.4 million, covering GPU capacity and CPU management node fees over the term. The company's Form 8-K describes the deal as a reservation of 96 enterprise AI servers. Fireworks paid a prepayment deposit, and the GPUs are expected to be deployed in late December or early January. The filing gives no megawatt figure. [Source 1] [Source 2]

Dallas, Texas (facility address not disclosed) · Announced. Definitive 36-month GPU capacity agreement disclosed October 26, 2026; GPUs expected to be deployed in late December 2026 or early January 2027. Compute services contract, not a space lease. No facility capacity, energization date or availability established. As of October 27, 2026.
Read the analysis
Deals & Leasing

Alcoa agrees to sell parts of its Massena East, New York site to a data center buyer for up to $315 million, with most of the price tied to approved capacity

Alcoa said on October 15, 2026 that it entered into definitive agreements during the third quarter to sell portions of its Massena East site in New York, with potential proceeds of up to $315 million. Alcoa expects about $50 million to $65 million at closing, depending on the amount of approved data center capacity, and may receive about $60 million to $250 million more as approved capacity is expanded and commissioned over the seven years after closing. Closing is expected within six months and is subject to permitting and regulatory approvals and the conditions required to begin construction. The release does not name the buyer or give a megawatt figure. [Source 1]

Massena East site, Massena, New York · Announced. Definitive agreements to sell portions of the Massena East site signed in the third quarter of 2026 and disclosed October 15, 2026. Closing expected within six months, subject to permitting and regulatory approvals and the conditions required to begin construction. No data center permit, utility agreement, construction, energization or availability established. As of October 26, 2026.
Read the analysis
Deals & Leasing

Digi Power X gets a $200 million debt commitment for its 40 MW Columbiana, Alabama data center leased to Cerebras

Digi Power X says it has received a commitment letter from a major lending institution for $200 million of debt financing to support its 40 MW AI data center in Columbiana, Alabama, with the financing syndicated by Goldman Sachs. The company expects the financing to close within 90 days, subject to definitive documentation and other conditions, including the lender's diligence. The facility is contracted to Cerebras Systems under a 10 year agreement. [Source 1] [Source 2]

Columbiana, Shelby County, Alabama · Under construction, per the company: Phase 1 targeted for December 2026 and Phase 2 for March 2027. Leased to Cerebras under a 10 year colocation agreement signed May 4, 2026. Debt financing committed, not closed. Not available. As of October 13, 2026.