Digi Power X gets a $200 million debt commitment for its 40 MW Columbiana, Alabama data center leased to Cerebras

Digi Power X says it has received a commitment letter from a major lending institution for $200 million of debt financing to support its 40 MW AI data center in Columbiana, Alabama, with the financing syndicated by Goldman Sachs. The company expects the financing to close within 90 days, subject to definitive documentation and other conditions, including the lender's diligence. The facility is contracted to Cerebras Systems under a 10 year agreement. [Source 1] [Source 2]

Digi Power X gets a $200 million debt commitment for its 40 MW Columbiana, Alabama data center leased to Cerebras
All news & analysisDeals & LeasingColumbiana, Shelby County, AlabamaUnder construction, per the company: Phase 1 targeted for December 2026 and Phase 2 for March 2027. Leased to Cerebras under a 10 year colocation agreement signed May 4, 2026. Debt financing committed, not closed. Not available. As of October 13, 2026.

Disclosed terms

Debt commitment
$200 million commitment letter, syndicated by Goldman Sachs [1]
Expected closing
Within 90 days, subject to conditions including lender diligence [1]
Capacity
40 MW total: 15 MW of IT load in Phase 1 plus 25 MW in Phase 2 [2]
Target dates
Phase 1 December 2026; Phase 2 March 2027 [1]
Tenant contract
Cerebras, 10 year initial term valued at about $1.1 billion [2]

The disclosure and our analysis

Evidence dates

Evidence: Digi Power X release of October 13, 2026 on ACCESS Newswire; the company's May 5, 2026 release on the Cerebras agreement, filed with the SEC on May 8, 2026; its Form 10-Q for the quarter ended June 30, 2026, filed August 14, 2026.

What the company discloses

**Financing.** A commitment letter for $200 million of debt from a lender the company does not name, syndicated by Goldman Sachs. The debt is to sit at a project special purpose vehicle, with an unsecured company guarantee through project completion and other limited matters. Closing is expected within 90 days and depends on definitive documents and the lender's diligence. Proceeds are for completing the Alabama project and related costs. [Source 1]

**Construction.** The company says construction at the 40 MW campus remains on target, with Phase 1 expected in December 2026 and Phase 2 in March 2027. It reports about $135 million of cash and about $153 million of 2026 capital spending to date, and no shares sold under its at the market program in the third quarter. [Source 1]

**Tenant and capacity.** In May, Digi Power X announced a colocation and master services agreement with Cerebras Systems for the Columbiana facility. It described Phase 1 as 15 MW of IT load and Phase 2 as an incremental 25 MW, for 40 MW in total, built to Tier III standards. It valued the initial 10 year term at about $1.1 billion, and up to $2.5 billion including renewals. [Source 2] The 10-Q says the agreement was signed May 4, 2026, that Cerebras holds an exclusive license to the data center for the term, and that the company was then seeking project level financing. [Source 3]

Buyer analysis

This is our analysis.

**A commitment letter is not funded debt.** Diligence and documentation still have to clear. Until closing, the company is funding construction largely from its own cash.

**Small AI builds can now attract bank debt when a tenant is signed.** A 40 MW single tenant site with a 10 year contract is the kind of project lenders will syndicate. Buyers planning their own builds of this size should expect lenders to ask for that same contract term and tenant credit.

**This capacity is spoken for.** Cerebras has exclusive rights to the facility for the term. It is not available to other buyers.

**Watch December.** Phase 1 is 15 MW of IT load due in December 2026. Delivery against that date will show whether the schedule holds.

What remains unknown

The reviewed sources do not name the lender, or disclose the interest rate, tenor, covenants or rent per kW. They do not confirm energization or power supply terms for the Columbiana site, or the status of the company's other expansion plans.

Sources

  1. Digi Power X release, ACCESS Newswire · Published 2026-10-13
  2. Digi Power X, Cerebras agreement release, Form 8-K Exhibit 99.1 · Published 2026-05-05
  3. Digi Power X, Form 10-Q for the quarter ended June 30, 2026 · Published 2026-08-14

Related reporting

Deals & Leasing

Amazon data centers in northern Indiana and Mississippi: Blackstone trust values 647 MW at $5.0B, a 7.0% cap rate

Blackstone Digital Infrastructure Trust (NYSE: BXDC) has agreed to buy a 75.1% controlling interest in two joint ventures that will own 13 newly constructed Amazon data centers with 647 megawatts of aggregate IT power capacity, nine buildings in northern Indiana and four in Mississippi, according to a Form 8-K filed November 16, 2026. The filing puts the aggregate gross value at $5.0 billion at an initial capitalization rate of 7.0%. At closing, Amazon Data Services will lease back 100% of both campuses on triple net leases with a weighted average initial term of 12 years and a 2.75% annual rent escalator. The deal had not closed as of the filing; either side may terminate if it does not close by December 31, 2026. [Source 1] [Source 2]

Northern Indiana (greater Chicago market) and Mississippi; exact sites not disclosed · Announced as of November 16, 2026: contribution agreement signed November 11, 2026, closing pending and expected in Q4 2026. To be 100% leased to Amazon Data Services at closing. Not available to other buyers.
Read the analysis
Deals & Leasing

Gainesville, Virginia data center sells for $779.5M: Blue Owl trust buys 54 MW hyperscaler building with a $512.6M loan

Blue Owl Digital Infrastructure Trust paid approximately $779.5 million on November 10, 2026 for a 54 megawatt data center in Gainesville, Virginia that its filing says is 100% leased to a hyperscaler customer. The property is 13720 University Boulevard, according to the purchase agreement. Citibank and Wells Fargo lent approximately $512.6 million against it at one-month Term SOFR plus 2.00%. The trust disclosed the deal in a Form 8-K filed with the SEC. [Source 1] [Source 2]

13720 University Boulevard, Gainesville, Prince William County, Virginia · Leased: the 8-K says the 54 MW building is 100% leased to a hyperscaler customer as of November 10, 2026, when the sale closed.
Read the analysis
Deals & Leasing

Hut 8 will pay $100 million at closing for two West Texas data center sites from Poolin's Chapter 11 sale, with up to $80 million more tied to signing an AI or HPC lease

Hut 8 disclosed on November 4, 2026 the terms of its agreement to buy two data center sites in West Texas from affiliates of Poolin Technology through a Chapter 11 sale. Consideration is up to $180.0 million: $100.0 million payable at closing and up to $80.0 million contingent on a qualifying data center lease or transfer for AI or HPC use. The U.S. Bankruptcy Court for the District of New Jersey approved the sale on October 2, 2026. Hut 8 says the sites have up to 230 MW of utility capacity at full energization, subject to final power approvals and infrastructure development. Closing is scheduled for December 2026. [Source 1] [Source 2]

West Texas (sites not named in the reviewed Hut 8 filings) · Approved: the U.S. Bankruptcy Court for the District of New Jersey approved the sale on October 2, 2026. Closing scheduled for December 2026, subject to seller extension rights and remaining closing conditions. Not closed as of November 4, 2026.
Read the analysis