Stafford County, Virginia approves the Accokeek Center data center rezoning, with about 122 MW of Dominion service planned at full build-out

Stafford County supervisors voted 4-3 on October 7, 2026 to rezone about 121 acres for the Accokeek Center data center campus and to approve a Dominion substation permit, according to local reports. County documents describe up to 590,000 square feet in two buildings between U.S. 1 and Interstate 95. The applicant says the project is expected to need about 122 MW of electrical service at full build-out. [Source 1] [Source 3] [Source 4]

Stafford County, Virginia approves the Accokeek Center data center rezoning, with about 122 MW of Dominion service planned at full build-out
All news & analysisDevelopment & PowerWest side of Richmond Highway (U.S. 1), about 2,500 feet north of Eskimo Hill Road, Falmouth District, Stafford County, VirginiaApproved. Rezoning to M-2 and the substation conditional use permit approved 4-3 on October 7, 2026, per local reports; county minutes were not yet posted when checked on October 14, 2026. Site plan and utility approvals remain. The applicant's fiscal analysis expects the first building to operate in 2029. Not available. As of October 14, 2026.

Disclosed terms

Vote
4-3 to approve rezoning and substation permit, per local reports [4]
Site
About 120.88 acres rezoned to M-2 Heavy Industrial [1]
Building area
Up to 590,000 square feet in two buildings [1]
Electrical service
About 122 MW at full build-out, applicant estimate [3]
Applicant tax projection
$15.5 million in 2029, settling at $13.5 million a year [3]

The disclosure and our analysis

Evidence dates

Evidence: Stafford County Board of Supervisors agenda item report for the October 7, 2026 public hearing; proposed Ordinance O26-16; the applicant's impact statement dated September 14, 2026; Potomac Local and Fredericksburg Free Press reports of October 8, 2026. County documents read October 14, 2026.

What was approved

Potomac Local reports that the board approved Ordinance O26-16, the rezoning, and Resolution R26-128, the substation conditional use permit, each by 4-3. Supervisors Diggs, Evans, Guy and Allen voted yes. Vanuch, English and Yeung voted no. A motion to delay the vote failed 5-2. [Source 4] The Fredericksburg Free Press reports the same 4-3 outcome. [Source 5] We did not find adopted minutes on the county portal as of October 14.

The application, RC24155981 by Falmouth Tech LLC, rezones eight parcels totaling about 120.88 acres from agricultural, rural residential and office zoning to M-2 Heavy Industrial. It allows up to 590,000 square feet of data center and accessory uses. The plan shows two data center buildings up to two stories, an equipment yard for backup generators, and an electric substation. [Source 1] [Source 2] The applicant's principals are associated with Tradition Companies LLC. [Source 3]

County staff said the use is not consistent with the future land use plan, which designates the site for mixed commercial and residential use, but recommended approval on balance. The Planning Commission recommended approval 4-3 on August 26, 2026. [Source 1]

Power

The applicant says that, based on discussions with Dominion Energy, the project is expected to need about 122 MW of electrical service at full build-out. A single on site substation of about seven acres, and no more than eight, would serve it. The substation would be owned and operated by Dominion and not dedicated to any single customer. An existing transmission corridor runs less than half a mile from the site. The applicant says it has asked Dominion for more information on transmission facilities and voltage. [Source 3]

The 122 MW figure is an electrical service estimate by the applicant. It is not critical IT load, not energized capacity and not a utility commitment.

Water, sound and setbacks

The proffers make reuse water the only source for industrial cooling and bar potable water for that use, with air based cooling as the fallback. [Source 1] The applicant says the design uses evaporative cooling with reuse water for about 4% of the year. [Source 3] The applicant's sound study projects no more than 48 dBA at the closest property line and 44 dBA at the closest home, against a 55 dBA county limit. [Source 1]

The applicant requested modifications where it does not meet county setback and buffer standards, and proffered at least 45 acres of tree preservation and a 1,350 foot primary building setback from one neighboring parcel. [Source 1]

Economics

The applicant's fiscal analysis by Mangum Economics, dated June 4, 2026, projects gross annual tax revenue of $15.5 million in 2029, when the first building is expected to operate, settling at $13.5 million a year, and 64 operating jobs. These are the applicant's projections. [Source 3]

Buyer analysis

This is our analysis.

**Entitled land, not capacity.** The vote zones the site and permits the substation. Power delivery depends on Dominion's transmission plan, which the applicant says is not yet defined. Buyers looking at Northern Virginia overflow sites should treat 2029 as the applicant's expectation, not a delivery date.

**A smaller campus by current standards.** About 122 MW of electrical service across 590,000 square feet is modest next to gigawatt campus plans. It may suit enterprise or regional hyperscale needs south of Prince William County. No end user or operator is named.

**Local friction is real.** The 4-3 votes, setback modifications and land use inconsistency signal that later approvals may draw scrutiny.

What remains unknown

The reviewed sources do not name an operator or tenant, the transmission voltage or line routing, Dominion's in service date for the substation, critical IT load, phasing between the two buildings, or pricing.

Sources

  1. Stafford County Board of Supervisors, agenda item report, Accokeek Center rezoning (O26-16) · Published 2026-10-07
  2. Stafford County, Proposed Ordinance O26-16 · Published 2026-10-07
  3. Falmouth Tech LLC, Accokeek Center impact statement (Exhibit B to O26-16) · Published 2026-09-14
  4. Potomac Local, Stafford supervisors approve Accokeek Center data campus, 4-3 · Published 2026-10-08
  5. Fredericksburg Free Press, Stafford supervisors OK Accokeek data center campus · Published 2026-10-08

Related reporting

Development & Power

FERC accepts PJM's 50 MW large load definition and registry but rejects its plan to connect new large loads ahead of new capacity

The Federal Energy Regulatory Commission on October 9, 2026 accepted two parts of PJM Interconnection's large load proposal: a definition of Large Load as 50 MW or more of cumulative peak load at a single electrical site, and a Large Load Registry, both effective October 12, 2026. It rejected the rest, including the Interim Resource Adequacy Service that would have let new large loads connect before matching new capacity in exchange for curtailment exposure. [Source 1]

PJM Interconnection region · Approved in part. FERC accepted the Large Load definition and Large Load Registry effective October 12, 2026 and directed a PJM compliance filing within 30 days. IRAS, the new capacity designation requirement, Bring Your Own New Capacity rules and the demand curve exclusion were rejected. As of October 9, 2026.
Read the analysis
Development & Power

Soluna registers a $471.8 million AI data center building with about 112 MW of critical IT load at Project Kati II in Willacy County, Texas

A Soluna entity registered Project Kati II with the Texas Department of Licensing and Regulation on October 7, 2026. The filing describes a single story, 471,884 square foot AI data center with a critical IT load of about 112 MW, an estimated cost of $471.8 million, and estimated construction from October 8, 2026 to October 8, 2027. No tenant is assigned. [Source 1]

1392 FM 1420, Santa Monica area, Willacy County, Texas · Proposed. Registered with TDLR on October 7, 2026, status Project Registered, with estimated construction dates of October 8, 2026 to October 8, 2027. The registration does not confirm that construction has started. No tenant assigned. Not available. As of October 14, 2026.
Read the analysis
Development & Power

Cipher lifts its Barber Lake cost estimate to about $2.94 billion and plans an $850 million note sale that will help fund it

Cipher Digital now estimates that its Barber Lake data center in Colorado City, Texas will cost $2,941 million to $2,966 million to complete, against an original budget of $2,157 million, according to an investor presentation filed with the SEC on October 13, 2026. The cost estimate is dated October 6, 2026. The same filing shows two of the facility's five data halls with rent commencement moved from the fourth quarter of 2026 to the first quarter of 2027, and announces a proposed $850 million private offering of convertible notes whose proceeds will partly fund additional equity in the project. [Source 1] [Source 2]

Colorado City, Texas · Under construction. Cipher says construction is on track to meet amended delivery milestones, with rent commencement on Data Halls 1 and 2 in Q4 2026, Data Halls 3 and 4 in Q1 2027 (originally Q4 2026) and Data Hall 5 in Q1 2027. Leased to Fluidstack, with a follow-on AI lab commitment. Not available. As of September 30, 2026, with the cost estimate as of October 6, 2026.
Read the analysis