Applied Digital puts $11M to $13M per MW build cost and lease values on all six AI campuses, from Polaris Forge to Delta Forge

An Applied Digital investor presentation filed with a Form 8-K on November 25, 2026 lists, for each of its six contracted AI data center leases, the critical IT load, base term, expected base-term lease value and delivery dates. Every campus page gives the same anticipated capital cost of $11 million to $13 million per MW. The company says the six leases total 1,560 MW of contracted critical IT load and $41.13 billion of base-term lease value, which excludes pass-through power. [Source 1]

Applied Digital puts $11M to $13M per MW build cost and lease values on all six AI campuses, from Polaris Forge to Delta Forge
All news & analysisPricing & EconomicsEllendale, Harwood and Center, North Dakota; Louisiana; Alabama; one site not disclosedLeased. Six signed leases for 1,560 MW of contracted critical IT load, per Applied Digital as of November 25, 2026; 275 MW online and the rest under construction or contracted for delivery through 2028, subject to power supply agreement and regulatory approval conditions. Not available capacity.

Disclosed terms

Contracted total
1,560 MW of critical IT load; $41.13B base-term lease value; $98.36B with all renewals [1]
Anticipated capex
$11M to $13M per MW, stated on each campus page [1]
New lease
150 MW, 18 year base term, $5.40B base-term value, signed November 2026, location not disclosed [1]
Polaris Forge 1
CoreWeave, 400 MW, Ellendale, North Dakota, $10.71B base term [1]
Power basis
Contracted revenue excludes pass-through power [1]
Conditions
Contracted capacity subject to power supply agreement and regulatory approval conditions [1]
Sample financing
Up to 80% loan to cost; Macquarie preferred equity $2.25M per MW at 12.75%; terms subject to definitive documentation [1]

The disclosure and our analysis

Evidence dates

Evidence: Applied Digital investor presentation dated November 2026, Exhibit 99.1 to a Form 8-K with a report date of November 25, 2026 (accepted by the SEC November 25, filing date November 27). Applied Digital press release of November 23, 2026 on its new 150 MW lease, Exhibit 99.1 to an earlier Form 8-K. Both read November 27, 2026.

The lease table, as disclosed

The presentation lists these contracted leases. All capacity figures are critical IT load under contract, as the company labels them. Base-term values are the company's expected figures. [Source 1]

1. **Polaris Forge 1, Ellendale, North Dakota:** CoreWeave, 400 MW, 15 year base term plus three 5 year options, $10.71 billion base term ($27.40 billion with all renewals), delivery 2H 2025 to 1H 2027.

2. **Polaris Forge 2, Harwood, North Dakota:** an investment grade hyperscaler, 200 MW, 15 years plus two 5 year options, $4.82 billion ($9.18 billion), delivery 2H 2026 to 1H 2027.

3. **Polaris Forge 3, Center, North Dakota:** a high investment grade hyperscaler, 300 MW, 15 years plus three 5 year options, $7.50 billion ($18.18 billion), delivery 2H 2027 to 2H 2028.

4. **Delta Forge 1, Louisiana:** a high investment grade hyperscaler, 300 MW, 15 years plus three 5 year options, $7.50 billion ($18.18 billion), delivery mid 2027 to 1H 2028.

5. **Delta Forge 2, Alabama:** a high investment grade hyperscaler, 210 MW, 15 years plus three 5 year options, $5.20 billion ($12.72 billion), delivery 1H 2028.

6. **New 150 MW lease, location not yet disclosed:** a high investment grade hyperscaler, signed November 2026, 18 years plus three 5 year options, $5.40 billion ($12.70 billion), delivery 1H 2028 to 2H 2028.

The company also lists a 100 MW Polaris Forge 2 expansion at Harwood as in negotiation and not yet signed. Its values in the table are estimates. [Source 1]

Build cost and margins

Each campus page in the presentation states anticipated capital expenditure of $11 million to $13 million per MW. Expected stabilized site NOI margins are 88% at Polaris Forge 1, 86% at Polaris Forge 2 and 85% at the other four sites, each plus or minus 3 points. The company calls these forward looking and not guidance. [Source 1]

The presentation defines rent as each lease's base-term value divided by its term. On that definition, Applied Digital's own figures imply average annual base-term rent of about $714 million at Polaris Forge 1, $500 million each at Polaris Forge 3 and Delta Forge 1, and $300 million on the new 150 MW lease. The company footnotes that contracted revenue figures exclude amounts attributable to pass-through power. [Source 1]

A sample capitalization for a 100 MW project, built on the same $11 million to $13 million per MW range, shows up to 80% loan to cost project debt ($8.75 million to $10.40 million per MW), Macquarie preferred equity of $2.25 million per MW carrying a 12.75% dividend, and Applied Digital common equity of $0 to $0.35 million per MW. The company says these terms remain subject to negotiation of additional definitive documentation. [Source 1]

Status by campus

The presentation reports 275 MW of critical IT online today and 1.285 GW under construction, which it describes as contracted and delivering through 2028. At Polaris Forge 1, it labels Building 1 (100 MW) and Building 2 (150 MW) as energized and Building 3 (150 MW) as under construction. It says contracted capacity is subject to power supply agreement and regulatory approval conditions, and that the new 150 MW lease is subject to conditions including power supply agreement approvals. [Source 1] The November 23 release says delivery of the new lease is anticipated to begin in the first half of calendar 2028, subject to development milestones, utility arrangements and regulatory approvals. [Source 2]

Under this site's status terms, the six sites are leased capacity, not available capacity. None of the reviewed figures describe space offered to new customers.

Buyer analysis

This is our analysis, not a company statement.

**A rare published build cost.** Most developers do not publish a per MW construction figure. Applied Digital puts $11 million to $13 million per MW on every campus page and uses it as the basis for its sample financing. For buyers weighing a build to suit or powered shell deal, it is one disclosed reference point for large AI halls. It is the company's estimate, not an audited cost, and the presentation does not say whether land or utility work is included.

**Lease value excludes power.** The company says its contracted revenue excludes pass-through power. That makes the figures closer to a rent comparison than a total cost of occupancy. Our pricing benchmarks page tracks implied rent from large AI leases using this kind of disclosure.

**The newest lease is longer.** The November 150 MW lease runs 18 years, against about 15 years for the other five. Its average annual base rent of about $2.0 million per MW, on the company's rent definition, is above the roughly $1.61 million to $1.79 million per MW for the other five leases. That is our arithmetic on company figures, and averages across a term can hide escalators. It fits the company's own statement in its November 23 release that the new lease has improved commercial terms over its prior leases, including higher pricing. [Source 2]

**Supply signal.** All 1,560 MW is contracted to named or unnamed single tenants and due by 2028. Buyers looking for North Dakota, Louisiana or Alabama capacity should not read these campuses as open inventory.

What remains unknown

The reviewed filings do not disclose the hyperscaler tenants other than CoreWeave, the location of the new 150 MW lease, rent per kW or escalators for any lease, whether the $11 million to $13 million per MW includes land, power infrastructure or tenant equipment, the conditions in the pending power supply agreements, or the status of the Polaris Forge 2 expansion talks beyond not yet signed.

Sources

  1. Applied Digital, investor presentation (Form 8-K Exhibit 99.1) · Published 2026-11-25
  2. Applied Digital, new 150 MW lease announcement (Form 8-K Exhibit 99.1) · Published 2026-11-23

Explore the market

Related reporting

Pricing & Economics

Columbiana, Alabama data center rent: Cerebras to pay Digi Power X $195 per kW a month for 15 MW

Cerebras Systems will pay Digi Power X a fixed, take-or-pay colocation fee of $195 per kW per month, escalating 3% a year, for the purpose-built Tier III data center in Columbiana, Alabama, according to Digi Power X's Form 10-Q for the quarter ended September 30, 2026, filed with the SEC on November 13, 2026. The 10-Q puts that at about $2.925 million a month for Phase 1, which is 15 MW of IT load. The company's November 13 results release says Phase 1 fees should average about $40 million a year over the ten-year term, about $402 million in total, with tenant access expected December 15, 2026 and billing from January 2027. The other 25 MW, Phase 2, is conditioned on the company securing adequate financing. [Source 1] [Source 2]

Columbiana, Shelby County, Alabama · Under construction (Phase 1) and leased to Cerebras, with the lease not yet commenced, as of September 30, 2026 per the 10-Q. Phase 2 (25 MW) is conditional on financing. Not available to other buyers.
Read the analysis
Pricing & Economics

Tampa Electric data center tariff: $18.98 per kW generation charge and $2M per MW security in proposed LLCS-1

Tampa Electric's proposed large load tariff for Florida data centers of 50 MW or more would bill an $18.98 per kW Incremental Generation Charge, a $4.78 per kW demand charge and other per kW charges against contracted demand, under a contract of at least 20 years. Customers without an investment grade credit rating would post security of $2.0 million per MW of contracted capacity. The company filed the tariff with the Florida Public Service Commission on September 30, 2026 in Docket No. 20260146-EI. On November 3, 2026 the Commission suspended it pending review and set a hearing for March 30 to April 2, 2027. [Source 1] [Source 3] [Source 4]

Tampa Electric service territory: Hillsborough County and parts of Polk, Pinellas and Pasco counties, Florida · Proposed: filed September 30, 2026; suspended by the Florida PSC on November 3, 2026 pending review; hearing set for March 30 to April 2, 2027. No rate is approved.
Read the analysis
Pricing & Economics

Spartanburg County data center agreements: $9M and $12.6M community payments for 65 and 50 IT MW projects

Spartanburg County, South Carolina put three data center development agreements to second reading at a special called council meeting on November 3, 2026. The draft agreements in the county's meeting packet commit 300 Jones Road Associates LLC to $9 million in community benefit payments over six installments for a data center of up to 65 IT MW at 430 Jones Road, and AIB CLT1 LLC to at least $12.6 million over a 12-year initial term for a 50 IT MW data center at 389 Tyger River Industrial Drive. A third draft, for Numara LLC and Valara Holdings LLC at 4000 S Pine Street, describes a 457 MW project with at least $2.76 billion of investment and lists no community benefit payment. [Source 1]

Spartanburg County, South Carolina (430 Jones Road; 389 Tyger River Industrial Drive, Moore; 4000 S Pine Street, Spartanburg) · Proposed: second reading and public hearings on the November 3, 2026 Spartanburg County Council agenda; final reading pending as of that packet. No construction, energization or availability is established for the new buildings.
Read the analysis