The disclosure and our analysis
Evidence dates
Evidence: Applied Digital investor presentation dated November 2026, Exhibit 99.1 to a Form 8-K with a report date of November 25, 2026 (accepted by the SEC November 25, filing date November 27). Applied Digital press release of November 23, 2026 on its new 150 MW lease, Exhibit 99.1 to an earlier Form 8-K. Both read November 27, 2026.
The lease table, as disclosed
The presentation lists these contracted leases. All capacity figures are critical IT load under contract, as the company labels them. Base-term values are the company's expected figures. [Source 1]
1. **Polaris Forge 1, Ellendale, North Dakota:** CoreWeave, 400 MW, 15 year base term plus three 5 year options, $10.71 billion base term ($27.40 billion with all renewals), delivery 2H 2025 to 1H 2027.
2. **Polaris Forge 2, Harwood, North Dakota:** an investment grade hyperscaler, 200 MW, 15 years plus two 5 year options, $4.82 billion ($9.18 billion), delivery 2H 2026 to 1H 2027.
3. **Polaris Forge 3, Center, North Dakota:** a high investment grade hyperscaler, 300 MW, 15 years plus three 5 year options, $7.50 billion ($18.18 billion), delivery 2H 2027 to 2H 2028.
4. **Delta Forge 1, Louisiana:** a high investment grade hyperscaler, 300 MW, 15 years plus three 5 year options, $7.50 billion ($18.18 billion), delivery mid 2027 to 1H 2028.
5. **Delta Forge 2, Alabama:** a high investment grade hyperscaler, 210 MW, 15 years plus three 5 year options, $5.20 billion ($12.72 billion), delivery 1H 2028.
6. **New 150 MW lease, location not yet disclosed:** a high investment grade hyperscaler, signed November 2026, 18 years plus three 5 year options, $5.40 billion ($12.70 billion), delivery 1H 2028 to 2H 2028.
The company also lists a 100 MW Polaris Forge 2 expansion at Harwood as in negotiation and not yet signed. Its values in the table are estimates. [Source 1]
Build cost and margins
Each campus page in the presentation states anticipated capital expenditure of $11 million to $13 million per MW. Expected stabilized site NOI margins are 88% at Polaris Forge 1, 86% at Polaris Forge 2 and 85% at the other four sites, each plus or minus 3 points. The company calls these forward looking and not guidance. [Source 1]
The presentation defines rent as each lease's base-term value divided by its term. On that definition, Applied Digital's own figures imply average annual base-term rent of about $714 million at Polaris Forge 1, $500 million each at Polaris Forge 3 and Delta Forge 1, and $300 million on the new 150 MW lease. The company footnotes that contracted revenue figures exclude amounts attributable to pass-through power. [Source 1]
A sample capitalization for a 100 MW project, built on the same $11 million to $13 million per MW range, shows up to 80% loan to cost project debt ($8.75 million to $10.40 million per MW), Macquarie preferred equity of $2.25 million per MW carrying a 12.75% dividend, and Applied Digital common equity of $0 to $0.35 million per MW. The company says these terms remain subject to negotiation of additional definitive documentation. [Source 1]
Status by campus
The presentation reports 275 MW of critical IT online today and 1.285 GW under construction, which it describes as contracted and delivering through 2028. At Polaris Forge 1, it labels Building 1 (100 MW) and Building 2 (150 MW) as energized and Building 3 (150 MW) as under construction. It says contracted capacity is subject to power supply agreement and regulatory approval conditions, and that the new 150 MW lease is subject to conditions including power supply agreement approvals. [Source 1] The November 23 release says delivery of the new lease is anticipated to begin in the first half of calendar 2028, subject to development milestones, utility arrangements and regulatory approvals. [Source 2]
Under this site's status terms, the six sites are leased capacity, not available capacity. None of the reviewed figures describe space offered to new customers.
Buyer analysis
This is our analysis, not a company statement.
**A rare published build cost.** Most developers do not publish a per MW construction figure. Applied Digital puts $11 million to $13 million per MW on every campus page and uses it as the basis for its sample financing. For buyers weighing a build to suit or powered shell deal, it is one disclosed reference point for large AI halls. It is the company's estimate, not an audited cost, and the presentation does not say whether land or utility work is included.
**Lease value excludes power.** The company says its contracted revenue excludes pass-through power. That makes the figures closer to a rent comparison than a total cost of occupancy. Our pricing benchmarks page tracks implied rent from large AI leases using this kind of disclosure.
**The newest lease is longer.** The November 150 MW lease runs 18 years, against about 15 years for the other five. Its average annual base rent of about $2.0 million per MW, on the company's rent definition, is above the roughly $1.61 million to $1.79 million per MW for the other five leases. That is our arithmetic on company figures, and averages across a term can hide escalators. It fits the company's own statement in its November 23 release that the new lease has improved commercial terms over its prior leases, including higher pricing. [Source 2]
**Supply signal.** All 1,560 MW is contracted to named or unnamed single tenants and due by 2028. Buyers looking for North Dakota, Louisiana or Alabama capacity should not read these campuses as open inventory.