Colocation Scout / News & Analysis

Tampa Electric data center tariff: $18.98 per kW generation charge and $2M per MW security in proposed LLCS-1

Tampa Electric's proposed large load tariff for Florida data centers of 50 MW or more would bill an $18.98 per kW Incremental Generation Charge, a $4.78 per kW demand charge and other per kW charges against contracted demand, under a contract of at least 20 years. Customers without an investment grade credit rating would post security of $2.0 million per MW of contracted capacity. The company filed the tariff with the Florida Public Service Commission on September 30, 2026 in Docket No. 20260146-EI. On November 3, 2026 the Commission suspended it pending review and set a hearing for March 30 to April 2, 2027. [Source 1] [Source 3] [Source 4]

Tampa Electric data center tariff: $18.98 per kW generation charge and $2M per MW security in proposed LLCS-1
All news & analysisPricing & EconomicsTampa Electric service territory: Hillsborough County and parts of Polk, Pinellas and Pasco counties, FloridaProposed: filed September 30, 2026; suspended by the Florida PSC on November 3, 2026 pending review; hearing set for March 30 to April 2, 2027. No rate is approved.

Disclosed terms

Incremental Generation Charge
$18.98 per kW, fixed for the LLCC Initial Term [1]
Demand Charge
$4.78 per kW on the greater of contracted, billing or 90% ratchet demand [1]
Transmission charge
$2.33 per kW of Contracted Capacity Demand, subject to true-up [1]
Security
$2.0 million per MW of contracted capacity; 50% for investment grade customers [1]
Term
At least 20 years from the in-service date [1]
LLCS-1 cap
1 GW, closing when full or on January 1, 2031 [1]
Hearing
March 30 to April 2, 2027 [4]

The disclosure and our analysis

Evidence dates

Evidence: Tampa Electric Company petition and proposed tariff sheets filed September 30, 2026; Florida PSC staff recommendation dated October 22, 2026; Commission vote sheet and Order No. PSC-2026-0399-PCO-EI, both dated November 3, 2026. Reviewed November 11, 2026.

What Tampa Electric filed

Florida's large load customer law, Section 366.043, Florida Statutes, required public utilities to file compliant tariffs by October 1, 2026. It defines a large load customer as one with an anticipated monthly peak load of 50 MW or more at a single location, and bars splitting a load into smaller connections to avoid the class. Tampa Electric filed its petition on September 30, 2026. It proposes two rate schedules, LLCS-1 and LLCS-2, a standard Large Load Customer Contract (LLCC) and related tariff changes. [Source 1]

LLCS-1 would cover the first gigawatt of large load demand. Tampa Electric says its rates recover the cost of 600 MW of energy storage, 600 MW of new generating capacity from its planned modernization of Big Bend Unit 4, and transmission to connect them, plus a share of average system costs. The schedule closes when the 1 GW cap is fully subscribed or on January 1, 2031, whichever comes first. Demand above the first gigawatt would go to LLCS-2, which uses a formula to recover the cost of the generation, storage and transmission built for those customers. The filing publishes no fixed LLCS-2 rates. Service is at transmission voltage of 69 kV or higher. [Source 1]

The LLCS-1 rates as filed

The proposed LLCS-1 tariff (Original Sheet Nos. 6.855 and 6.860) lists these charges. [Source 1]

Basic Service Charge: $126.72 per day. Demand Charge: $4.78 per kW, applied to the greatest of Contracted Capacity Demand, Billing Demand, or 90% of the highest Billing Demand in the previous 11 months. Energy Charge: 0.223 cents per kWh.

Incremental Generation Charge: $18.98 per kW, on the same greatest-of basis. The tariff says this rate stays unchanged during the LLCC Initial Term. Incremental Transmission Charge: $2.33 per kW of Contracted Capacity Demand, an indicative rate subject to true-up to actual costs.

Incremental Fuel Transportation Charge: none in 2028 through 2030, $2.09 per kW in 2031 and $6.16 per kW in 2032 through 2047, subject to true-up. Incremental PPA Charge: $17.10 per kW in 2028, $11.13 in 2029, $7.72 in 2030, $3.74 in 2031, $1.60 in 2032 and none from 2033, subject to true-up.

The minimum monthly bill is the sum of the basic service, demand, incremental generation, transmission, fuel transportation and PPA charges, plus other generally applicable charges. Usage charges apply on top. The basic service, demand and energy charges are marked as subject to change in later rate proceedings. Billing Demand is the highest 30-minute kW demand in the billing period. A load ramp period of up to five years can be agreed in the contract. [Source 1]

Contract term, security and exit

The term of service is at least 20 years from the in-service date, including the ramp period. Customers must give three years' notice to end service at the end of the term. Leaving early, or failing to give that notice, triggers a Termination Fee equal to the net present value of the incremental generation, transmission, fuel transportation and PPA charges for the rest of the initial term. [Source 1]

Security under the LLCC is $2.0 million multiplied by the MW of Contracted Capacity Demand for a customer without an investment grade credit rating. A customer with an investment grade rating, or one using a protective insurance product, posts 50% of that amount, or $1.0 million per MW. Before service, a customer must also pay for system studies, accept their results, pay any contribution in aid of construction, sign an affidavit of ownership under the law's foreign entity rule, and execute the LLCC. The tariff also covers entities that meter into a colocation or similar agreement at a single location that meets the 50 MW threshold. [Source 1]

Status

As of November 3, 2026: Proposed. Commission staff recommended on October 22 that the tariffs be suspended so staff could review the petition, citing an 11/30/26 60-day suspension date. On November 3 the Commission approved that recommendation, with no dissent recorded on the vote sheet, and kept the docket open. Order No. PSC-2026-0399-PCO-EI, issued the same day, sets a hearing for March 30 to April 2, 2027. Intervenor testimony is due January 28, 2027, Tampa Electric's rebuttal February 15, 2027, and the prehearing conference is March 16, 2027. No rate in this article is approved. [Source 2] [Source 3] [Source 4]

Buyer and operator analysis

This is our analysis, from the filed rates only. Adding the per kW charges that make up the minimum bill (demand, incremental generation, transmission, fuel transportation and PPA) gives about $43.19 per kW a month in 2028, $33.85 in 2032 and $32.25 from 2033. At 1 MW of contracted demand, that is about $32,250 to $43,190 a month, or roughly $387,000 to $518,000 a year, before the basic service charge, energy, fuel and clause charges and any true-ups. Most of it is owed whether or not the load shows up, because the charges bill against contracted demand or a 90% ratchet.

The security term is the bigger up-front number. For a 100 MW project without an investment grade rating, $2.0 million per MW means $200 million of security before service. That cost sits with the developer, and in a colocation deal it can flow into rent, a tenant guarantee or a credit requirement.

For colocation buyers in the Tampa Bay area, the practical point is timing. The tariff is not in effect, a hearing is set for spring 2027, and the LLCS-1 rates rest on new generation and storage that Tampa Electric plans to build. A provider quoting new capacity above 50 MW in Tampa Electric's territory should be able to say which schedule the site expects, whether it has signed an LLCC, and who is posting the security. A smaller deployment inside an existing facility is not itself a large load customer; the 50 MW test applies to the load at a single location.

What remains unknown

The reviewed filings do not disclose any specific large load customer, site or MW request in Tampa Electric's territory, any LLCS-2 rate, the fuel and clause charges that would apply on top of the LLCS-1 base rates, or the total cost of the Big Bend Unit 4 modernization and the 600 MW of storage. We did not review the three sets of direct testimony filed with the petition, any intervenor filings, or the comparable tariffs filed by other Florida utilities.

Sources

  1. Tampa Electric Company, Petition for Approval of Large Load Customer Tariffs with proposed tariff sheets, Florida PSC Docket No. 20260146-EI (Document No. 07096-2026) · Published 2026-09-30
  2. Florida PSC staff recommendation to suspend the proposed tariffs, Docket No. 20260146-EI (Document No. 07470-2026) · Published 2026-10-22
  3. Florida PSC vote sheet, November 3, 2026 Commission conference, Item 9 (Document No. 07695-2026) · Published 2026-11-03
  4. Florida PSC Order No. PSC-2026-0399-PCO-EI establishing procedure (Document No. 07681-2026) · Published 2026-11-03

Related reporting

Pricing & Economics

Spartanburg County data center agreements: $9M and $12.6M community payments for 65 and 50 IT MW projects

Spartanburg County, South Carolina put three data center development agreements to second reading at a special called council meeting on November 3, 2026. The draft agreements in the county's meeting packet commit 300 Jones Road Associates LLC to $9 million in community benefit payments over six installments for a data center of up to 65 IT MW at 430 Jones Road, and AIB CLT1 LLC to at least $12.6 million over a 12-year initial term for a 50 IT MW data center at 389 Tyger River Industrial Drive. A third draft, for Numara LLC and Valara Holdings LLC at 4000 S Pine Street, describes a 457 MW project with at least $2.76 billion of investment and lists no community benefit payment. [Source 1]

Spartanburg County, South Carolina (430 Jones Road; 389 Tyger River Industrial Drive, Moore; 4000 S Pine Street, Spartanburg) · Proposed: second reading and public hearings on the November 3, 2026 Spartanburg County Council agenda; final reading pending as of that packet. No construction, energization or availability is established for the new buildings.
Read the analysis
Pricing & Economics

Riot's Corsicana lease: $130 per kW a month for 910 MW of powered land, and its 10-Q names Anthropic as the tenant

Riot Platforms disclosed in its quarterly report filed November 4, 2026 that the tenant at its Corsicana Facility in Navarro County, Texas will pay base rent of $130.0 per kilowatt of critical IT load capacity per month for each delivered block, escalating 3% a year, under a triple net powered land lease for 910 MW of critical IT load capacity. The 10-Q names the tenant as Anthropic PBC; Riot's earnings release calls it a leading Frontier AI Lab. The lease was signed October 28, 2026 and became effective November 4, 2026. Delivery is targeted in three phases from June 28, 2027 to July 30, 2028. [Source 1] [Source 2]

Corsicana Facility, Navarro County, Texas · Leased: lease signed October 28, 2026 and effective November 4, 2026 for 910 MW of critical IT load capacity. Delivery targeted in phases from June 28, 2027 to July 30, 2028.
Read the analysis
Pricing & Economics

HIVE's BUZZ HPC borrows about $129 million at 9% fixed to buy 2,303 Nvidia GB200 GPUs for a Cohere contract in Canada

HIVE Digital Technologies said on October 27, 2026 that a BUZZ HPC subsidiary entered into a fixed rate credit facility of about $129 million from an unnamed institutional lender. The loan carries 9.0% interest over a three year amortizing term at about 80% loan to cost, and funds a $165 million cluster of 2,303 Nvidia GB200 GPUs contracted to Cohere under a three year, $225 million contract. HIVE says the compute stays in Canada and GPU delivery is expected toward the end of Q4 2026. [Source 1]

Canada (facility not disclosed) · Financing agreement entered into (per HIVE, October 27, 2026); Cohere contract signed June 2026. GPU delivery expected toward the end of Q4 2026. No facility, megawatt or availability status disclosed.
Read the analysis