The disclosure and our analysis
Evidence dates
Evidence: Digi Power X Form 10-Q for the quarter ended September 30, 2026, filed November 13, 2026; Digi Power X third quarter 2026 results release, filed as Exhibit 99.1 to a Form 8-K on November 13, 2026; Digi Power X Form 10-Q for the quarter ended June 30, 2026, filed August 14, 2026. Reviewed November 16, 2026.
What the filings disclose
Note 20 of the third quarter 10-Q describes the ten-year data center colocation and master services agreement Digi Power X signed with Cerebras Systems Inc. on May 4, 2026. Digi Power X is obligated to construct, commission and operate a purpose-built Tier III facility in Columbiana, Alabama delivering up to 40 MW of IT load, made up of Phase 1 at 15 MW and a conditional Phase 2 at 25 MW. In exchange, the 10-Q says, it will receive a fixed, take-or-pay colocation fee of $195.00 per kW per month, approximately $2,925,000 a month for Phase 1 and $4,875,000 a month for Phase 2, escalating 3.0% annually over the term. [Source 1]
The same rate and terms appear in the company's 10-Q for the quarter ended June 30, 2026. We did not report the rate when we covered the project's $200 million debt commitment on October 13, 2026, and we found no news coverage that reports it. [Source 3]
The 10-Q says the full deployment of Phase 2, which would bring the campus to 40 MW of IT load, is conditioned on the company securing adequate financing. [Source 1]
Money already paid
During the third quarter Digi Power X received $12,000,000 from Cerebras as the Phase 1 non-recurring charge, which the 10-Q describes as consideration for the design, procurement and construction of the Phase 1 infrastructure. The charge is refundable in certain circumstances before Phase 1 commences, including termination for the company's material breach or failure to achieve Ready for Service by the final outside delivery date, limited to amounts not yet applied to completed work. The company records it as unearned lease revenue and a current liability. [Source 1]
The 10-Q accounts for the agreement as a lease: Cerebras obtains exclusive use of the facility, Digi Power X keeps ownership of the land and building, and the lease commences when each phase is made available for Cerebras's use. As of September 30, 2026, Phase 1 was under construction, the lease had not commenced and no lease revenue had been recognized. [Source 1]
Schedule and contract value, per the company
The November 13 results release says Phase 1 fees should average approximately $40 million a year over the ten-year term, an approximate total of $402 million. Subject to various conditions, Phase 2 would add approximately $58.5 million in annual fees, for a total contract value of approximately $1.07 billion if both phases commence. An option for an additional term could raise the total potential value to approximately $2.5 billion. [Source 2]
The company says it expects to give Cerebras access to the Phase 1 facility on December 15, 2026, start commissioning the liquid cooling and power systems then, and begin Phase 1 billing in January 2027. It says Phase 2 work is underway and it is targeting tenant access for Phase 2 in March 2027. These are company targets. [Source 2]
The release also says the company's proposed $200 million credit facility syndicated by Goldman Sachs is currently expected to close in the fourth quarter of 2026, subject to definitive documentation and various conditions. [Source 2]
Status
As of September 30, 2026: Under construction, per the 10-Q, for Phase 1. Leased: the agreement gives Cerebras exclusive use of the facility for the term, but the lease had not commenced. Phase 2 is proposed and conditional on financing. None of this capacity is available to other buyers. [Source 1]
Buyer and operator analysis
This is our analysis, from the filed figures only. $195 per kW per month is $2.34 million per MW of IT load per year in the first year. With a 3% annual escalator, the monthly rate would reach about $254 per kW in year ten. Applying that escalator to the 10-Q's monthly figures gives about $402 million for Phase 1 and about $1.07 billion for both phases over ten years, which matches the company's release.
The rate is a take-or-pay fee measured per kW of IT load for a single tenant, liquid cooled AI facility. The reviewed filings do not say whether electricity is billed inside the fee or passed through separately, so it should not be compared directly with an all-in retail colocation quote that bundles power. Buyers comparing it with their own quotes should first confirm how each proposal bills energy, and whether it charges for committed or used capacity.
The structure is also worth noting. The tenant prepaid $12 million toward construction, refundable if the operator misses Ready for Service. Phase 2 is contracted but conditional on the operator's financing. That pairing of a signed rate with conditional delivery is a reason to ask any developer offering future AI capacity which phases are funded today.